Application of Linear Scheduling in Water Canal Construction with a Comparison of Critical Path Method
Main Article Content
Abstract
Critical path method (CPM) still remains the most commonly used scheduling technique, despite many studies confirming its shortcomings for scheduling repetitive construction projects. This research evaluated the case study of an alignment-based precast water canal erection project, which was originally planned with CPM and analysed the suitability of using linear scheduling method (LSM) for the same project. The case study project was scheduled using both CPM and LSM tools and the results were compared in terms of estimated total duration and resource cost. The results showed that LSM produced a saving of 10 days in total duration and 20.07% in estimated resource cost over CPM. LSM also proved to be the better tool in terms of other schedule attributes like resource assignment, levelling, visualisation, etc., for alignment-based projects. LSM can be highly efficient for scheduling different types of repetitive construction and offers benefits like better workflow and continuous resource usage.
Article Details

This work is licensed under a Creative Commons Attribution 4.0 International License.
References
Agrama, F.A. (2011). Linear projects scheduling using spreadsheets features. Alexandria Engineering Journal, 50(2): 179–185. https://doi.org/10.1016/j.aej.2011.01.018.
________. (2006). The line of balance technique by genetic optimization. PhD diss. Tanta University.
Ammar, M.A. (2019). Resource optimisation in line of balance scheduling. Construction Management and Economics, 38(8): 715–725. https://doi.org/10.1080/01446193.2019.1606924.
Andersson, N. and Christensen, K. (2007). Practical implications of locationbased scheduling. In W. Hughes (ed.), CME 25 Conference Construction Management and Economics: Past, Present and Future. Reading, UK: School of Construction Management and Engineering, University of Reading, 1367– 1376.
Arditi, D., Tokdemir, O.B. and Suh, K. (2002). Challenges in line-of-balance scheduling. Journal of Construction Engineering and Management, 128(6): 545–556. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:6(545).
Bansal, V.K. and Pal, M. (2009). Construction schedule review in GIS with a navigable 3D animation of project activities. International Journal of Project Management, 27(5): 532–542. https://doi.org/10.1016/j.ijproman.2008.07.004.
Benjaoran, V., Tabyang, W. and Sooksil, N. (2015). Precedence relationship options for the resource levelling problem using a genetic algorithm. Construction Management and Economics, 33(9): 711–723. https://doi.org/10.1080/01446193.2015.1100317.
Bragadin, M.A. and Kähkönen, K. (2016). Schedule health assessment of construction projects, Construction Management and Economics, 34(12): 875–897. https://doi.org/10.1080/01446193.2016.1205751.
Burns, S.A., Liu, L. and Feng, C.-W. (1996). The LP/IP hybrid method for construction time-cost trade-off analysis. Construction Management and Economics, 14(3): 265–276. https://doi.org/10.1080/014461996373511.
Central Public Works Department (2019). Analysis of Rates for Delhi. Vol. 1. New Delhi, India: Government of India.
Duffy, G., Woldesenbet, A., Jeong, D.H.S. and Oberlender, G.D. (2012). Advanced linear scheduling program with varying production rates for pipeline construction projects. Automation in Construction, 27: 99–110. https://doi.org/10.1016/j.autcon.2012.05.014.
Duffy, G.A. (2009). Linear scheduling of pipeline construction projects with varying production rates. PhD diss. Oklahoma State University. Available at: https://hdl.handle.net/11244/7833.
El-Rayes, K. and Moselhi, O. (1998). Resource-driven scheduling of repetitive activities. Construction Management and Economics, 16(4): 433–446. https://doi.org/10.1080/014461998372213.
Galloway, P.D. (2006). Survey of the construction industry relative to the use of CPM scheduling for construction projects. Journal of Construction Engineering and Management, 132(7): 697–711. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(697).
Hamzeh, F.R., Zankoul, E. and Rouhana, C. (2015). How can "tasks made ready" during lookahead planning impact reliable workflow and project duration? Construction Management and Economics, 33(4): 243–258. https://doi.org/10.1080/01446193.2015.1047878.
Harmelink, D.J. and Rowings, J.E. (1998). Linear scheduling model: Development of controlling activity path. Journal of Construction Engineering and Management, 124(4): 263–268. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(263).
Harris, R.B. and Ioannou, P.G. (1998). Scheduling projects with repeating activities. Journal of Construction Engineering and Management, 124(4): 269–278. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(269).
Hegazy, T. (2005). Computerized system for efficient scheduling of highway construction. Transportation Research Record, 1907(1): 8–14. https://doi.org/10.1177%2F0361198105190700102.
Hegazy, T. and Kamarah, E. (2008). Efficient repetitive scheduling for high-rise construction. Journal of Construction Engineering and Management, 134(4): 253–264. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:4(253).
Hegazy, T. and Menesi, W. (2010). Critical path segments scheduling technique, Journal of Construction Engineering and Management, 136(10): 1078–1085. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000212.
Johnston, D.W. (1981). Linear scheduling method for highway construction. Journal of the Construction Division, 107(2): 247–261. https://doi.org/10.1061/JCCEAZ.0000960.
Jongeling, R. and Olofsson, T. (2007). A method for planning of work-flow by combined use of location-based scheduling and 4D CAD. Automation in Construction, 16(2): 189–198. https://doi.org/10.1016/j.autcon.2006.04.001.
Kastor, A. and Sirakoulis, K. (2009). The effectiveness of resource levelling tools for resource constraint project scheduling problem. International Journal of Project Management, 27(5): 493–500. https://doi.org/10.1016/j.ijproman.2008.08.006.
