Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman
Main Article Content
Abstract
While the concepts of planning and scheduling seem to be adequately discussed in the project management literature, relatively few examples of factors specifically affecting the performance of planning and scheduling are to be found. The study reported in this paper investigated a set of factors identified as enablers and barriers to successful project planning and scheduling of construction projects in Oman. The study adopted a questionnaire-based survey to measure the impact of each factor. The data were analysed using the relative impact (or importance) index (RII). On the basis of RII rankings, the results revealed that the identified enablers and barriers were all considered significant. This could imply that all of the factors should be considered equally from the perspective of project planning and scheduling, including schedule control. In addition, the results suggest that project managers should pay attention to the more significant barriers to mitigate their potential impacts on planning and scheduling. Recommendations for mitigating those barriers are presented. The study provides useful insights into the impact of various factors on the planning and scheduling performance of construction projects in Oman and how improvement might be achieved.
Article Details

This work is licensed under a Creative Commons Attribution 4.0 International License.
References
Abeyasinghe, M.C.L., Greenwood, D.J. and Johansen, D.E. (2001). An efficient method for scheduling construction projects with resource constraints. International Journal of Project Management, 19(1): 29–45. http://dx.doi.org/10.1016/S0263-7863(00)00024-7.
Ahadzie, D.K., Proverbs, D.G. and Olomolaiye, P.O. (2008). Critical success criteria for mass house building projects in developing countries. International Journal of Project Management, 26(6): 675–687. http://dx.doi.org/10.1016/j.ijproman.2007.09.006.
Ahsan, K. and Gunawan, I. (2010). Analysis of cost and schedule performance of international development projects. International Journal of Project Management, 28(1): 68–78. http://dx.doi.org/10.1016/j.ijproman.2009.03.005.
Ahuja, V. and Thiruvengadam, V. (2004). Project scheduling and monitoring: Current research status. Construction Innovation: Information, Process, Management, 4(1): 19–31.
Al Tabtabai, H.M. (2002). Causes for delays in construction projects in Kuwait. Engineering Journal of Qatar University, 15: 19–37.
Al?Kharashi, A. and Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1): 3–23. http://dx.doi.org/10.1080/01446190802541457.
Alnuaimi, A.S. and Al Mohsin, M.A. (2013). Causes of delay in completion of construction projects in Oman. Paper presented at the International Conference on Innovations in Engineering and Technology (ICIET). Bangkok, Thailand, 25–26 December, 267–270. http://dx.doi.org/10.15242/IIE.E1213590.
Alnuaimi, A.S., Taha, R.A., Al Mohsin, M. and Al-Harthi, A.S. (2009). Causes, effects, benefits, and remedies of change orders on public construction projects in Oman. Journal of Construction Engineering and Management, 136(5): 615– 622. http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000154.
Alsakini, W., Wikström, K. and Kiiras, J. (2004). Proactive schedule management of industrial turnkey projects in developing countries. International Journal of Project Management, 22(1): 75–85. http://dx.doi.org/10.1016/S0263-7863(03)00006-1
Assaf, S.A. and Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4): 349–357. http://dx.doi.org/10.1016/j.ijproman.2005.11.010.
Ballal, T., Elhag, T. and Ambusaidy, M.S. (2007). Project risk management in Oman: A survey of risk practices in the construction industry. CIB World Congress: Construction for Development. Cape Town: Construction Industry Development Board (CIDB) and Council for Scientific and Industrial Research (CSIR), 549–557.
Bates D.W. and Gawande A.A. (2003). Improving Safety with Information Technology. New England Journal of Medicine, 348: 2526–2534. http://dx.doi.org/10.1056/NEJMsa020847.
Bevilacqua, M., Ciarapica, F.E. and Giacchetta, G. (2009). Critical chain and risk analysis applied to high-risk industry maintenance: A case study. International Journal of Project Management, 27(4): 419–432. http://dx.doi.org/10.1016/j.ijproman.2008.06.006.
