Critical Barriers to Implementing Risk Assessment and Management Practices (RAMP) in the Iranian Construction Sector

Main Article Content

Nicholas Chileshe
M. Reza Hosseini
Jacqueline Jepson

Abstract

Late completions, frequent work stoppages and cost overruns are common issues in developing countries. Effective risk management (RM) can be utilised to address these common construction issues; however, the uptake of risk management within the Iranian construction industry, as in many developing nations, is limited. This study explored why RM is not used through a questionnaire survey of 90 professionals in the Iranian construction industry. The findings show that professionals in the industry perceive the three greatest barriers to be (1) a lack of experience among practitioners, (2) the lack of available risk management consultants and (3) a lack of knowledge and necessary skills. In contrast, the professionals believed that the least common barriers were tight scheduling of projects and costs associated with risk management implementation. No significant differences were found between the perceptions of the three sub-groups—contractors, consultants and clients (private and public)—regarding the barriers to risk management. The study contributes to the field by providing insights into what causes the low level of implementation of risk assessment and management practices (RAMP) in Iran. It is anticipated that this type of study will result in raising the level of awareness about practices designed to improve risk management in developing countries. The study advocates a number of solutions for addressing the identified barriers. These solutions can be implemented or used as guidelines by construction companies and policy makers in other developing countries confronting similar problems.

Article Details

How to Cite
Nicholas Chileshe, M. Reza Hosseini, and Jacqueline Jepson. 2016. “Critical Barriers to Implementing Risk Assessment and Management Practices (RAMP) in the Iranian Construction Sector”. Journal of Construction in Developing Countries 21 (2): 81–112. https://doi.org/10.21315/jcdc2016.21.2.5.
Section
Articles

References

Abbott, M.L. (2011). Understanding Educational Statistics Using Microsoft Excel® and SPSS®. Hoboken, NJ: John Wiley and Sons.

Ahmed, A., Kayis, B. and Amornsawadwatana, S. (2007). A review of techniques for risk management in projects. Benchmarking: An International Journal, 14(1): 22–36. http://dx.doi.org/10.1108/14635770710730919.

Akhavan, P., Zahedi, M.R. and Hosein, S.H. (2014). A conceptual framework to address barriers to knowledge management in project-based organizations. Education, Business and Society: Contemporary Middle Eastern Issues, 7(2/3): 98–119. http://dx.doi.org/10.1108/EBS-10-2013-0040.

Alavifar, A.M. and Motamedi, S. (2014). Identification, evaluation and classification of time delay risks of construction projects in Iran. Paper presented at the International Conference on Industrial Engineering and Operations Management. Bali, Indonesia, 7–9 January.

Amaratunga, D., Baldry, D., Sarshar, M. and Newton, R. (2002). Quantitative and qualitative research in the built environment: Application of "mixed" research approach. Work Study, 51(1): 17–31. http://dx.doi.org/10.1108/00438020210415488.

Arashpour, M., Shabanikia, M. and Arashpour, M. (2012). Valuing the contribution of knowledge-oriented workers to projects: A merit based approach in the construction industry. Australasian Journal of Construction Economics and Building, 12(4): 1–12. http://dx.doi.org/10.5130/ajceb.v12i4.2724.

Banaitien?, N., Banaitis, A. and Norkus, A. (2011). Risk management in projects: Peculiarities of Lithuanian construction companies. International Journal of Strategic Property Management, 15(1): 60–73. http://dx.doi.org/10.3846/1648715X.2011.568675.

Bowers, J. and Khorakian, A. (2014). Integrating risk management in the innovation project. European Journal of Innovation Management, 17(1): 25–40. http://dx.doi.org/10.1108/EJIM-01-2013-0010.

Cagliano, A.C., Grimaldi, S. and Rafele, C. (2015). Choosing project risk management techniques: A theoretical framework. Journal of Risk Research, 18(2): 232–248. http://dx.doi.org/10.1080/13669877.2014.896398.

Carless, S.A. and De Paola, C. (2000). The measurement of cohesion in work teams. Small Group Research, 31(1): 71–88. http://dx.doi.org/10.1177/104649640003100104.

