Time Delay and Cost Overrun of Road over Bridge (ROB) Construction Projects in India
Main Article Content
Abstract
This paper aims at studying the factors that contribute to time delay and cost overrun of Road over Bridge (ROB) projects in India. Data for the research study were collected from 62 respondents, including owners, contractors, and consultants of ROB projects. The literature survey and the questionnaire survey helped in identifying 29 factors. The topmost factors were ranked based on the frequency of occurrences. The correlation among owners, contractors, and consultants on ranking of factors was derived by Spearman rank correlation. Factor analysis was used to classify the factors into groups and identify the key groups responsible for time delay and cost overrun of projects. This study will help all stakeholders of ROB projects in India to understand the factors and thereby reduce time delay and cost overrun as well as expedite their completion.
Article Details

This work is licensed under a Creative Commons Attribution 4.0 International License.
References
Akoa, B.B. (2011). Cost overruns and time delays in highway and bridge projects in developing countries - experiences from Cameroon. MS diss., Michigan State University.
Choudhry, R.M., Nasir, A.R. and Gabriel, H.F. (2012). Cost and time overruns in highway projects in Pakistan. Pakistan Engineering Congress, Centenary Celebration, Paper No 726, 353–369.
Dutta, A. and Dutta, P. (2015). Causes of time and cost overruns in transportation sector projects in Bangladesh. International Journal of Economics and Management Studies, 2(4): 15–17.
Flyvbjerg, B., Holm, M.K.S. and Buhl, S.L. (2004). What causes cost overrun in transport infrastructure transport projects? Transport Reviews, 24(1): 3–18. https://doi.org/10.1080/0144164032000080494a
Fugar, F. and Baah, A. (2010). Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building, 10(1/2): 103– 116. https://doi.org/10.5130/AJCEB.v10i1-2.1592
Ghasemi, A. and Zahedias, S. (2012). Normality tests for statistical analysis: A guide for non-statisticians. International Journal of Endocrinology and Metabolism, 10(2): 486–489. https://doi.org/10.5812/ijem.3505
Honrao, Y. and Desai, D.B. (2015). Study of delay in execution of infrastructure projects – highway construction. International Journal of Scientific and Research Publications, 5(6): 1–8.
Kishore, M., Rao, C.H. and Singh, L. (2012). Time and cost overrun analysis on national highway development projects. Journal of the Indian Roads Congress, 73(3): 299–321.
Le-Hoai, L., Lee, Y.D. and Lee, J.Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering, 12(6): 367–377. https://doi.org/10.1007/s12205- 008-0367-7
Mahamid, I. and Bruland, A. (2012). Cost deviation in road construction projects: The case of Palestine. Australian Journal of Construction Economics and Building, 12(1): 58–71. https://doi.org/10.5130/ajceb.v12i1.2427
Patil, S.K., Gupta, A.K., Desai, D.B. and Sajane, A.S. (2013). Causes of delay in Indian transportation infrastructure projects. International Journal of Research in Engineering and Technology, 2(11): 71–80. https://doi.org/10.15623/ijret.2013.0211013
Ramanathan, C., Narayanan, S.P. and Idrus, A. (2012). Construction delays causing risks on time and cost – a critical review. Australian Journal of Construction Economics and Building, 12(1): 37–57. https://doi.org/10.5130/ajceb.v12i1.2330
Singh, R. (2009). Delays and cost overruns in infrastructure projects: An enquiry into extents, causes and remedies, working paper no. 181. Delhi: Centre for Development Economics, Department of Economics, Delhi School of Economics.
Yong, A.G. and Pearce, S. (2013). A beginner’s guide to factor analysis: Focusing on exploratory factor analysis. Tutorials in Quantitative Methods for Psychology, 9(2): 79–94. https://doi.org/10.20982/tqmp.09.2.p079
Wijekoon, S.B. and Attanayake, A.M.C.T.K. (2012). Study on the cost overruns in road construction projects in Sri Lanka. International Conference on Sustainable Built Environment, Sri Lanka, Paper No 69. The Earls Regency Hotel, Kandy, 14–16 December 2012. Sri Lanka: University of Peradeniya.
Williams, B., Brown, T. and Onsman, A. (2010). Exploratory factor analysis: A five-step guide for novices. Australian Journal of Paramedicine, 8(3): 1–13.