Multiphase Project Risk Management on Food Factory Building Construction: Consultant Perspective
Main Article Content
Abstract
This article reports on research on a flour mill factory building construction in Indonesia by investigating the root cause of time overrun in consultant perspective. While numerous risks are identified during the phases of construction project, it is unknown which risk is the primary cause of project delays. To have a better understanding of the optimisation of the risk management and the risk mitigation, a multiphase risk management is proposed, which is divided into four phases, namely pre-design, design, tender and construction. Employing the bow-tie analysis enables a more in-depth examination to identify the risk. From each bow-tie diagram, a detailed risk mitigation table can be formulated and made the response for each risk easier to plan. The probability impact matrix is then used to identify the risk score and to evaluate the risk. This research began by giving questionnaires to 45 qualified respondents. It was found that 45 factors that caused the delay in all phases were divided into nine factors from the pre-design phase, 14 factors from the design phase, 6 factors from the tender phase and 16 factors from the construction phase. As the final step of the risk management process, there are various responses in this research depends on their final assessment based on the scores and the questionnaire results. Factory building construction is quite different from the other type of building construction because machine design also being an important part that affects the structural, architectural, mechanical and electrical aspects.
Article Details

This work is licensed under a Creative Commons Attribution 4.0 International License.
References
Badreddine, A., Romdhane, T.B., HajKacem, M.A.B. and Amor, N.B. (2014). A new multi-objectives approach to implement preventive and protective barriers in bow tie diagram. Journal of Loss Prevention in the Process Industries, 32: 238–253. https://doi.org/10.1016/j.jlp.2014.09.012
COSO (Committee of Sponsoring Organizations) (2004). Enterprise risk management: Integrated framework. Available at: www.coso.org/Publications/ERM/COSO_ERM_ ExecutiveSummary.pdf [Accessed on 11 July 2020].
Creswell, J.W., Klassen, A.C., Clark, V.L.P. and Smith, K.C. (2011). Best Practices for Mixed Methods Research in the Health Sciences. Bethesda, MD: National Institutes of Health. Available at: https://obssr.od.nih.gov/research-resources/mixed-methods-research [Accessed on 10 December 2020].
De Ruijter, A. and Guldenmund, F. (2016). The bowtie method: A review. Safety Science, 88: 211–218. https://doi.org/10.1016/j.ssci.2016.03.001
Departemen Pekerjaan Umum (2007). Pelatihan Ahli Manajemen Konstruksi. Jakarta: Departemen Pekerjaan Umum, 11–14.
El-Shehaby, M., Nosair, I. and El-Moniem, S. (2014). Risk assessment and analysis for the construction of off shore oil and gas projects. International Journal of Scientific Research and Education, 2(2): 317–333.
Flanagan, R. and Norman, G. (1993). Risk Management and Construction. Oxford: Blackwell Scientific.
Gündüz, M., Nielsen, Y. and Özdemir, M. (2013). Quantification of delay factors using the relative importance index method for construction projects in Turkey. Journal of Management in Engineering, 29(2): 133–139. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129
Hamzah, N., Khoiry, M.A., Arshad, I., Tawil, N.M. and Che Ani, A.I. (2011). Cause of construction delay: Theoretical framework. Procedia Engineering, 20: 490–495. https://doi.org/10.1016/j.proeng.2011.11.192
Ibironke, O.T., Oladinrin, T.O., Adeniyi, O. and Eboreime, I.V. (2013). Analysis of nonexcusable delay factors influencing contractors’ performance in Lagos State, Nigeria. Journal of Construction in Developing Countries, 18(1): 53–72.
Kikwasi, G. (2013). Causes and effects of delays and disruptions in construction projects in Tanzania. Australasian Journal of Construction Economics and Building – Conference Series, 1(2): 52–59. https://doi.org/10.5130/ajceb-cs.v1i2.3166
Le-Hoai, L., Lee, Y.D. and Lee, J.Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering, 12(6): 367–377. https://doi.org/10.1007/s12205-008-0367-7
Murray, M., Seif, M. and Umaru, W. (2013). Causes of project delay in Nigerian construction industry. European Journal of Civil Engineering and Architecture, 10: 1–7.
Ministry of Public Works and Housing (2020). Kebijakan dan perubahan di sektor jasa konstruksi di masa pandemi. Buletin Konstruksi, Vol. 4. Available at: https://binakonstruksi.pu.go.id/storage/Buletin_2020-edisi-4.pdf [Accessed on 24 December 2020].
Njogu, P.M. (2015). Assessment of effects of construction risks on project delivery among contractors in Kenya construction project management. MSc diss. Jomo Kenyatta University of Agriculture and Technology. Available at: http://ir.jkuat.ac.ke/bitstream/handle/123456789/1798/PeterMSc2015.pdf?sequence=1&isAllowed=y [Accessed on 10 December 2020].
PMI (Project Management Institute) (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide). 6th Ed. Newtown Square, PA: Project Management Institute.
Sudirman, W.B. and Hardjomuljadi, S. (2011). Project risk management in hydropower plant projects: A case study from the state-owned electricity company of Indonesia. Journal of Infrastructure Development, 3(2): 171–186. https://doi.org/10.2139/ssrn.1853943
Susetyo, B. and Utami, T.B. (2017). Bidding cost evaluation with fuzzy methods on building project in Jakarta. Proceedings: 3rd International Conference on Construction and Building Engineering (ICONBUILD) 2017: Smart Construction Towards Global Challenges, 1903(1): 070004. https://doi.org/10.1063/1.5011573
Sweis, G.J. (2013). Factors affecting time overruns in public construction projects: The case of Jordan. International Journal of Business and Management, 8(23): 120–129. https://doi.org/10.5539/ijbm.v8n23p120
Tumi, S.A.H., Omran, A. and Pakir, A.H.K. (2009). Causes of delay in construction industry in Libya. In The International Conference on Economics and Administration. Bucharest, Romania: The Faculty of Administration and Business, 265–272.
Ullah, K., Abdullah, A.H., Nagapan, S., Suhoo, S. and Khan, M.S. (2017). Theoretical framework of the causes of construction time and cost overruns. IOP Conference Series: Materials Science and Engineering, 271: 012032. https://doi.org/10.1088/1757-899X/271/1/012032
Zidane, Y.J. and Andersen, B. (2018). The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business, 11(3): 650–672. https://doi.org/10.1108/IJMPB-05-2017-0052