Time and Cost Overruns on Large Projects: Understanding the Root Cause
Main Article Content
Abstract
Time and cost overruns are a persistent problem on large projects despite apparent progress of the project management profession. This article reports on findings from research carried out on large projects in South Africa to find the root cause of this phenomenon. The article begins by investigating the existing theories on the causes of time and cost overruns followed by empirical investigation using case studies. The results showed that time and cost overruns on large projects originated from the external environment which in turn affected the organisation and the project environments. The root cause was found to be a lack of project-specific experience by the project team, external and organisational decisions in the past, community resistance and pressure on the project team and scope change drive from stakeholders. From the results, it is proposed that an effective strategy to reduce time and cost overruns should involve not only the management of the project environment but also the organisation and external environments. The article adds knowledge to the overrun causation theory and management of large projects.
Article Details

This work is licensed under a Creative Commons Attribution 4.0 International License.
References
Ahiaga-Dagbui, D.D., and Smith, S.D. (2014). Dealing with construction cost overruns using data mining. Construction Management and Economics, 32(7/8): 682– 694. https://doi.org/10.1080/01446193.2014.933854.
Ahiaga-Dagbui, D.D., Smith, S.D., Love, P.E.D. and Ackermann, F. (2015). Spotlight on construction cost overrun research: Superficial, replicative and stagnated. In A.B. Raiden and E. Aboagye-Nimo (eds.), Proceedings of 31st Annual ARCOM Conference. Lincoln, UK: Association of Researchers in Construction Management (ARCOM).
AlSehaimi, A., Koskela, L. and Tzortzopoulos, P. (2013). The need for alternative research approaches in construction management: The case of delay studies. Journal of Management in Engineering, 29: 407–413. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000148.
Ameh, O.J., Soyingbe, A.A. and Odusami, K.T. (2010). Significant factors causing cost overruns in telecommunication projects in Nigeria. Journal of Construction in Developing Countries, 15(2): 49–67.
Anderson, D.K. and Merna, T. (2003). Project management strategy: Project management represented as a process based set of management domains and the consequences of project management strategy. International Journal of Project Management, 21: 387–393. https://doi.org/10.1016/S0263-7863(02)00087-X.
Cantarelli, C., Molin, E.J.E., Wee, B.V. and Flyvbjerg, B. (2012). Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of decision to build and project phases. Transport Policy, 22: 49–56. https://doi.org/10.1016/j.tranpol.2012.04.001.
Capka, J.R. (2004). Mega-projects are a different breed. Public Roads, July/August.
Dahl, R.E., Lorentzen, S., Oglend, A. and Osmundsen, P. (2017). Pro-cyclical petroleum investments and cost overruns in Norway. Energy Policy, 100: 68– 78. https://doi.org/10.1016/j.enpol.2016.10.004.
Eizakshiri, F., Chan, P.W. and Emsely, M. (2011). Delays, what delays? A critical review of the literature on delays in construction. In C. Egbu and E.C.W. Lou (eds.), Proceedings 27th Annual ARCOM Conference. Bristol, UK: Association of Researchers in Construction Management (ARCOM), 839–848.
Fellows, R. and Lui, A. (2008). Research Methods for Construction. Chichester: Blackwell.
Flyvbjerg, B. (2011). Over budget, over time, over and over again. Managing major projects. In P.W.G. Morris and J.K. Pinto (eds.), The Oxford Handbook of Project Management. Oxford: Oxford University Press, 321–344.
Frimpong, Y., Oluwoye, J. and Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing country: Ghana as a case study. International Journal of Project Management, 21: 321–326. https://doi.org/10.1016/S0263-7863(02)00055-8.
Giezen, M. (2012). Keeping it simple? A cases study into the advantages and disadvantages of reducing complexity in mega project planning. International Journal of Project Management, 30: 781–790. https://doi.org/10.1016/j.ijproman.2012.01.010.
Groenveld, G.D. (2006). The way forward for the South African construction industry: An analysis with project management solutions. MBA diss., Stellenbosch University.
Harding, J. (2013). Qualitative Data Analysis from Start to Finish. London: Sage.
Kaliba, C., Muya, M. and Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management, 27: 522–531. https://doi.org/10.1016/j.ijproman.2008.07.003.
Le-Hoai, L., Lee, Y.D. and Lee, J.Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering, 12(6): 367–377. https://doi.org/10.1007/s12205-008-0367-7.