Carter, A. and Chinyio, E. (2012). Effectiveness of risk management: Barriers and solutions. International Journal of Project Organisation and Management, 4(4): 368–378. http://dx.doi.org/10.1504/IJPOM.2012.050330.

Cheung, E., Chan, A.P.C., Lam, P.T.I., Chan, D.W.M. and Ke, Y. (2012). A comparative study of critical success factors for public private partnerships (PPP) between Mainland China and the Hong Kong Special Administrative Region. Facilities, 30(13/14): 647–666. http://dx.doi.org/10.1108/02632771211273132.

Chileshe, N. and Kikwasi, G.J. (2014). Critical success factors for implementation of risk assessment and management practices within the Tanzanian construction industry. Engineering, Construction and Architectural Management, 21(3): 291–319. http://dx.doi.org/10.1108/ECAM-01-2013-0001.

Chileshe, N. and Kikwasi, G.J. (2013). Perception of barriers to implementing risk assessment and management practices by construction professionals in Tanzania. In S.D. Smith and D.D. Ahiaga-Dagbui (eds.). 29th Annual ARCOM Conference. Reading, UK, 2–4 September. Reading, UK: Association of Researchers in Construction Management, 1137–1146.

Chileshe, N. and Yirenkyi-Fianko, A.B. (2012). An evaluation of risk factors impacting construction projects in Ghana. Journal of Engineering, Design and Technology, 10(3): 306–329. http://dx.doi.org/10.1108/17260531211274693.

Choudhry, R. and Iqbal, K. (2013). Identification of risk management system in construction industry in Pakistan. Journal of Management in Engineering, 29(1): 42–49. http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000122.

Cronk, B.C. (2012). How to Use SPSS: A Step-By-Step Guide to Analysis and Interpretation. 7th Ed. Glendale, CA: Pyrczak Pub.

Deng, X., Low, S., Li, Q. and Zhao, X. (2014). Developing competitive advantages in political risk management for international construction enterprises. Journal of Construction Engineering and Management, 140(9): 04014040-1– 10.

Ebrahimnejad, S., Mousavi, S.M. and Seyrafianpour, H. (2010). Risk identification and assessment for build-operate-transfer projects: A fuzzy multi attribute decision making model. Expert Systems with Applications, 37(1): 575–586. http://dx.doi.org/10.1016/j.eswa.2009.05.037.

Fallahi, A. (2008). Bam earthquake reconstruction assessment: An interdisciplinary analytical study on the risk preparedness of Bam and its cultural landscape: A World Heritage property in danger. Structural Survey, 26(5): 387–399. http://dx.doi.org/10.1108/02630800810922739.

Fereidouni, H.G. (2011). Factors contributing to the fluctuations in residential construction in Iran. Australasian Journal of Construction Economics and Building, 11(4): 77–86. http://dx.doi.org/10.5130/ajceb.v11i4.2295.

Forza, C. (2002). Survey research in operations management: A process-based perspective. International Journal of Operations and Production Management, 22(2): 152–194. http://dx.doi.org/10.1108/01443570210414310.

Ghahramanzadeh, M. (2013). Managing risk of construction projects a case study of Iran. PhD diss. University of East London.

Ghoddousi, P. and Hosseini, M.R. (2012). A survey of the factors affecting the productivity of construction projects in Iran. Technological and Economic Development of Economy, 18(1): 99–116. http://dx.doi.org/10.3846/20294913.2012.661203.

Ghoddousi, P., Bahrami, N., Chileshe, N. and Hosseini, M.R. (2014). Mapping sitebased construction workers' motivation: Expectancy theory approach. Australasian Journal of Construction Economics and Building, 14(1): 60–77. http://dx.doi.org/10.5130/ajceb.v14i1.3712.

Ghoddousi, P., Poorafshar, O., Chileshe, N. and Hosseini, M.R. (2015). Labour productivity in Iranian construction projects. International Journal of Productivity and Performance Management, 64(6): 811–830. http://dx.doi.org/10.1108/IJPPM-10-2013-0169.

