Improvement of Risk Management in Cost Estimation in the Building Construction Industry in Uganda
Main Article Content
Abstract
The cost performance of construction projects is a crucial success factor. However, risks in construction projects make exact budgetary requirements challenging to forecast accurately, resulting in underestimation and overestimation. Inaccurate cost estimates could further result in unnecessary financial loss to project stakeholders and the loss of reputation and trustworthiness of construction professionals. In Uganda, risk factors are either ignored or subjectively taken care of by simply allowing a contingency figure ranging from 0% to 10% of the project cost. However, this method is sometimes unreliable and difficult to justify to project owners. Therefore, there is a need for a reliable and justifiable risk-based cost estimation method. The current study aimed to improve risk management in cost estimation in the building construction industry in Uganda. The specific objectives were to establish the risk factors, assess the effects of the risk factors and develop a reliable model that can be used for risk-based cost estimation in the building construction industry in Uganda. The study adopted a mixed-method approach by utilising quantitative and qualitative research methods. The collection of data was done using a self-administered questionnaire and an interview guide. The data was first sorted, coded and entered for analysis using the Statistical Package for the Social Sciences (SPSS) and Microsoft Excel. The risk factors in cost estimation were identified through a detailed literature review. The study revealed that the top five risk factors influencing cost estimation were: cost of materials, inflation, fraudulent practices and kickbacks, incomplete scope definition, and incomplete design and specification. The study concluded that the risk factors with the most severe effects on cost estimation were inflation, proficiency in estimating, cost of materials, incomplete design and specification, fraudulent practices and kickbacks. The study proposed a model developed using the analytic hierarchy process (AHP). The study recommends more research on the efficiency and effectiveness of risk-based cost estimation models.
Article Details

This work is licensed under a Creative Commons Attribution 4.0 International License.
References
AACE (Association for the Advancement of Cost Engineering) (2013). 10s–90:
AACE recommended practice and standard cost engineering terminology.
Available at: https://web.aacei.org/docs/default-source/rps/10s-90.pdf?sfvrsn=2fcaddb5_75 [Accessed on 14 March 2023].
Abd Karim, N.A., Rahman, I.A., Memmon, A.H., Jamil, N. and Azis, A.A.A. (2012).
Significant risk factors in construction projects: Contractor’s perception. In
IEEE Colloquium on Humanities, Science and Engineering (CHUSER).
Sabah, Malaysia: IEEE, 347–350.
Abdel-Monem, M., Alshaer, K.T. and El-Dash, K. (2022). Assessing risk factors affecting
the accuracy of conceptual cost estimation in the Middle East. Buildings,
(7): 950. https://doi.org/10.3390/buildings12070950
Adesi, M., Owusu-Manu, D.G. and Boateng, F. (2019). Segmentation of quantity
surveying professional services for focus strategy and diversification. Journal
of Financial Management of Property and Construction, 24(3): 294–308.
https://doi.org/10.1108/JFMPC-09-2018-0052
Ajator, U.O. (2017). Evaluation of risk factors affecting cost performance of
construction projects in Jalingo, Taraba State. International Journal of Civil,
Mechanical and Energy Science (IJCMES), 3(2): 138–153.
_____. (2014). Financial engineering and project risk management: Imperatives for
professional quantity surveyors. Journal of Environment and Earth Science, 4: 23.
Akinshin, A. (2021). Using Kish’s effective sample size with weighted quantiles. Available
at: https://aakinshin.net/posts/kish-ess-weighted-quantiles/#Kish1965
[Accessed on 14 March 2023].
Albtoush, A.M.F. and Doh, S.I. (2019). A review on causes of cost overrun in the
construction projects. International Journal of New Innovations in Engineering
and Technology, 12(3): 15–22.
Aljohani, A., Ahiaga-Dagbui, D. and Moore, D. (2017). Construction projects cost
overrun: What does the literature tell us? International Journal of Innovation,
Management and Technology, 8(2): 137.
