Studying the Reasons for Delay and Cost Overrun in Construction Projects: The Case of Iran

Main Article Content

Hamed Samarghandi
Seyed Mohammad Moosavi Tabatabaei
Pouria Taabayan
Ahmad Mir Hashemi
Keith Willoughby

Abstract

Undesirable delays in construction projects impose excessive costs and precipitate exacerbated durations. Investigating Iran, a developing Middle Eastern country, this paper focuses on the reasons for construction project delays. We conducted several interviews with owners, contractors, consultants, industry experts and regulatory bodies to accurately ascertain specific delay factors. Based on the results of our industry surveys, a statistical model was developed to quantitatively determine each delay factor's importance in construction project management. The statistical model categorises the delay factors under four major classes and determines the most significant delay factors in each class: owner defects, contractor defects, consultant defects and law, regulation and other general defects. The most significant delay factors in the owner defects category are lack of attention to inflation and inefficient budgeting schedule. In the contractor defects category, the most significant delay factors are inaccurate budgeting and resource planning, weak cash flow and inaccurate pricing and bidding. As for the consultant defects delay factors such as inaccurate first draft and inaccuracies in technical documents have the most contribution to the defects. On the other hand, outdated standard mandatory items in cost lists, outdated mandatory terms in contracts and weak governmental budgeting are the most important delay factors in the law, regulation and other general defects. Moreover, regression models demonstrate that a significant difference exists between the initial and final project duration and cost. According to the models, the average delay per year is 5.9 months and the overall cost overrun is 15.4%. Our findings can be useful in at least two ways: first, resolving the root causes of particularly important delay factors would significantly streamline project performance and second, the regression models could assist project managers and companies with revising initial timelines and estimated costs. This study does not consider all types of construction projects in Iran: the scope is limited to certain types of private and publicly funded projects as will be described. The data for this study has been gathered through a detailed questionnaire survey.

Article Details

How to Cite
Hamed Samarghandi, Seyed Mohammad Moosavi Tabatabaei, Pouria Taabayan, Ahmad Mir Hashemi, and Keith Willoughby. 2016. “Studying the Reasons for Delay and Cost Overrun in Construction Projects: The Case of Iran”. Journal of Construction in Developing Countries 21 (1): 51-84. https://doi.org/10.21315/Jcdc2016.21.1.4.
Section
Articles

References

Abd El-Razek, M., Bassioni, H. and Mobarak, A. (2008). Causes of delay in building construction projects in Egypt. Journal of Construction Engineering and Management, 134(11): 831–841. doi: 10.1061/(ASCE)0733- 9364(2008)134:11(831).

Abdul Kadir, M., Lee, W., Jaafar, M., Sapuan, S. and Ali, A. (2005). Factors affecting construction labour productivity for Malaysian residential projects. Structural Survey, 23(1): 42–54. doi: 10.1108/02630800510586907.

Aibinu, A.A. and Jagboro, G.O. (2002). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management, 20(8): 593–599. doi: 10.1016/S0263-7863(02)00028-5.

Alaghbari, W.E., M. Razali, A.K., Salim, A. and Ernawati, M.K. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2): 192–206. doi: 10.1108/09699980710731308.

Al-Khalil, M.I. and Al-Ghafly, M.A. (1999). Delay in public utility projects in Saudi Arabia. International Journal of Project Management, 17(2): 101–106. doi: 10.1016/S0263-7863(98)00020-9.

Al-Momani, A.H. (2000). Construction delay: A quantitative analysis. International Journal of Project Management, 18(1): 51–59. doi: 10.1016/S0263-7863(98)00060-X.

Alrashed, I., Phillips, M. and Kantamaneni, K. (2014). Implementing multidimensional CAD models to reduce the project cost estimations gap between the financial ministry and other government ministries in Saudi Arabia. Journal of Advanced Management Science, 2(3): 170–175. doi: 10.12720/joams.2.3.170-175.

Alzober, W. and Yaakub, A.R. (2014). Integrated model for MCDM: Selection contractor in Malaysian construction industry. Applied Mechanics and Materials, 548–549: 1587–1595. doi: 10.4028/www.scientific.net/AMM.548-549.1587.

Arditi, D., Akan, G.T. and Gurdamar, S. (1985). Reasons for delays in public projects in Turkey. Construction Management and Economics, 3(2): 171–181. doi: 10.1080/01446198500000013.

Ashworth, A. (2013). Cost Studies of Buildings. Abingdon, UK: Routledge.

Assaf, S.A. and Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4): 349–357. doi: 10.1016/j.ijproman.2005.11.010.