Kim, A., Wang, S., Medal, L. and Sadatsafavi, H. (2019). Linear Scheduling Evaluation and Best Practices Development: Phase. Report. Washington: Washington State Transportation Center (TRAC). Available at: https://www.wsdot.wa.gov/research/reports/fullreports/898-1.pdf.
Koskela, L., Howell, G., Pikas, E. and Dave, B. (2014). If CPM is so bad, why have we been using it so long? In B.T. Kalsaas, L. Koskela and T.A. Smith (eds.), 22nd Annual Conference of the International Group for Lean Construction (IGLC 2014): Understanding and Improving Project Based Production. Red Hook, NY: Curran Associates, Inc.
Liu, L., Liu, Y., Tang, Y. and Li, Q. (2013). Research on railway tunnel construction scheduling technique based on LSM. In F. Chen, Y. Liu and G. Hua (eds.), LTLGB 2012: Proceedings of International Conference on Low-carbon Transportation and Logistics, and Green Buildings. Berlin/Heidelberg: Springer, 895–903. https://doi.org/10.1007/978-3-642-34651-4_120.
Liu, S.S. and Wang, C.J. (2007). Optimization model for resource assignment problems of linear construction projects. Automation in Construction, 16(4): 460–473. https://doi.org/10.1016/j.autcon.2006.08.004.
Lu, M. and Lam, H.C. (2009). Transform schemes applied on non-finish-to-start logical relationships in project network diagrams. Journal of Construction Engineering and Management, 135(9): 863–873. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000062.
Lucko, G. (2008). Productivity scheduling method compared to linear and repetitive project scheduling methods. Journal of Construction Engineering and Management, 134(9): 711–720. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:9(711).
________. (2007). Computational analysis of linear and repetitive construction project schedules with singularity functions. Paper presented at the International Workshop on Computing in Civil Engineering 2007. Pittsburgh, Pennsylvania, 24–27 July.
Lucko, G. and Orozco, A.A. (2009). Float types in linear schedule analysis with singularity functions. Journal of Construction Engineering and Management, 135(5): 368–377. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000007.
Markiz, N. and Jrade, A. (2019). Integrating an expert system with BrIMS, cost estimation and linear scheduling at conceptual design stage of bridge projects. International Journal of Construction Management, 22(5): 913–918. https://doi.org/10.1080/15623599.2019.1661572.
Mattila, K.G. and Park, A. (2003). Comparison of linear scheduling model and repetitive scheduling method. Journal of Construction Engineering and Management, 129(1): 56–64. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:1(56).
Olivieri, H., Seppänen, O. and Granja, A.D. (2018). Improving workflow and resource usage in construction schedules through location-based management system (LBMS). Construction Management and Economics, 36(2): 109–124. https://doi.org/10.1080/01446193.2017.1410561.
Olivieri, H., Seppänen, O., Alves, T.D.C.L., Scala, N.M., Schiavone, V., Liu, M. and Granja, A.D. (2019). Survey comparing critical path method, last planner system and location-based techniques. Journal of Construction Engineering and Management, 145(12): 04019077. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001644.
Project Management Institute (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th Ed. Newton Square, PA: Project Management Institute, Inc.
Russell, A.D. and Wong, W.C. (1993). New generation of planning structures. Journal of Construction Engineering and Management, 119(2): 196–214. https://doi.org/10.1061/(ASCE)0733-9364(1993)119:2(196)
Rzepecki, L. and Biruk, S. (2018). Simulation method for scheduling linear construction projects using the learning-forgetting effect. MATEC Web of Conferences, 219: 04007. https://doi.org/10.1051/matecconf/201821904007.
Sharma, S. and Bansal, V.K. (2018). Location-based planning and scheduling of highway construction projects in hilly terrain using GIS. Canadian Journal of Civil Engineering, 45(7): 570-582. https://doi.org/10.1139/cjce-2017-0359.
Shi, Q. and Blomquist, T. (2012). A new approach for project scheduling using fuzzy dependency structure matrix. International Journal of Project Management, 30(4): 503–510. https://doi.org/10.1016/j.ijproman.2011.11.003.
Song, L., Lee, S.-H. and Rachmat, F.H. (2012). Stochastic look-ahead scheduling method for linear construction projects. Journal of Risk Analysis and Crisis Response, 2(4): 252–260. https://doi.org/10.2991/jrarc.2012.2.4.4.
Tang, Y.J., Liu, R.K. and Sun, Q.X. (2014). Two-stage scheduling model for resource leveling of linear projects. Journal of Construction Engineering and Management, 140(7): 80–89. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000862.
Tapia, P.R.M. and Gransberg, D.D. (2016). Forensic Linear Scheduling for Delay Claim Analysis: Panama Canal Borinquen Dam Case Study. Washington DC: Transportation Research Board.
Xu, J. and Zhang, Z. (2012). A fuzzy random resource-constrained scheduling model with multiple projects and its application to a working procedure in a largescale water conservancy and hydropower construction project. Journal of Scheduling, 15(2): 253–272. https://doi.org/10.1007/s10951-010-0173-1.
Yamín, R.A. and Harmelink, D.J. (2001). Comparison of linear scheduling model (LSM) and critical path method (CPM). Journal of Construction Engineering and Management, 112(4): 476–491. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:5(374).
Zhang, L. (2015). Repetitive Project Scheduling: Theory and Methods. 1st Ed. Amsterdam/Oxford/Massachusetts: Elsevier. Available at: https://www.elsevier.com/books/repetitive-project-scheduling-theory-and-methods/zhang/978-0-12-801763-0.