Bokor, O., Kocsis, T. and Szenik, G. (2011). New tools in project scheduling: Challenges of the construction project planning. Budownictwo i In?ynieria ?rodowiska, 3(2): 214–221.
Burke, R. (2003). Project Management: Planning and Control Techniques. Hoboken, NJ: John Wiley and Sons.
Cegarra, J. and van Wezel, W. (2011). A comparison of task analysis methods for planning and scheduling. In C.F. Jan, W. Toni and R.W. John (eds). Behavioral Operations in Planning and Scheduling. Berlin: Springer, 323–338.
Cerveny, J.F. and Galup, S.D. (2002). Critical chain project management: Holistic solution aligning quantitative and qualitative project management methods. Production and Inventory Management Journal, 43(3/4): 55–64.
Chitkara, K. (2002). Construction Project Management: Planning, Scheduling and Controlling. New Delhi: Tata McGraw-Hill Education.
Colman, A.M., Morris, C.E. and Preston, C.C. (1997). Comparing rating scales of different lengths: Equivalence of scores from 5-point and 7-point scales. Psychological Reports, 80(2): 355–362. http://dx.doi.org/10.2466/pr0.1997.80.2.355.
David, H., Steven, T., Dianne, H. and James, B. (2013). Construction and projects in Oman: Overview. Construction and Projects Multi-Jurisdictional Guide 2013/14. Washington DC: Association of Coporate Counsel (ACC). Available at: http://www.dentons.com/~/media/PDFs/Insights/2013/September/Omanpdf.pdf (Accessed on 10 October 2014).
Davis, K. (2014). Different stakeholder groups and their perceptions of project success. International Journal of Project Management, 32(2): 189–201. http://dx.doi.org/10.1016/j.ijproman.2013.02.006.
De Snoo, C., Van Wezel, W. and Jorna, R.J. (2011). An empirical investigation of scheduling performance criteria. Journal of Operations Management, 29(3): 181–193. http://dx.doi.org/10.1016/j.jom.2010.12.006.
Elmaghraby, S.E.E., Herroelen, W.S. and Leus, R. (2003). Note on the paper "Resource-constrained project management using enhanced theory of constraint" by Wei et al. International Journal of Project Management, 21(4): 301–305. http://dx.doi.org/10.1016/S0263-7863(02)00085-6
Faridi, A.S. and El?Sayegh, S.M. (2006). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11): 1167–1176. http://dx.doi.org/10.1080/01446190600827033.
Fellows, R.F. and Liu, A.M. (2009). Research Methods for Construction. Chichester, UK: Wiley-Blackwell.
Field, A.P. (2005). Kendall's coefficient of concordance. In Encyclopedia of Statistics in Behavioral Science. New Jersey: John Wiley and Sons. http://dx.doi.org/10.1002/0470013192.bsa327.
Ghosh, S. and Jintanapakanont, J. (2004). Identifying and assessing the critical risk factors in an underground rail project in Thailand: A factor analysis approach. International Journal of Project Management, 22(8): 633–643. http://dx.doi.org/10.1016/j.ijproman.2004.05.004.
González, P., González, V., Molenaar, K. and Orozco, F. (2014). Analysis of causes of delay and time performance in construction projects. Journal of Construction Engineering and Management, 140(1): 1–9. http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000721.
Hair, J.F. (2009). Multivariate Data Analysis. Upper Saddle River, NJ: Prentice Hall. http://dx.doi.org/10.1016/j.csda.2008.11.030.
Halpin, D. and Riggs, L. (1992). Planning and Analysis of Construction Operations. New York: Wiley-Interscience.
Hameed, A. (2005). Resource-driven scheduling: Barriers to implementation. PhD diss. University Teknologi Malaysia.
Hameri, A.P. and Heikkilä, J. (2002). Improving efficiency: Time-critical interfacing of project tasks. International Journal of Project Management, 20(2): 143– 153. http://dx.doi.org/10.1016/S0263-7863(00)00044-2
Hartmann, S. and Briskorn, D. (2010). A survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of Operational Research, 207(1): 1–14. http://dx.doi.org/10.1016/j.ejor.2009.11.005.
