Identifying and Addressing Critical Issues in the Indian Construction Industry: Perspectives of Large Building Construction Clients

Main Article Content

Santhosh Loganathan
Purushothaman Srinath
Mohan Kumaraswamy
Satyanarayana Kalidindi
Koshy Varghese

Abstract

The Indian construction industry faces increasing challenges amidst serious performance shortfalls. Confronting similar issues in past decades, other countries such as the UK, USA, and Singapore commissioned high-powered studies and set up industry development bodies to address their own priorities. Initiatives in other countries are briefly reviewed before outlining the launch of the “Construction Industry Improvement Initiative India” (Ci3 India) that aims to address our own challenges. This paper focuses on identifying and launching a platform to address the current and imminent critical issues in the Indian Construction Industry. Nineteen critical issues were identified, verified, and validated through four focus group sessions at two Regional Roundtables with 54 high calibre large building construction clients, academicians, and other invited experts. The identified issues were consolidated to 10 Action Items. Seven Action Teams were then mobilized to work on the 10 Action Items. Having consolidated a base consensus of clients on the way forward, it was also proposed to develop a “Construction Clients’ Charter” that will set out basic principles, protocols, and targeted good practices by lead clients, who by voluntarily agreeing and implementing these together, could catalyse significant industry improvements.

Article Details

How to Cite
Santhosh Loganathan, Purushothaman Srinath, Mohan Kumaraswamy, Satyanarayana Kalidindi, and Koshy Varghese. 2017. “Identifying and Addressing Critical Issues in the Indian Construction Industry: Perspectives of Large Building Construction Clients”. Journal of Construction in Developing Countries 22 (Supp. 1): 121-44. https://doi.org/10.21315/Jcdc2017.22.Supp1.7.
Section
Articles

References

Agarwal, M. (2013). The opportunity and challenge of India’s infrastructure. Mumbai: PricewaterhouseCoopers, 10. Available at: https://www.pwc.com/gx/en/capital-projects-infrastructure/assets/gridlines-india-article-2013.pdf [Accessed on 18 July 2016].

Al-Kharashi, A. and Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1): 3–23. https://doi.org/10.1080/01446190802541457

Bramble, B.B. and Callahan, M.T. (1992). Construction delay claims. New York: Wiley Law Publications.

Building and Construction Authority. (1999). About BCA. Singapore: Building and Construction Authority. Available at: https://en.wikipedia.org/wiki/Building_and_Construction_Authority [Accessed on 18 July 2016].

Business Roundtable Report. (1983). More money for construction, summary report of the construction industry cost effectiveness. New York: The Business Roundtable, 11–36.

Construction Industry Institute. (2016). About CII. Austin, Texas: Construction Industry Institute. Available at: https://www.construction-institute.org/scriptcontent/index.cfm [Accessed on 5 July 2016].

Construction Industry Council. (2016). About us. London: Construction Industry Council. Available at: www.cic.uk [Accessed on 5 July 2016].

Construction Industry Institute India. (2016). First regional roundtable report of Ci3 India. Chennai: Construction Industry Institute India, Available at: http://www.ci3.in/reports.html [Accessed on at 5 July 2106].

De Saram, D.D., Rahman, M.M. and Kumaraswamy, M.M. (2001). Setting targets and selecting tools for Construction Industry development. Proceedings of the FEISCA Conference on ‘Engineering Management for Accelerated Development in South & South-East Asia’. Trans Asia Hotel, Colombo, 27–28 October 2001. Colombo: Institution of Engineers.

DMG Events India. (2015). Construction market in India. Mumbai: DMG Events India Pvt. Ltd, 13. Available at: http://www.arbinternational.es/ARCHIVO/documentos/sectorial/1431507298_construction-market-report.pdf [Accessed on 18 July 2016].

Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(3): 479–489. https://doi.org/10.1016/j.ijproman.2011.10.004

Egan, J. (1998). Rethinking construction: Report of the construction task force. London: Department for the Environment, Transport and the Regions.

Fayek, R.A., Rankin, H.J. and Tromposch, E. (2008). Client driven performance improvement strategies for the construction industry: Development and implementation challenges. In P. Brandon and S.-L. Lu (eds.). Clients driving innovation. London: Blackwell, 202–204. https://doi.org/10.1002/9781444301342.ch20

Fox, P. and Skitmore, M. (2007). Factors facilitating construction industry development. Building Research and Information, 35(2): 178–188. https://doi.org/10.1080/09613210600980192

Government of India. (2010). Annual report to the people on employment. Delhi: Ministry of Labour and Employment, Government of India, 362. Available at: http://labour.gov.in/sites/default/files/Annual%20Report%202009-10%20English_0.pdf [Accesed on 10 July 2016].