Goh, C.S. and Abdul Rahman, H. (2013). The identification and management of major risks in the Malaysian construction industry. Journal of Construction in Developing Countries, 18(1): 19–32.

Hair Jr, J.F., Hult, G.T.M., Ringle, C. and Sarstedt, M. (2014). A Primer on Partial Least Squares Structural Equation Modeling (PLS-SEM). Thousand Oaks, CA: Sage Publications.

Hair, J.F., Sarstedt, M., Pieper, T.M. and Ringle, C.M. (2012). The use of partial least squares structural equation modeling in strategic management research: A review of past practices and recommendations for future applications. Long Range Planning, 45(5–6): 320–340. http://dx.doi.org/10.1016/j.lrp.2012.09.008.

Harner, M.M. (2010). Barriers to effective risk management. Seton Hall Law Review, 40(4): 1323–1366.

Hwang, B.-G., Zhao, X. and Toh, L.P. (2014). Risk management in small construction projects in Singapore: Status, barriers and impact. International Journal of Project Management, 32(1): 116–124. http://dx.doi.org/10.1016/j.ijproman.2013.01.007.

Ifpinfo.com. (2014). Thriving construction industry in Iran. Ifpinfo.com: Middle East Business News and Events. Beirut: IFP Group. Available at: http://www.ifpinfo.com/Iran-NewsArticle-5250#.Vb1U3_mIV1B [Accessed on 2 August 2015].

Ikediashi, D.I., Ogunlana, S.O. and Alotaibi, A. (2014). Analysis of project failure factors for infrastructure projects in Saudi Arabia: A multivariate approach. Journal of Construction in Developing Countries, 19(1): 35–52.

International Monetary Fund (IMF). (2014). 2014 Article IV Consultation: Staff Report; Press Release; and Statement by the Executive Director for the Islamic Republic of Iran. IMF Country Report No. 14/93. Washington DC: IMF.

Jafari, M., Akhavan, P., Nour, J.R. and Fesharaki, M.N. (2007). Knowledge management in Iran aerospace industries: A study on critical factors. Aircraft Engineering and Aerospace Technology, 79(4): 375–389. http://dx.doi.org/10.1108/00022660710758240.

Jafari, M., Rezaeenour, J., Mazdeh, M.M. and Hooshmandi, A. (2011). Development and evaluation of knowledge risk management model for project-based organizations: A multi-stage study. Management Decisions, 49(3): 309–329. http://dx.doi.org/10.1108/00251741111120725.

Jahangiri, K., Izadkhah, Y.O. and Jamaledin Tabibi, S. (2011). A comparative study on community-based disaster management in selected countries and designing a model for Iran. Disaster Prevention and Management: An International Journal, 20(1): 82–94. http://dx.doi.org/10.1108/09653561111111108.

KarimiAzari, A., Mousavi, N., Mousavi, S.F. and Hosseini, S. (2011). Risk assessment model selection in construction industry. Expert Systems with Applications, 38(8): 9105–9111. http://dx.doi.org/10.1016/j.eswa.2010.12.110.

Kazaz, A. and Ulubeyli, S. (2007). Drivers of productivity among construction workers: A study in a developing country. Building and Environment, 42(5): 2132–2140. http://dx.doi.org/10.1016/j.buildenv.2006.04.020.

Khan, O. and Burnes, B. (2007). Risk and supply chain management: Creating a research agenda. The International Journal of Logistics Management, 18(2): 197–216. http://dx.doi.org/10.1108/09574090710816931.

Kikwasi, G.J. (2011). An assessment of risk management practices by consultants in Tanzania. In T.C. Haupt (ed.). Proceedings of the 6th Built Environment. Johannesburg, South Africa, 31 July–2 August. Johannesburg, South Africa: Association of Schools of Construction, 302–314.

Kim, S. and Bajaj, D. (2000). Risk management in construction: An approach for contractors in South Korea. Cost Engineering, 42(1): 38–44.

Kululanga, G. (2012). Capacity building of construction industries in Sub?Saharan developing countries. Engineering, Construction and Architectural Management, 19(1): 86–100. http://dx.doi.org/10.1108/09699981211192580.

