Critical Delay Factors in Typical Physical Projects: The Case of the Ministry of Home Affairs in Malaysia

Main Article Content

Aishatul Izwani Aminorlah
Noorlizawati Abd Rahim
Zainai Mohamed
Ain Naadia Mazlan

Abstract

In Malaysia, public projects have been consistently reported as dilapidated and delayed, causing the government to bear financial losses. Furthermore, the purposes of the projects have not been fully achieved, thus affecting the public interest. This study examined the critical contributing factors to the delay in implementing physical projects in the Ministry of Home Affairs (MOHA). The scope involved the physical construction projects of the Immigration Department of Malaysia’s offices and premises in Malaysia, which was mandated in the 11th Malaysia Plan. A total of 105 respondents, including contractors, consultants, endusers and clients, participated in a survey on the factors and effects of physical project delay. The data were analysed using the relative importance index (RII) and Spearman’s correlation to identify the most critical delay factors and their association with delay effects. A total of 38 delay factors were identified, with contractor-related factors being the most critical, followed by consultant-related, client-related and other factors. These delay factors were found to be positively correlated with the effects of delay, including time and cost overrun, quality, litigation and arbitration, and abandonment.

Article Details

How to Cite
Aishatul Izwani Aminorlah, Noorlizawati Abd Rahim, Zainai Mohamed, and Ain Naadia Mazlan. 2023. “Critical Delay Factors in Typical Physical Projects: The Case of the Ministry of Home Affairs in Malaysia”. Journal of Construction in Developing Countries 28 (2): 57–79. https://doi.org/10.21315/.
Section
Articles

References

Aibinu, A.A. and Jagboro, G.O. (2002). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management, 20(8): 593–599. https://doi.org/10.1016/S0263-7863(02)00028-5

Al-Adwani, M.M., Mollasalehi, S. and Fleming, A.J. (2018). A study of root causes of delays in the public-sector construction projects in Kuwait. In Proceedings: International Conference on Construction Futures (ICCF). Wolverhampton, UK: ICCF. Available at: https://salford-repository.worktribe.com/output/1372961/a-study-of-root-causes-of-delays-in-the-public-sector-construction-projects-in-kuwait

Al-Kharashi, A. and Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1): 3–23. https://doi.org/10.1080/01446190802541457

Alsulaiti, A.A. and Kerbache, L. (2020). Analysis of critical delay factors in construction projects with a focus on Qatar. International Journal of Business and Economics Research, 9(3): 130–139. https://doi.org/10.11648/j.ijber.20200903.16

Alsuliman, J.A.(2019). Causes of delay in Saudi publicconstructionprojects. Alexandria Engineering Journal, 58(2): 801–808. https://doi.org/10.1016/j.aej.2019.07.002

Amoatey, C.T., Ameyaw, Y.A., Adaku, E. and Famiyeh, S. (2015). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business, 8(1): 198–214. https://doi.org/10.1108/IJMPB-04-2014-0035

Anyanwu, C.I. (2013). The role of building construction project team members in building projects delivery. Journal of Business and Management, 14(1): 30–34. https://doi.org/10.9790/487x-1413034

Arantes, A., da Silva, P.D. and Ferreira, L.M. (2015). Delays in construction projects-causes and impacts. In J.M. Framinan, P.P. Gonzalez and A. Artiba (eds.), 2015 International Conference on Industrial Engineering and Systems Management (IESM). Seville, Spain: IEEE, 1105–1110. https://doi.org/10.1109/IESM.2015.7380293

Aswathy, M.S., Mittal, A. and Behera, S. (2020). Effect of excavation on the settlement of adjacent structures. Construction in Geotechnical Engineering, 713–722. https://doi.org/10.1007/978-981-15-6090-3_53

Azhar, S. (2019). The causes of project delay in the Ministry of Defence, Malaysia. PhD diss. Universiti Teknologi Malaysia.

Aziz, R.F. and Abdel-Hakam, A.A. (2016). Exploring delay causes of road construction projects in Egypt. Alexandria Engineering Journal, 55(2): 1515–1539. https://doi.org/10.1016/j.aej.2016.03.006

Brookes, N. (2013). Construction project management. Construction Management and Economics, 31(9): 1019–1020. https://doi.org/10.1080/01446193.2013.787488

Chandu, A., Sheetal, P. and Bhalerao, N.V. (2016). A methodology for ranking of causes of delay for residential projects. International Research Journal of Engineering and Technology (IRJET), 3(6): 224–231.

