Construction Disputes Causes and Resolution Methods: A Case Study from a Developing Country
Main Article Content
Abstract
The increasing complexity of the construction industry, characterised by diverse multidisciplinary project teams, various stakeholders, distinctive site conditions and uncertainties, can contribute to an antagonistic environment, which may result in disputes arising between the contractual parties. Identifying the most common causes of disputes is important for an efficient contract management process. This study aims to help project stakeholders incorporate consolidative contract management strategies before commencing a new project by identifying the most common causes of construction disputes in Jordanian construction projects. Key causative factors of disputes were analysed through a literature review, a questionnaire survey and a case study analysis of construction projects in Jordan. The results revealed that the main factors leading to disputes in Jordan are incomplete technical drawings/specifications, variations initiated by the owner/consultant (additive/ deductive) and errors and omissions in the contract documents. Moreover, the results show that the most popular methods of dispute resolution in the Jordanian construction industry are negotiation and arbitration. The findings can enable local and international construction stakeholders to initiate contract management strategies before commencing projects. More effective planning can help to reduce the negative impacts of known causes of disputes.
Article Details

This work is licensed under a Creative Commons Attribution 4.0 International License.
References
Abwunza, A., Kivaa, T. and Muigua, K. (2021). Explaining the effectiveness of
construction arbitration: An organizational justice perspective. Journal of
Legal Affairs and Dispute Resolution in Engineering and Construction, 13:
https://doi.org/10.1061/(ASCE)LA.1943-4170.0000479
Acharya, N.K., Lee, Y.D. and Kim, J.K. (2006). Critical construction conflicting
factors identification using analytical hierarchy process. KSCE Journal of Civil
Engineering, 10: 165−174. https://doi.org/10.1007/BF02824057
Adnan, H., Shamsuddin, S.M., Supardi, A. and Ahmad, N. (2012). Conflict prevention
in partnering projects. Procedia − Social and Behavioral Sciences, 35: 772−781.
https://doi.org/10.1016/j.sbspro.2012.02.148
Alamri, N., Amoudi, O. and Njie, G. (2017). Analysis of construction delay causes in
dams projects in Oman. European Journal of Business and Social Sciences,
(2): 19−42.
Alkhamali, K., Motawa, I. and Ogunlana, S.O. (2010). Cultural factors influencing
disputes in public construction. In P. Barrett, D. Amaratunga, R. Haigh, K.
Keraminiyage and C. Pathirage (eds.), Proceedings W113 − Special Track
th CIB World Building Congress 2010. Salford: Commercial International
Bank, 475−488.
Almutairi, S., Kashiwagi, J., Kashiwagi, D. and Sullivan, K. (2015). Factors causing
construction litigation in Saudi Arabia. Journal for the Advancement of
Performance Information and Value, 7: 58.
Alshahrani, S. (2017). Dispute resolution methods in the construction industry sector
in the Kingdom of Saudi Arabia. MATEC Web of Conferences, 138: 02015.
Aryal, S. (2018). A review of causes and effects of dispute in the construction projects
of Nepal. Journal of Steel Structure and Construction and Building Materials,
: 144. https://doi.org/10.4172/2472-0437.1000144
Assaf, S., Hassanain, M.A., Abdallah, A., Sayed, A.M.Z. and Alshahrani, A. (2019).
Significant causes of claims and disputes in construction projects in Saudi
Arabia. Built Environment Project and Asset Management, 9(5): 597−615.
https://doi.org/10.1108/BEPAM-09-2018-0113
Awwad, R., Barakat, B. and Menassa, C. (2016). Understanding dispute resolution
in the Middle East region from perspectives of different stakeholders. Journal
of Management in Engineering, 32: 05016019. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000465
Cakmak, E. and Irlayici Cakmak, P. (2014). An analysis of causes of disputes in
the construction industry using analytical network process (ANP). Procedia
− Social and Behavioral Sciences, 109: 183–187. https://doi.org/10.1016/j.sbspro.2013.12.441
Cooper, R., Moss, P., Williams, R.N., Kitt. G. and Recan, J. (2017). Global Construction
Disputes Report 2017 − Avoiding the Same Pitfalls. North America: Arcadis.