Augustine, I.E., Ajayi, J.R., Ade B.A. and Edwin, A.A. (2013). Assessment of risk management practices in Nigerian construction industry: Toward establishing risk management index. International Journal of Pure and Applied Sciences and Technology, 16(2): 20–31.

Baldwin, J.R., Manthei, J.M., Rothbart, H. and Harris, R.B. (1971). Causes of delay in the construction industry. Journal of the Construction Engineering Division, 97(2): 177–187.

Barber, H.M., Jr. and El-Adaway, I.H. (2014). Economic performance assessment for construction industry in the southeastern United States. Journal of Management in Engineering, 31(2): 05014014. doi: 10.1061/(ASCE)ME.1943- 5479.0000272.

Bramble, B.B. and Callahan, M.T. (2012). Construction Delay Claims. New York: Aspen Publishers.

Chan, D.W. and Kumaraswamy, M.M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15(1): 55–63. doi: 10.1016/S0263-7863(96)00039-7.

Chan, W.M.D. and Kumaraswamy, M.M. (2002). Compressing construction durations: Lessons learned from Hong Kong building projects. International Journal of Project Management, 20(1): 23–35. doi: 10.1016/S0263-7863(00)00032-6.

Cheng, M.Y. and Kang, S.T. (2012). Integrated fuzzy preference relations with decision utilities for construction contractor selection. Journal of the Chinese Institute of Engineers, 35(8): 1051–1063. doi: 10.1080/02533839.2012.708510.

Doane, D.P. and Seward, L.E. (2015). Applied Statistics in Business and Economics. New York: McGraw-Hill Education.

Doloi, H, Sawhney, A. and Iyer, K.C. (2012). Structural equation model for investigating factors affecting delay in Indian construction projects. Construction Management and Economics, 30(10): 869–884. doi: 10.1080/01446193.2012.717705.

Faridi, A.S. and El-Sayegh, S.M. (2006). Significant factors causing delay in the UAE construction industry. Construction Management Economics, 24(11): 67–76. doi: 10.1080/01446190600827033.

Fong, N., Wong, L. and Wong, L. (2006). Fire services installation related contributors of construction delays. Building and Environment, 41(2): 211– 222. doi: 10.1016/j.buildenv.2005.01.004.

Freund, J. (1991). Mathematical Statistics. Upper Saddle River, NJ: Prentice Hall PTR.

Frimpong, Y., Oluwoye, J. and Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries: Ghana as a case study. International Journal of Project Management, 21(5): 321–326. doi: 10.1016/S0263-7863(02)00055-8.

Fugar, F.D.K. and Agyakwah-Baah, A.B. (2010). Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building, 10(1/2): 103–116. doi: 10.5130/ajceb.v10i1/2.1592.

Ghahramanzadeh, M. (2013). Managing risk of construction projects: A case study of Iran. PhD diss. University of East London.

Gündüz, M., Nielsen, Y. and Özdemir, M. (2013). Quantification of delay factors using the relative importance index method for construction projects in Turkey. Journal of Management in Engineering, 29(2): 133–139. doi: 10.1061/(ASCE)ME.1943-5479.0000129.

Hamzah, N., Khoiry, M., Arshad, I., Badaruzzaman, W. and Tawil, N. (2012). Identification of the causes of construction delay in Malaysia. World Academy of Science, Engineering and Technology, 72: 614–619. Hinton, P.R. (2004). SPSS Explained. Abingdon, UK: Routledge.

Huang, X. (2011). An analysis of the selection of project contractor in the construction management process. International Journal of Business and Management, 6(3): 184–189. doi: 10.5539/ijbm.v6n3p184.

Iyer, K.C., Chaphalkar, N.B. and Joshi, G.A. (2008) Understanding time delay disputes in construction contracts. International Journal of Project Management, 26(2): 174–184. doi: 10.1016/j.ijproman.2007.05.002.

Jaapar, A., Zawawi, M., Bari, N.A.A. and Ahmad, N. (2012). Value management in the Malaysian construction industry: Addressing a theory and practice gap. Procedia-Social and Behavioral Sciences, 35: 757–763. doi: 10.1016/j.sbspro.2012.02.146.

Jalal, M.P. (2008). Studying FIDIC type contracts (in Persian). Paper presented at the Fourth International Project Management Conference. Tehran, Iran.

Kaliba, C., Muya, M. and Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management, 27(5): 522–531. doi: 10.1016/j.ijproman.2008.07.003.

Kaming, P.F., Olomolaiye, P.O., Holt, G.D. and Harris, F.C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15(1): 83–94. doi: 10.1080/014461997373132.

Kang, B.G., Eng, V.S., Goh, B.H., Choong, W.K. and Yeong, T.W. (2014). Investigation into the current practice of cost estimating and the introduction of a standard price book in the Malaysia construction industry. Advanced Materials Research, 838: 3109–3114.