Department of Statistics Malaysia (2019). Malaysia’s quarter construction statistics. Available at: https://www.dosm.gov.my/v1/index.php

Duma, H. (2012). The relationship between general contractor and subcontractor. MSc diss. Universiti Teknologi Malaysia.

Economic Planning Unit (EPU) (2015). Eleventh Malaysia Plan 2016–2020. Putrajaya: EPU. Available at: http://rmk11.epu.gov.my/book/eng/Elevent-Malaysia-Plan/RMKe-11Book.pdf.2015

Gebrehiwet, T. and Luo, H. (2017). Analysis of delay impact on construction project based on RII and correlation coefficient: Empirical study. Procedia Engineering, 196: 366–374.

Ghasemzadeh, B. (2014). Investigating causes of delays in Iranian construction industry according to project delivery methods. PhD diss. Eastern Mediterranean University.

Głuszak, M. and Leśniak, A. (2015). Construction delays in client’s opinion: Multivariate statistical analysis. Procedia Engineering, 123: 182–189. https://doi.org/10.1016/j.proeng.2015.10.075

Gomarn, P. and Pongpeng, J. (2018). Causes of construction delay from contractors and suppliers in Thailand’s oil and gas platform projects. MATEC Web of Conferences, 192: 02008. https://doi.org/10.1051/matecconf/201819202008

Goodwin, L.D. and Leech, N.L. (2006). Understanding correlation: Factors that affect the size of r. The Journal of Experimental Education, 74(3): 249–266. https://doi.org/10.3200/JEXE.74.3.249-266

Guida, P.L. and Sacco, G. (2019). A method for project schedule delay analysis. Computers and Industrial Engineering, 128: 346–357. https://doi.org/10.1016/j.cie.2018.12.046

Halim, M.S., Jaafar, M., Osman, O. and Akbar, S. (2010). The contracting firm’s failure and financial related factors: A case study of Malaysian contracting firms. International Research Journal of Finance and Economics, 52: 28–39.

Hisham, S.N.A. and Yahya, K. (2016). Causes and effects of delays in construction industry. Construction Management, Geotechnics and Transportation, 2: 78–89.

Idrus, N.A., Ismail, S. and Saleh, A.L. (2020). Causes of government physical project delays in Prime Minister’s Department, Malaysia. In M. Awang and M.M.M. Fared (eds.), ICACE 2019. Singapore: Springer, 201–206.

Jatarona, N.A., Md Yusof, A., Ismail, S. and Saar, C.C. (2016). Public construction projects performance in Malaysia. Journal of Southeast Asian Research: 1–7. https://doi.org/10.5171/2016.940838

Johnson, K.T. (2017). The training deficiency in corporate America: Training security professionals to protect sensitive information. PhD diss. Walden University.

Kementerian Dalam Negeri (KDN) (2019). Peruntukan RMK 11. Available at: http://www.moha.gov.my

Khair, K., Mohamed, Z., Mohammad, R., Farouk, H. and Ahmed, M.E. (2018). A management framework to reduce delays in road construction projects in Sudan. Arabian Journal for Science and Engineering, 43(4): 1925–1940. https://doi.org/10.1051/e3sconf/20186503004

Khan, R.A., Liew, M.S. and Ghazali, Z. (2014). Malaysian construction sector and Malaysia vision 2020: Developed nation status. Procedia – Social and Behavioral Sciences, 109: 507–513. https://doi.org/10.1016/j.sbspro.2013.12.498

Khoiry, M.A., Kalaisilven, S. and Abdullah, A. (2018). A review of minimising delay in construction industries. E3S Web of Conferences. EDP Sciences, 65: 03004. https://doi.org/10.1051/e3sconf/20186503004

Krejcie, R.V. and Morgan, D.W. (1970). Determining sample size for research activities. Educational and Psychological Measurement, 30(3): 607–610.

