Factors Affecting Contractors' Bidding Decisions for Construction Projects in Nigeria

Main Article Content

Opeyemi Olanrewaju Oyeyipo
Koleola Tunwase Odusami
Rapheal Abiodun Ojelabi
Adedeji Olushola Afolabi

Abstract

Bidding is the most common means by which contractors obtain work. The construction industry accounts for approximately three quarters of the Gross Domestic Product (GDP) in the country. It is generally believed that wrong bidding practice is a major contributor to the construction industry's inefficiency. This means that any improvement in bidding has the potential to enhance the industry's performance, improve the quality of the decision-making process and assist in achieving the strategic objective of contracting organisations. In an effort to uncover the main factors that characterise the bid/no bid decision of contracting organisations, a study to evaluate the factors that affect contractors' decisions to bid for a project and to evaluate the importance of the identified factors to decision makers was conducted. A structured questionnaire was used as the principal instrument for collecting data from respondents. A total sample of 100 was drawn from these collections of construction contractors from Lagos state. Fifty were completed and returned, representing a 50% response rate. Frequency, percentage, mean score and Spearman's correlation were used in analysing data collected for the study. The results indicate that the financial capability of clients, availability of capital and availability of material are the most important factors that contractors consider when making a bid/no bid decision. The study also reveals that competition (number and identity of competitors) does not have significant influence on contractors' bidding decisions. The study recommends that contractors should also build their reputations in the construction industry by acquiring technical competencies and capabilities as these qualities have become important considerations in assessing contractors' competiveness, as well as being key indicators of successful tendering in construction projects.

Article Details

How to Cite
Opeyemi Olanrewaju Oyeyipo, Koleola Tunwase Odusami, Rapheal Abiodun Ojelabi, and Adedeji Olushola Afolabi. 2016. “Factors Affecting Contractors’ Bidding Decisions for Construction Projects in Nigeria”. Journal of Construction in Developing Countries 21 (2): 21–35. https://doi.org/10.21315/jcdc2016.21.2.2.
Section
Articles

References

Banki, M.T., Esmaeeli, B. and Ravanshadnia, M. (2008). The assessment of bidding strategy of Iranian construction firm. International Journal of Management Science and Engineering Management, 4(2): 153–160.

Dozzi, S.P., AbouRizk, S.M. and Schroeder, S.L. (1996). Utility-theory model for bid mark-up decisions. ASCE Journal of Construction Engineering and Management, 122(2): 119–124. http://dx.doi.org/10.1061/(ASCE)0733-9364(1996)122:2(119)

Dulaimi, M.F. and Shan, H.G. (2002). The factors influencing bid mark-up decisions of large and medium-size contractors in Singapore. Construction Management and Economics, 20(7): 601–610. http://dx.doi.org/10.1080/01446190210159890.

Egemen, M. and Mohamed, A.N. (2007). A framework for contractors to reach strategically correct bid/no bid and mark-up size decisions. Building and Environment, 42(3): 1373–1385. http://dx.doi.org/10.1016/j.buildenv.2005.11.016.

El-Mashaleh, M.S., Al-Jundi, A., Mattar, S., Ali, R.A. and Al-Hammad, J. (2014). Understanding key bidding factors considered by top Jordan contractors. Jordan Journal of Civil Engineering, 8(4): 455–464.

Fayek, A., Ghoshal, I. and AbouRizk, S. (1999). A survey of bidding practices of Canadian civil engineering construction contractors. Canadian Journal of Civil Engineering, 26(1): 13–25. http://dx.doi.org/10.1139/l98-038.

Harris, F. and McCaffer, R. (2000). Modern Construction Management. 5th Ed. Oxford: Blackwell Science.

Hassanein, A.G. (1996). Factors affecting the bidding behaviour of contractors in Egypt. Building Research and Information, 24(4): 228–236. http://dx.doi.org/10.1080/09613219608727534.

Hatush, Z. and Skitmore, M. (1997). Evaluating contractor's prequalification data: selection criteria and project success factors. Construction Management and Economics, 15(2): 129–147. http://dx.doi.org/10.1080/01446199700000002.

Lifson, M.W. and Shaifer, E.F. (1982). Decision and Risk Analysis for Construction Management. New York: John Wiley and Sons.

Lowe, D.J. and Parvar, J. (2004). A logistic regression approach to modeling the contractor's decision to bid. Construction Management and Economics, 22(6): 643–653. http://dx.doi.org/10.1080/01446190310001649056.

Odusote, O.O. and Fellows, R.F. (1992). An examination of the importance of resource considerations when contractors make project selection decisions. Construction Management and Economics, 10(2): 137–151. http://dx.doi.org/10.1080/01446199200000013.

Oo, B.L., Drew, D.S. and Lo, H.P. (2008). A comparison of contractors' decision to bid behaviour according to different market environments. International Journal of Project Management, 26(4): 439–447. http://dx.doi.org/10.1016/j.ijproman.2007.06.001.

Shash, A.A. (1993). Factors considered in tendering decisions by top UK contractors. Construction Management and Economics, 11(2): 111–118. http://dx.doi.org/10.1080/01446199300000004.

Wanous, M., Boussabaine, A.H. and Lewis, J. (2000). To bid or not to bid: A parametric solution. Construction Management and Economics, 18(4): 457– 466. http://dx.doi.org/10.1080/01446190050024879.

Wanous, M., Boussabaine, H.A. and Lewis, J. (2003). A neural network bid/no bid model: The case for contractors in Syria. Construction Management and Economics, 21(7): 737–744. http://dx.doi.org/10.1080/0144619032000093323.

Wong, C.H., Holt, G.D. and Cooper, P.A. (2000). Lowest price or value? Investigation of UK construction clients' tender selection process. Construction Management and Economics, 18(7): 767–774. http://dx.doi.org/10.1080/014461900433050.