Kutsch, E. and Hall, M. (2009). The rational choice of not applying project risk management in information technology projects. Project Management Journal, 40(3): 72–81. http://dx.doi.org/10.1002/pmj.20112.

Liu, J., Li, B., Lin, B. and Nguyen, V. (2007). Key issues and challenges of risk management and insurance in China's construction industry: An empirical study. Industrial Management and Data Systems, 107(3): 382–396. http://dx.doi.org/10.1108/02635570710734280.

Liu, J.Y., Low, S.P. and He, X. (2011). Current practices and challenges of implementing enterprise risk management (ERM) in Chinese construction enterprises. International Journal of Construction Management, 11(4): 49–63. http://dx.doi.org/10.1080/15623599.2011.10773178.

Lyons, T. and Skitmore, M. (2004). Project risk management in the Queensland engineering construction industry: A survey. International Journal of Project Management, 22(1): 51–61. http://dx.doi.org/10.1016/S0263-7863(03)00005-X.

Moavenzadeh, F. (1978). Construction industry in developing countries. World Development, 6(1): 97–116. http://dx.doi.org/10.1016/0305-750X(78)90027-X.

Mojtahedi, S.M.H., Mousavi, S.M. and Makui, A. (2010). Project risk identification and assessment simultaneously using multi-attribute group decision making technique. Safety Science, 48(4): 499–507. http://dx.doi.org/10.1016/j.ssci.2009.12.016.

Nateghi?A., F. (2000). Existing and proposed earthquake disaster management organization for Iran. Disaster Prevention and Management: An International Journal, 9(3): 200–205. http://dx.doi.org/10.1108/09653560010335130.

Ofori, G. and Toor, S. (2012). Leadership and construction industry development in developing countries. Journal of Construction in Developing Countries, 17(Suppl. 1): 1–21.

Paape, L. and Speklè, R.F. (2012). The adoption and design of enterprise risk management practices: An empirical study. European Accounting Review, 21(3): 533–564. http://dx.doi.org/10.1080/09638180.2012.661937.

Parsizadeh, F. and Ghafory?Ashtiany, M. (2010). Iran public education and awareness program and its achievements. Disaster Prevention and Management: An International Journal, 19(1): 32–47. http://dx.doi.org/10.1108/09653561011022126.

Perera, B.A.K.S., Rameezdeen, R., Chileshe, N. and Hosseini, M.R. (2014). Enhancing the effectiveness of risk management practices in Sri Lankan road construction projects: A Delphi approach. International Journal of Construction Management, 14(1): 1–19. http://dx.doi.org/10.1080/15623599.2013.875271.

Perthes, V. (2010). Ambition and fear: Iran's foreign policy and nuclear programme. Survival, 52(3): 95–114. http://dx.doi.org/10.1080/00396338.2010.494879.

Pournader, M., Tabassi, A.A. and Baloh, P. (2015). A three-step design science approach to develop a novel human resource-planning framework in projects: The cases of construction projects in USA, Europe, and Iran. International Journal of Project Management, 33(2): 419–434. http://dx.doi.org/10.1016/j.ijproman.2014.06.009.

Rao Tummala, V.M., Leung, H.M., Mok, C.K., Burchett, J.F. and Leung, Y.H. (1997). Practices, barriers and benefits of using risk management approaches in selected Hong Kong industries. International Journal of Project Management, 15(5): 297–312. http://dx.doi.org/10.1016/S0263-7863(96)00082-8.

Ringle, C.M., Sarstedt, M. and Straub, D. (2012), A critical look at the use of PLS-SEM in MIS Quarterly. MIS Quarterly (MISQ), 36(1): iii–xiv.

Roudsari, B.S. and Ghodsi, M. (2005). Occupational injuries in Tehran. Injury, 36(1): 33–39. http://dx.doi.org/10.1016/j.injury.2003.10.034.

Sharifirad, M.S. (2011). The dimensions of learning organization questionnaire (DLOQ). International Journal of Manpower, 32(5/6): 661–676. http://dx.doi.org/10.1108/01437721111158251.