Kometa, S.T., Olomolaiye, P.O. and Harris, F.C. (1994). Attributes of UK construction clients influencing project consultants' performance. Construction Management and Economics, 12(5): 433–443. doi: 10.1080/01446199400000053.

Koushki, P., Al?Rashid, K. and Kartam, N. (2005). Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics, 23(3): 285–294. doi: 10.1080/0144619042000326710.

Le-Hoai, L., Dai Lee, Y. and Lee, J.Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering, 12(6): 367–377. doi: 10.1007/s12205-008-0367-7.

Lin, G., Shen, G.Q., Sun, M. and Kelly, J. (2011). Identification of key performance indicators for measuring the performance of value management studies in construction. Journal of Construction Engineering and Management, 137(9): 698–706. doi: 10.1061/(ASCE)CO.1943-7862.0000348.

Loo, S.C. and Abdul-Rahman, H. (2012). Malaysian contractors in gulf construction: A preliminary study on financial and economic risks. International Journal of Engineering and Technology, 4(4): 975–4024.

Luo, X., Shen, G.Q., Fan, S. and Xue, X. (2011). A group decision support system for implementing value management methodology in construction briefing. International Journal of Project Management, 29(8): 1003–1017. doi: 10.1016/j.ijproman.2010.11.003.

Miller, I. and Miller, M. (2012). John E. Freund's Mathematical Statistics with Applications. Upper Saddle River, NJ: Pearson.

Miller, I., Freund, J.E. and Miller, M. (2014). John E. Freund's Mathematical Statistics with Applications. Upper Saddle River, NJ: Pearson Education Ltd.

Odeh, A.M. and Battaineh, H.T. (2002). Causes of construction delay: Traditional contracts. International Journal of Project Management, 20(1): 67–73. doi: 10.1016/S0263-7863(00)00037-5.

Ponz-Tienda, J.L., Pellicer, E. and Yepes, V. (2012). Complete fuzzy scheduling and fuzzy earned value management in construction projects. Journal of Zhejiang University Science A, 13(1): 56–68. doi: 10.1631/jzus.A1100160.

Pourrostam, T. and Ismail, A. (2012). Causes and effects of delay in Iranian construction projects. International Journal of Engineering and Technology, 4(5): 598. doi: 10.7763/IJET.2012.V4.441.

Ross, S.M. (2014). Introduction to Probability Models. Cambridge, MA: Academic Press.

Saleh, A.H.T., Abdelnaser, O. and Abdul, H.K.P. (2009). Causes of delay in construction industry in Libya. The International Conference on Economics and Administration, Faculty of Administration and Business (ICEA-FAA). University of Bucharest, Romania, 14–15 November. Bucharest: Faculty of Administration and Business (ICEA-FAA), University of Bucharest.

Sambasivan, M. and Soon, Y.W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5): 517–526. doi: 10.1016/j.ijproman.2006.11.007.

Shakeri, E. and Ghorbani, A. (2005). Studying the contractual reasons of construction contractors' claims (in Persian). Paper presented at the First Conference on Expansion of Contractual Order in Iranian Industrial Structure.

Tehran, Iran. Shebob, A., Dawood, N., Shah, R.K. and Xu, Q. (2012). Comparative study of delay factors in Libyan and the UK construction industry. Engineering, Construction and Architectural Management, 19(6): 688–712. doi: 10.1108/09699981211277577.

Statistical Center of Iran. (n.d.). Homepage. Available at: http://www.amar.org.ir/Default.aspx?tabid=133.

Sweis, G., Sweis, R., Abu Hammad, A. and Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6): 665–674. doi: 10.1016/j.ijproman.2007.09.009.

The Central Bank of Iran. (n.d.). Homepage. Available at: http://www.cbi.ir/default_en.aspx.

Toor, S.U.R. and Ogunlana, S.O. (2008). Problems causing delays in major construction projects in Thailand. Construction Management and Economics, 26(4): 395–408. doi: 10.1080/01446190801905406.

Vogt, W.P. and Johnson, B. (2011). Dictionary of Statistics and Methodology: A Nontechnical Guide for the Social Sciences. Thousand Oaks, CA: Sage Publications.

Zaneldin, E.K. (2006). Construction claims in United Arab Emirates: Types, causes, and frequency. International Journal of Project Management, 24(5): 453– 459. doi: 10.1016/j.ijproman.2006.02.006.

Zavadskas, E.K., Vilutiene, T., Turskis, Z. and Tamosaitiene, J. (2010). Contractor selection for construction works by applying SAW?G and TOPSIS grey techniques. Journal of Business Economics and Management, 11(1): 34–55. doi: 10.3846/jbem.2010.03