Mohammad, N. and Hamzah, Z. (2019). A review of causes of variation order in the constructionofterracehousingprojectsinMalaysia.MATECWebofConferences, 277: 03013. https://doi.org/10.1051/MATECCONF%2F201927703013

Nasir, N.M., Nawi, M.N.M., Rahim, M.K.I.A., Bahaudin, A.Y. and Tapa, A. (2016). A review of delay factors in Malaysian Industrialized Building System (IBS) construction project. ARPN Journal of Engineering and Applied Sciences, 11(16): 9868–9873.

Nguyen, L.D., Ogunlana, S.O. and Lan, D.T.X. (2004). A study on project success factors in large construction projects in Vietnam. Engineering, Construction and Architectural Management, 11(6): 404–413. https://doi.org/10.1108/09699980410570166

Orangi, A., Palaneeswaran, E. and Wilson, J. (2011). Exploring delays in Victoria-based Australian pipeline projects. Procedia Engineering, 14: 874–881. https://doi.org/10.1016/j.proeng.2011.07.111

Project Management Institute (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide). 6th Ed. Pennsylvania, USA: Project Management Institute.

Pulmanis, E. (2015). Micro-economical aspects of public projects: Impact factors for project efficiency and sustainability. Sixth International Scientific Conference on Project Management in the Baltic Countries, 3(1): 272–285.

Rafat, K.F. and Ahmed, R. (2017). Empirical study on causes of project delays. International Journal of Social, Behavioral, Educational, Economic, Business and Industrial Engineering, 10(1): 166–174. https://doi.org/10.5281/zenodo.1339822

Rashid, Y. (2020). Analysis of delay factors and their effects on construction projects. Management Science Letters, 10(6): 1197–1204. https://doi.org/10.5267/j.msl.2019.11.039

Riazi, M., Riazi, S. and Lamari, F. (2013). Public sector project delay: The Malaysian perspective and the way forward. Paper presented at the CIB World Building Congress 2013. Brisbane, Australia, 5–9 May.

Salim, M.S., Zakaria, R., Aminuddin, E., Hamid, A.R.A., Abdullah, R. and Khan, J.S. (2018). The factors impacted to local contractor from Foreign Direct Investment in advancing economic hub development in Iskandar Malaysia. IOP Conference Series: Earth and Environmental Science. IOI Publishing, 143(1): 012034. https://doi.org/10.1088/1755-1315/143/1/012034

Sambasivan, M., Deepak, T.J., Salim, A.N. and Ponniah, V. (2017). Analysis of delays in Tanzanian construction industry: Transaction cost economics (TCE) and structural equation modeling (SEM) approach. Engineering, Construction and Architectural Management, 24(2): 308–325. https://doi.org/10.1108/ECAM-09-2015-0145

Senouci, A., Ismail, A. and Eldin, N. (2016). Time delay and cost overrun in Qatari public construction projects. Procedia Engineering, 164: 368–375. https://doi.org/10.1016/j.proeng.2016.11.632

Shah, R.K. (2016). An exploration of causes for delay and cost overrun in construction projects: A case study of Australia, Malaysia and Ghana. Journal of Advanced College of Engineering and Management, 2(1): 41–55. https://doi.org/10.3126/jacem.v2i0.16097

Shahsavand, P., Marefat, A. and Parchamijalal, M. (2018). Causes of delays in construction industry and comparative delay analysis techniques with SCL protocol. Engineering, Construction and Architectural Management, 25: 497–533. https://doi.org/10.1108/ECAM-10-2016-0220

Singh, S., Bala, A., Dixit, S. and Varshney, D. (2018). Critical analysis of causes of delay in residential construction projects in India. International Journal of Civil Engineering and Technology, 9(1): 330–345.

Tafazzoli, M. and Shrestha, P.P. (2017). Investigating causes of delay in U.S. construction projects. In 53rd ASC Annual International Conference. Seattle, Washington: Associated Schools of Construction, 611–621.

Thomas, A.V. and Sudhakumar, J. (2013). Critical analysis of the key factors affecting construction labour productivity: An Indian perspective. International Journal of Construction Management, 13(4): 103–125. https://doi.org/10.1080/15623599.2013.10878231

Van, L.T., Sang, N.M. and Viet, N.T. (2015). A conceptual model of delay factors affecting government construction projects. ARPN Journal of Science and Technology, 5(2): 92–100.

Varghese, A.R. and Varghese, S. (2015). Analysis of delays in construction projects. International Journal of Engineering Research and General Science, 3(6): 108–112.