Silva, E.S., Wu, Y. and Ojiako, U. (2013). Developing risk management as a competitive capability. Strategic Change, 22(5–6): 281–294. http://dx.doi.org/10.1002/jsc.1940.

Slaughter, E.S. (2000). Implementation of construction innovations. Building Research and Information, 28(1): 2–17. http://dx.doi.org/10.1080/096132100369055.

Tabassi, A.A. and Bakar, A.H.A. (2009). Training, motivation, and performance: The case of human resource management in construction projects in Mashhad, Iran. International Journal of Project Management, 27(5): 471–480. http://dx.doi.org/10.1016/j.ijproman.2008.08.002.

Tabassi, A.A., Ramli, M. and Bakar, A.H.A. (2012). Effects of training and motivation practices on teamwork improvement and task efficiency: The case of construction firms. International Journal of Project Management, 30(2): 213– 224. http://dx.doi.org/10.1016/j.ijproman.2011.05.009.

Tadayon, M., Jaafar, M. and Nasri, E. (2012). An assessment of risk identification in large construction projects in Iran. Journal of Construction in Developing Countries, 17(1): 57–69.

Tah, J.H.M. and Carr, V. (2001). Knowledge-based approach to construction project risk management. Journal of Computing in Civil Engineering, 15(3): 170–177. http://dx.doi.org/10.1061/(ASCE)0887-3801(2001)15:3(170).

Tang, W., Qiang, M., Duffield, C.F., Young, D.M. and Lu, Y. (2007). Risk management in the Chinese construction industry. Journal of Construction Engineering and Management, 133(12): 944–956. http://dx.doi.org/10.1061/(ASCE)0733-9364(2007)133:12(944).

Tarokh, M.J., Sharifi, E. and Nazemi, E. (2008). Survey of BPR experiences in Iran: Reasons for success and failure. Journal of Business and Industrial Marketing, 23(5): 350–362. http://dx.doi.org/10.1108/08858620810881629.

Tavakkoli-Moghaddam, R., Mousavi, S. and Hashemi, H. (2011). A Fuzzy Comprehensive Approach for Risk Identification and Prioritization Simultaneously in EPC Projects. Rijeka, Croatia: InTech Publisher, 123–146. http://dx.doi.org/10.5772/16247.

Thaheem, M.J. and De Marco, A. (2014). Sustainable repair and maintenance of buildings in the developing countries: A risk management perspective and proposal of customized framework. Journal of Civil Engineering and Architecture Research, 1(1):14–23.

Wang, J. and Yuan, H. (2011). Factors affecting contractors' risk attitudes in construction projects: Case study from China. International Journal of Project Management, 29(2): 209–219. http://dx.doi.org/10.1016/j.ijproman.2010.02.006.

Wang, S.Q., Dulaimi, M.F. and Aguria, M.Y. (2004). Risk management framework for construction projects in developing countries. Construction Management and Economics, 22(3): 237–252. http://dx.doi.org/10.1080/0144619032000124689.

Wang, X., Fang, D. and Pham, L. (2009). Risk assessment of Australian construction and engineering firms in China. International Journal of Construction Management, 9(2): 119–131. http://dx.doi.org/10.1080/15623599.2009.10773134.

Zadeh, M.G. (2010). Risk management implementation in the iranian construction industry from contractors' perspective. MSc diss. Universiti Teknologi Malaysia.

Zhao, X., Hwang, B.G. and Low, S.P. (2013). Developing fuzzy enterprise risk management maturity model for construction firms. Journal of Construction Engineering and Management, 139(9): 1179–1189. http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000712.

Zhao, X., Hwang, B.-G., Low, S.P. and Wu, P. (2014). Reducing hindrances to enterprise risk management implementation in construction firms. Journal of Construction Engineering and Management, 141(3): 04014083. http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000945.

Zou, P.X., Zhang, G. and Wang, J.-Y. (2006). Identifying key risks in construction projects: Life cycle and stakeholder perspectives. Proceedings: The 12th Annual Conference of the Pacific Rim Real Estate Society. The University of Auckland Business School, Auckland, New Zealand, 22–25 January. Auckland, New Zealand: Pacific Rim Real Estate Society (PRRES)