Allahaim, F.S., Liu, L. and Kong, X. (2016). Developing risk-based cost contingency
estimation model based on the influence of cost overrun causes. CIB World
Building Congress, 1: 726–739.
Asal, E.M. (2014). Factors affecting building construction projects cost estimating.
Arab MSc diss. Arab Academy for Science, Technology and Maritime
Transport (AASTMT).
Ashmawi, K., Hadidi, L.A., Assaf, S., Tuffaha, F.M. and Al-Ofi, K. (2018). Risk assessment
and allocation in the contract for public works used in Saudi Arabia
construction industry. Cogent Engineering, 5(1): 1–21. https://doi.org/10.1080/23311916.2018.1490148
Atapattu, C., Domingo, N. and Sutrisna, M. (2023). Causes and effects of cost
overruns in construction projects. Paper presented at the 45th Australasian
Universities Building Education Association Conference. Western Sydney
University, Sydney, 23–25 November.
Bahati, C.M. and Kwena, R. (2023). Critical aspects influencing the construction
projects’ performance in Rwanda: A case of Rubavu Modern Market. The
International Journal of Business Management and Technology, 7(1): 659–671.
Bolstein, A.R. and Crow, M. (2008). Statistical formulas and citations for EPA’s 2007
ERP sample planner and ERP results analyzer. EPA Contract Number EP-W-04-
, Work Assignment, 3–61.
Buertey, J.I.T. (2014). Project cost risk and uncertainties: Towards a conceptual
cost contingency estimation model. International Journal of Construction
Engineering and Management, 3(5): 144–155. https://doi.org/10.5923/j.ijcem.20140305.02
Butcher, N. and Demmers, L. (2003). Cost Estimating Simplified. California: Libris
Design Project.
Challal, A. and Tkiouat, M. (2012). The design of cost estimating model of construction
project: Application and simulation. Open Journal of Accounting, 1: 15–26.
https://doi.org/10.4236/ojacct.2012.11003.
Chapman, R.J. (2001). The controlling influences on effective risk identification
and assessment for construction design management. International Journal
of Project Management, 19(3): 147–160. https://doi.org/10.1016/s0263-7863(99)00070-8
Chileshe, N. and Kikwasi, G.J. (2013). Perception of barriers to implementing risk
assessment and management practices by construction professionals
in Tanzania. In Proceedings: 29th Annual Association of Researchers in
Construction Management Conference, ARCOM 2013. Reading: ARCOM,
–1146.
Choon, T.T. and Ali, K.N. (2008). A review of potential areas of construction cost
estimating and identification of research gaps. Journal Alam Bina, 11(2): 61–72.
CoST (2017). The 1st Assurance Report: Uganda. Kampala: CoST Uganda Chapter.
Dlamini, M. and Cumberlege, R. (2021). The impact of cost overruns and delays in
the construction business. IOP Conference Series: Earth and Environmental
Science, 654(1): 012029. https://doi.org/10.1088/1755-1315/1202/9/012029
Doloi, H. (2012). Cost overruns and failure in project management: Understanding
the roles of key stakeholders in construction projects. Journal of Construction
Engineering and Management, 139(3): 267–279. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000464
Easwaramoorthy, M. and Zarinpoush, F. (2006). Interviewing for research. Available
at: https://sectorsource.ca/sites/default/files/resources/files/tipsheet6_interviewing_for_research_en_0.pdf [Accessed on 14 March 2023].
Eja, K.M. and Ramegowda, M. (2020). Government project failure in developing
countries: A review with particular reference to Nigeria. Global Journal of
Social Sciences, 19: 35–47.
El-Touny, A.S., Ibrahim, A.H. and Amer, M.I. (2014). Estimating cost contingency for
highway construction projects using analytic hierarchy process. International
Journal of Computer Science Issues, 11(6): 73.