Hoel, S.G.T. (1999). Quantifying buffers for project schedules. Production and Inventory Management Journal, 40(2): 43–47.
Holt, G.D. (2014). Asking questions, analysing answers: Relative importance revisited. Construction Innovation: Information, Process, Management, 14(1): 2–16.
Hussein, B.A. and Klakegg, O.J. (2014). Measuring the impact of risk factors associated with project success criteria in early phase. Procedia Engineering: Social and Behavioral Sciences, 119: 711–718.
Hwang, B.G., Zhao, X. and Ng, S.Y. (2013). Identifying the critical factors affecting schedule performance of public housing projects. Habitat International, 38(1): 214–221. http://dx.doi.org/10.1016/j.habitatint.2012.06.008.
Hyväri, I. (2006). Project management effectiveness in project-oriented business organizations. International Journal of Project Management, 24(3): 216–225. http://dx.doi.org/10.1016/j.ijproman.2005.09.001.
Ibironke, O.T., Oladinrin, T.O., Adeniyi, O. and Eboreime, I.V. (2013). Analysis of nonexcusable delay factors influencing contractors' performance in Lagos State, Nigeria. Journal of Construction in Developing Countries, 18(1): 53–72.
Iyer, K. and Jha, K. (2006). Critical factors affecting schedule performance: Evidence from Indian construction projects. Journal of Construction Engineering and Management, 132(8): 871–881. http://dx.doi.org/10.1061/(ASCE)0733-9364(2006)132:8(871)
Johny, J. (2012). The effect of design and construction integration on project delays in Bahrain. MSc diss. University of Portsmouth.
Joshi, V. and Ghosal, S. (2013). Scenario of foreign direct investment with special reference to Sultanate of Oman. International Journal of Research and Development in Technology and Management Sciences, 20(8): 1–9.
Jurf, N.A. and Beheiry, S. (2012). Factors affecting cost and schedule in Qatar's residential compounds projects. International Journal of Engineering Management and Economics, 3(1): 117–134. http://dx.doi.org/10.1504/IJEME.2012.048608.
Kazaz, A., Manisali, E. and Ulubeyli, S. (2008). Effect of basic motivational factors on construction workforce productivity in Turkey. Journal of Civil Engineering and Management, 14(2): 95–106. http://dx.doi.org/10.3846/1392-3730.2008.14.4.
Kerzner, H. (2009). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 10th Ed. Hoboken, NJ: John Wiley and Sons.
Kerzner, H.R. (2013). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 11th Ed. Hoboken, NJ: John Wiley and Sons.
Luu, V.T., Kim, S.Y., Nguyen, V.T. and Ogunlana, S.O. (2009). Quantifying schedule risk in construction projects using Bayesian belief networks. International Journal of Project Management, 27(1): 39–50. http://dx.doi.org/10.1016/j.ijproman.2008.03.003.
Mokhtari, H., Baradaran K.R. and Salmasnia, A. (2011). Time-cost tradeoff analysis in project management: An ant system approach. IEEE Transactions on Engineering Management, 58(1): 36–43. http://dx.doi.org/10.1109/TEM.2010.2058859.
Moneke, U. (2012). Evaluation of factors affecting work schedule effectiveness in the management of construction projects. Interdisciplinary Journal of Contemporary Research in Business, 3(10): 297–309.
Mubarak, S.A. (2010). Construction Project Scheduling and Control. Hoboken, NJ: John Wiley and Sons. http://dx.doi.org/10.1002/9780470912171.
Mulholland, B. and Christian, J. (1999). Risk assessment in construction schedules. Journal of Construction Engineering and Management, 125(1): 8–15 http://dx.doi.org/10.1061/(ASCE)0733-9364(1999)125:1(8).
Müller, R. and Turner, R. (2010). Leadership competency profiles of successful project managers. International Journal of Project Management, 28(5): 437–448. http://dx.doi.org/10.1016/j.ijproman.2009.09.003.