Government of India. (2002). Report of the National Commission on Labour. New Delhi: Ministry of Labour, Government of India.

Horner, R.M.W., Talhouni, B.T. and Thomas, H.R. (1989). Preliminary results of major labour productivity monitoring programme. Proceeding of the 3rd Yugoslavian Symposium on Construction Management. Cavtat, Croatia: Zagreb University, 18–28.

Hillebrandt, P.M. (2000). Economic theory and the construction industry, 3rd Ed. London: Macmillan. https://doi.org/10.1057/9780230372481

Hwang, B. and Soh, C. (2013). Trade-level productivity measurement: Critical challenges and solutions. Journal of Construction Engineering and Management, 139(11): 1–11. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000761

India Smart Cities Challenge. (2016). What is a smart city? New Delhi: Ministry of Housing and Urban Affairs, Government of India. Available at: http://www.smartcitieschallenge.in/what-is-a-smart-city [Accessed on 18 July 2016].

Iyer, K.C. and Jha, K.N. (2005). Factors affecting cost performance: Evidence from Indian construction projects. International Journal of Project Management, 23(4): 283–295. https://doi.org/10.1016/j.ijproman.2004.10.003

Iyer, K.C. and Jha, K.N. (2006). Critical factors affecting schedule performance : Evidence from Indian construction projects. Journal of Construction Engineering and Management, 132(8): 871–881. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:8(871)

Kontio, J., Lehtola, L. and Bragge, J. (2004). Using the focus group method in software engineering: Obtaining practitioner and user experiences. Proc. 2004 Int. Symp. on Empirical Software Engineering. Redondo Beach, CA, USA, 20 August 2004. Washington, DC: IEEE Computer Society, 271–280. https://doi.org/10.1109/ISESE.2004.1334914

Kumaraswamy, M.M., Palaneeswaran, E. and Humphreys, P. (2000). Selection matters – in construction supply chain optimisation. International Journal of Physical Distribution and Logistics Management, 30(7/8): 661–680. https://doi.org/10.1108/09600030010346431

Kumaraswamy, M.M., Rowlinson, S., Rahman, M.M. and Phua, F. (2002). Strategies for triggering the required "cultural revolution" in the construction industry. In R. Fellows and D. Seymour. (Eds.). Perspectives on culture in construction. Rotterdam: CIB, 268–285.

Kumaraswamy, M.M. (2006). Accelarating construction industry development. Journal of Construction in Developing Countries, 11(1): 73–94.

Laskar, A. and Murty, C.V.R. (2010). Challenges before construction industry in India. Proceedings: National Seminar on Sustainable Infrasture and Rehablitation Technology. Kanpur, India: IIT Kanpur, 1–18.

Latham, M. (1994). Constructing the team: Final report. Joint review of procurement and contractual arrangements in the United Kingdom construction industry. London: H. M. Stationery Office.

Lim, E.C. and Alum, J. (1995). Construction productivity: Issues encountered by contractors in Singapore. International Journal of Project Management, 13(1): 51–58. https://doi.org/10.1016/0263-7863(95)95704-H

Loganathan, S. and Kalidindi, S. (2016). Absenteeism and turnover of migrant construction workers in Indian projects—A survey-based study. In J. L. PerdomoRivera, A. Gonzáles-Quevedo, C. L. del Puerto, F. Maldonado-Fortunet and O. I. Molina-Bas (eds.). Proceeding of Construction Research Congress. University of Puerto Rico-Mayagüez, 31 May – 2 June 2016. Puerto Rico: University of Pureto Rico, 1793–1802. https://doi.org/10.1061/9780784479827.179

Loganathan, S. and Kalidindi, S. (2015). Masonry labor productivity variation: An Indian case study. In N. Raghavan and K. Varghese (eds.). Proceedings of the first Indian Lean Construction Conference. Godrej and Boyce Manufacturing Company Ltd., 6–7 February 2015, 175–185.

Make in India. (2014). Construction. New Delhi: Invest India. Available at: http://www.makeinindia.com/sector/construction [Accessed on 18 July 2016].

Marková, I., Grossen, P.L.M. and Orvig, A.S. (2007). Dialogue in focus groups: Exploring socially shared knowledge. Oakville, CT: Equinox Publishing, 243.

Ministry of Housing and Urban Poverty Alleviation. (2015). Pradhan Mantri Awas Yojana. New Delhi: Ministry of Housing and Urban Affairs. Available at: http://mhupa.gov.in/User_Panel/UserView.aspx?TypeID=1434 [Accessed on 15 June 2016].

Ministry of Personnel, Public Grievances and Pensions. (2012). Grievance analysis and systemic reforms recommendation. Delhi: Ministry of Personnel, Public Grievances and Pensions, Government of India, 259. Available at http://www.darpg.gov.in/sites/default/files/proc_4th_conf.pdf [Accessed on 10 June 2016].