Gordon, N., Davidoff, F., Tarnow, E., Reidenberg, M.M. and Endriss, K. (2002). A
question of response rate. Science, 25(1): 25.
Haggarty, L. (1996). What is content analysis? Medical Teacher, 18(2): 99–101.
https://doi.org/10.3109/01421599609034141
Hatamleh, M.T., Hiyassat, M., Sweis, G.J. and Sweis, R.J. (2018). Factors affecting the
accuracy of cost estimate: Case of Jordan. Engineering, Construction and
Architectural Management, 25. https://doi.org/10.1108/ECAM-10-2016-0232.
Herszon, L. and Keraminiyage, K. (2014). Dimensions of project complexity and their
Impact on cost estimation. Paper presented at PMI® Global Congress 2014.
Phoenix, Arizona, 26 October.
Ibrahim, A. and Mohamed, L. (2021). Factors affecting the accuracy of construction
project cost estimation in Egypt. Jordan Journal of Civil Engineering, 15: 329–
https://doi.org/10.23883/ijrter.2017.3161.rrkha
Idrus, A., Nuruddin, M. and Rohman, M. (2011). Development of project cost
contingency estimation model using risk analysis and fuzzy expert system.
Expert Systems with Applications, 38: 1501–1508. https://doi.org/10.1016/j.eswa.2010.07.061
International Organization for Standardization (2009). ISO 31000: 2009: Risk
Management: Principles and Guidelines. Geneva: International Organization
for Standardization.
Kamau, S., Gesimba, P.O. and Gichuhi, D. (2022). Cost control and realization of
national government constituencies development fund projects in Kikuyu
constituency, Kiambu County, Kenya. International Journal of Research
in Business and Social Science (2147–4478), 11(7): 226–233. https://doi.org/10.20525/ijrbs.v11i7.1628
Kepher, J.A., Nyonje, R.O. and Rambo, C.M. (2022). Negotiation Strategies on
Construction Cost Overruns in Real Estate Projects: Nairobi and Kisumu
counties, Kenya. Available at: https://journalspress.com/negotiationstrategies-0n-construction-cost-overruns-in-real-estate-projects-nairobi-andkisumu-counties-kenya/ [Accessed on 14 March 2023].
Kibwami, N. (2020). Predicting cost over-run of building projects using public
procurement requirements: A case of Uganda. International Journal
of Construction Engineering and Management, 9: 171–181. https://doi.org/10.5923/j.ijcem.20200905.04.
Kish, L. (1965). Survey Sampling. New York: John Wiley & Sons, Inc.
Kwoyigah, D., Alagidede, I.P. and Amidu, S. (2021). Cost performance and
management styles in construction projects in the Techiman Municipality.
Journal of Construction and Built Environment, 1(1): 10–25.
Lavrakas, P.J. (2008). Self-administered questionnaire. In P.J. Lavrakas (ed.),
Encyclopedia of Survey Research Methods. Thousand Oaks, CA: Sage
Publications, 809–810.
Mahamid, I. (2014). Factors affecting cost estimate accuracy: Evidence from
Palestinian construction projects. International Journal of Management
Science and Engineering Management, 10: 1–9. https://doi.org/10.1080/17509653.2014.925843
Miller, R. and Lessard, D. (2001). Understanding and managing risks in large
engineering projects. International Journal of Project Management, 19(8):
–443. https://doi.org/10.1016/S0263-7863(00)00045-X
Nevada DOT (2021). Risk management and risk-based cost estimation
guidelines. Available at: https://www.dot.nv.gov/home/
showpublisheddocument/4518/637637657516400000 [Accessed on 14 March
.
Nguyen, P.T., Pham, C.P., Phan, P.T., Vu, N., Duong, M.T.H. and Nguyen, Q.L.H.T.T.
(2021). Exploring critical risk factors of office building projects. The Journal
of Asian Finance, Economics and Business, 8(2): 309–315. https://doi.org/10.13106/jafeb.2021.vol8.no2.0309