Nah, F.F.N., Lau, J.L.S. and Kuang, J. (2001). Critical factors for successful enterprise systems. Business Process Management Journal, 7(3): 285–296. http://dx.doi.org/10.1108/14637150110392782.
Nepal, M.P., Park, M. and Son, B. (2006). Effects of schedule pressure on construction performance. Journal of Construction Engineering and Management, 132(2): 182–188. http://dx.doi.org/10.1061/(ASCE)0733-9364(2006)132:2(182).
Noronha, S.J. and Sarma, V.V.S. (1991). Knowledge-based approaches for scheduling problems: A survey. IEEE Transactions on Knowledge and Data Engineering, 3(2): 160–171. http://dx.doi.org/10.1109/69.87996.
Odusami, K., Iyagba, R. and Omirin, M. (2003). The relationship between project leadership, team composition and construction project performance in Nigeria. International Journal of Project Management, 21(7): 519–527. http://dx.doi.org/10.1016/S0263-7863(02)00059-5.
Oxford Business Group. (2013). Oman's Construction Sector Building Up. London: Oxford Business Group. Available at: https://www.oxfordbusinessgroup.com/oman-2013.
Oxford Business Group. (2014). Oman's construction sector building up. Available at: https://www.oxfordbusinessgroup.com/oman-2014/construction.
Rivera, F.A. and Duran, A. (2004). Critical clouds and critical sets in resourceconstrained projects. International Journal of Project Management, 22(6): 489–497. http://dx.doi.org/10.1016/j.ijproman.2003.11.004.
Schatteman, D., Herroelen, W., Van de Vonder, S. and Boone, A. (2008). Methodology for integrated risk management and proactive scheduling of construction projects. Journal of Construction Engineering and Management, 134(11): 885–893. http://dx.doi.org/10.1061/(ASCE)0733-9364(2008)134:11(885).
Shash, A.A. and Ahcom, J. (2006). Organizational aspects of planning and scheduling subsystem. Journal of Construction Research, 7(1/2): 247–265. http://dx.doi.org/10.1142/S160994510600058X.
Siegel, S. and Castellan, N.J. (1988). Nonparametric Statistics for the Behavioral Sciences. New York: McGraw-Hill Book Company.
Steyn, H. (2002). Project management applications of the theory of constraints beyond critical chain scheduling. International Journal of Project Management, 20(1): 75–80. http://dx.doi.org/10.1016/S0263-7863(00)00054-5.
Taroun, A. (2014). Towards a better modelling and assessment of construction risk: Insights from a literature review. International Journal of Project Management, 32(1): 101–115. http://dx.doi.org/10.1016/j.ijproman.2013.03.004.
Thornley, G. (2013). Critical Path Analysis in Practice: Collected Papers on Project Control. London: Routledge Publications.
Trietsch, D. (2005). Why a critical path by any other name would smell less sweet. Project Management Journal, 36(1): 27–39.
Voth, G.W. (2009). Classification of schedule management barriers through concept mapping. MSc diss. Air Force Institute of Technology.
Weaver, P. (2009) Scheduling in the age of complexity. Proceedings: The Sixth Annual PMI College of Scheduling Conference. Boston, MA, 17–20 May. Available at: http://www.mosaicprojects.com.au/Resources_Papers_089.html (Accessed on Feburary 2011).
White, D. and Fortune, J. (2002). Current practice in project management: An empirical study. International Journal of Project Management, 20(1): 1–11. http://dx.doi.org/10.1016/S0263-7863(00)00029-6
Yang, J. (2007). How the critical chain scheduling method is working for construction. Cost Engineering, 49(4): 25–32.
Yang, L.R., Huang, C.F. and Wu, K.S. (2011). The association among project manager's leadership style, teamwork and project success. International Journal of Project Management, 29(3): 258–267. http://dx.doi.org/10.1016/j.ijproman.2010.03.006.
Zhou, J., Love, P., Wang, X., Teo, K. and Irani, Z. (2013). A review of methods and algorithms for optimizing construction scheduling. Journal of the Operational Research Society, 64: 1091–1105. http://dx.doi.org/10.1057/jors.2012.174.