Momaya, K. and Selby, K. (1998). International competitiveness of the Canadian construction industry: A comparison with Japan and the United States. Canadian Journal of Civil Engineering, 25(4): 640–652. https://doi.org/10.1139/l98-004

National Research Council. (2009). Advancing the competitiveness and efficiency of the US construction industry. Washington DC, USA: National Academies Press. https://doi.org/10.17226/12717

Ofori, G. (1984). Improving the construction industry in declining developing economies. Construction Management and Economics, 2(3465): 127–132. https://doi.org/10.1080/01446198400000012

Ofori, G. (1985). Managing construction industry development. Construction Management and Economics, 3(1): 33–35. https://doi.org/10.1080/01446198500000004

Ofori, G. (1994). Practice of construction industry development at the crossroads. Habitat International, 18(2): 41–56. https://doi.org/10.1016/0197-3975(94)90049-3

Ofori, G. (2000a). Globalization and construction industry development: Research opportunities. Construction Management and Economics, 18(3): 257–262. https://doi.org/10.1080/014461900370627

Ofori, G. (2000b). Challenges for construction industries in developing countries. Proceedings of the Second International Conference of the CIB TG 29. Grand Palm Hotel, Gaborone, Botswana, 15–17 November 2000, 1–11.

Ofori, G. (2001). Challenges facing the construction industries of Southern Africa. Regional Conference: Developing the Construction Industries of Southern Africa. Pretoria, South Africa, 23–25 April 2001.

Ofori, G. (2006). Revaluing construction in developing countries: A research agenda. Journal of Construction in Developing Countries, 11(1): 1–16.

Ofori, G. (2015). Nature of the construction industry, its needs and its development: An review of four decades of research. Journal of Construction in Developing Countries, 20(2), 115–135.

Palaneeswaran, E., Kumaraswamy, M.M., Rahman, M.M. and Ng, T.S.T. (2003). Curing congenital construction industry concerns through relationally integrated supply chains. Building and Environment Journal, 38(4): 571–582. https://doi.org/10.1016/S0360-1323(02)00188-9

Rahman, M.M. and Kumaraswamy, M.M. (2002). Joint risk management through transactionally efficient relational contracting. Construction Management and Economics, 20(1): 45–54. https://doi.org/10.1080/01446190110089682

Satyanarayana, K.N. and Iyer, K.C. (1996). Evaluation of delays in Indian construction contracts. Journal of the Institution of Engineers (India), 77(2): 14–22. Sawhney, A., Agnihotri, R. and Paul, K. V. (2014). Grand challenges for the Indian construction industry. Built Environment Project and Asset Management, 4(4): 317–334. https://doi.org/10.1108/BEPAM-10-2013-0055

Schwab, K. (2013). The global competitiveness report 2013–2014. Geneva: World Economic Forum, 569. Available at: http://www3.weforum.org/docs/WEF_GlobalCompetitivenessReport_2013-14.pdf [Accessed on 10 July 2016].

Schwab, K. (2011). The global competitiveness report 2011–2012. Geneva: World Economic Forum, 544. Available at: http://www3.weforum.org/docs/WEF_GCR_Report_2011-12.pdf [Accessed on 10 July 2016].

Scott, (2016). Three challenges facing the construction Industry and whats being done to help, Taurus Blog, 30 June. Fort Saskatchewan, Alberta, Canada: Taurus Projects Inc. Available at: http://www.taurusprojects.ca/index.php/easyblog/entry/3-challenges-facing-the-construction-industry.html [Accessed on 20 January 2017].

Thomas, A.V. and Sudhakumar, J. (2014). Factors influencing construction labour productivity: An Indian case study. Journal of Construction in Developing Countries, 19(1): 53–68.

Thomas, A.V. and Sudhakumar, J. (2013). Labour productivity variability among labour force – A case study. The International Journal of Engineering and Science, 2(5): 57–65.

Ugwu, O.O., Kumaraswamy, M.M., Rahman, M.M. and Ng, S.T. (2003a). IT tools for collaborative working in relationally integrated supply chains. In F. Bontempi (ed.). 2nd Intnl. Structural Engineering and Construction Conference. 23–26 September 2003, Rome, Italy. Florida, USA: CRC Press.

Wells, J. (1986). Construction industry in developing countries: Alternative strategies for development. London: Croom Helm.

World Bank. (1984). The construction industry: Issues and strategies in developing countries. Washington D.C.: World Bank.

Yang, Y., Kumaraswamy, M., Pam, H. and Mahesh, G. (2011). Integrated qualitative and quantitative methodology to assess validity and credibility of models for bridge maintenance management system development. Journal of Management in Engineering, 27(3): 149–158. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000051.