Lim, C.S. and Mohamed, M.Z. (1999). Criteria of project success: An exploratory reexamination. International Journal of Project Management, 17(4): 243–248. https://doi.org/10.1016/S0263-7863(98)00040-4.
Lin, Y. and Lui, S. (2011). Small and large projects: Their dynamics and which ones to take. Kybernetes, 40(9): 1354–1372. https://doi.org/10.1108/03684921111169431.
Love, P. E. D., Smith, J., Simpson, I., Regan, M. and Olatunji, O. (2014). Understanding the landscape of overruns in transport infrastructure projects. Environment and Planning B: Planning and Design, 41: 1–20.
Love, P.E.D., Ahiaga-Dagbui, D.D. and Irani, Z. (2016). Cost overruns in transportation infrastructure projects: Sowing the seeds for a probabilistic theory of causation. Transportation Research Part A, 92: 184–194. https://doi.org/10.1016/j.tra.2016.08.007.
Memon, A.H., Rahman, A.I., Abdullah, M.R. and Azis, A.A.A. (2014). Factors affecting construction cost performance in project management projects: Case of MARA large projects. International Journal of Civil Engineering and Built Environment, 1(1): 30–35.
Merrow, E.W. (2011). Industrial Megaprojects: Concepts, Strategies and Practices for Success. Hoboken, NJ: John Wiley and Sons.
Morris, P.W.G and Geraldi, J. (2011). Managing the institutional context for projects. Project Management Journal, 42(6): 20–32. https://doi.org/10.1002/pmj.20271.
Morris, P.W.G. and Hough, G.H. (1987). The Anatomy of Major Projects: A Study of the Reality of Project Management. Chichester: John Wiley and Sons.
Muianga, E.A.D., Granja, A.D. and Ruiz, J.A. (2014). Influence factors on cost and time overruns in Mozambicans construction projects: Preliminary findings. Proceedings: 5th International Conference on Engineering, Project and Production Management. Port Elizabeth, South Africa: Nelson Mandela Metropolitan University, 10–21.
Mukuka, M., Aigbavboa, C. and Thwala, W. (2015). Effects of construction project schedule overruns: A case of the Gauteng Province, South Africa. Procedia Manufacturing, 3: 1690–1695. https://doi.org/10.1016/j.promfg.2015.07.989.
Murray, M. (2010). An investigation into programme management risks. PhD diss., University of Witwatersrand.
Mushayi, V., Botha, B., Anderdoff, C., Cumberledge, R. and Abey, M. (2018). Cost overruns and their impact in the business of construction. Proceedings: The Twelfth Built Environment Conference. Penhill Estate, South Africa: Association of Schools of Construction of Southern Africa, 277–287.
Ofori, G., Hindle, R. and Hugo, F. (1996). Improving the construction industry in South Africa: A strategy. Habitat International, 20(2): 203–220. https://doi.org/10.1016/0197-3975(95)00056-9.
Ramanathan, C., Narayanan, S.P. and Idrus, A.B. (2012). Construction delays causing risks on time and cost: A critical review. Australasian Journal of Construction Economics and Building, 12: 37–57. https://doi.org/10.5130/AJCEB.v12i1.2330.
Rosenfield, Y. (2013). Root-cause analysis of construction-cost overruns. Journal of Construction Engineering and Management, 140(1): 04013039. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000789.
Senouci, A., Ismail, A. and Eldin, N. (2016). Time delay and cost overrun in Qatari public construction projects. Procedia Engineering, 164: 368–375. https://doi.org/10.1016/j.proeng.2016.11.632.
Sweis, G. (2013). Factors affecting time overruns in public construction projects: The case of Jordan. International Journal of Business and Management, 8(23): 120–129. https://doi.org/10.5539/ijbm.v8n23p120.
Tai, S.W. and Anumba, C.J. (2009). A survey on communications in large-scale construction projects in China. Engineering, Construction and Architectural Management, 16(2): 136–149. https://doi.org/10.1108/09699980910938019.
Whittaker, B. (1999). What went wrong? Unsuccessful information technology projects. Information Management and Computer Security, 7(1): 23–29. https://doi.org/10.1108/09685229910255160.
Yin, R.K. (2014). Case Study Research: Design and Methods. 5th Ed. Thousand Oaks, CA: Sage.