Dada, M. (2013). Frequency of conflicts in construction project procurement: A
correlation analysis. International Journal of Construction Supply Chain
Management, 3(1): 1−15. https://doi.org/10.14424/ijcscm301013-01-15
Daoud, O.E.K. and Azzam, O.M. (1999). Sources of disputes in construction contracts
in the Middle East. Technology, Law and Insurance, 4(1−2): 87−93. https://doi.org/10.1080/135993799349171
Davis, P., Ellis, J. and Cheung, S. (2010). Dispute causation: Identification of pathogenic
influences in construction. Engineering, Construction and Architectural
Management, 17(4): 404−423. https://doi.org/10.1108/09699981011056592
Dmaidi, N. (2013). Construction contracting management obstacles in Palestine.
International Journal of Construction Engineering and Management, 2:
−22. https://doi.org/10.5923/j.ijcem.20130201.03
Ejohwomu, O., Oshodi, O. and Onifade, M.K. (2016). Causes of conflicts in
construction projects in Nigeria: Consultant’s and contractor’s perspective.
Nigerian Journal of Technology, 35(2): 270. http://dx.doi.org/10.4314/njt.v35i2.6
El-Razek, M.A., Bassioni, H. and Mobarak, A.M. (2008). Causes of delay in building
construction projects in Egypt. Journal of Construction Engineering and
Management, 134(11): 831–841. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831)
El-Sayegh, S., Ahmad, I., Aljanabi, M., Herzallah, R., Metry, S. and El-Ashwal, O. (2020).
Construction disputes in the UAE: Causes and resolution methods. Buildings,
(10): 171. https://doi.org/10.3390/buildings10100171
Enshassi, A., Choudhry, R.M. and El-Ghandour, S. (2009). Contractors’ perception
towards causes of claims in construction projects. International Journal of
Construction Management, 9: 79−92. https://doi.org/10.1080/15623599.2009.10773123
Exactitude Consultancy (2022). Construction industry market is expected to be worth
USD 17,247.96 billion by 2029, growing at a 7.3% annual rate. Available at:
https://www.globenewswire.com/en/news-release/2022/08/23/2502951/0/en/Construction-Industry-Market-Is-Expected-To-Be-Worth-USD-17-247-96-Billion-by-2029-Growing-At-A-7-3-Annual-Rate.html#:~:text=The%20size%20of%20the%20global,USD%2011%2C561.40%20billion%20in%202020 [Accessedon 1 February 2023].
Getahun, A., Macarubbo, Y. and Legese, A. (2016). Assessment of construction
dispute resolution in Ethiopian Somali regional state road projects: A case
study on road projects in the region. American Journal of Civil Engineering,
(6): 282−289. https://doi.org/10.11648/j.ajce.20160406.13
Gharaibeh, L.G., Matarneh, S.T., Arafeh, M. and Sweis, G. (2021). Factors leading
to design changes in Jordanian construction projects. International Journal
of Productivity and Performance Management, 70(4): 893−915. https://doi.org/10.1108/IJPPM-08-2019-0412
Hadikusumo, B.H.W. and Tobgay, S. (2015). Construction claim types and causes
for a large-scale hydropower project in Bhutan. Journal of Construction in
Developing Countries, 20(1): 49−63.
Hardjomuljadi, S. (2014). Factor analysis on causal of construction claims and
disputes in Indonesia (with reference to the construction of hydroelectric
power project in Indonesia). International Journal of Applied Engineering
Research, 9(22): 12421−12446.
Harmon, K.M. 2009. Case study as to the effectiveness of dispute review boards
on the Central Artery/Tunnel Project. Journal of Legal Affairs and Dispute
Resolution in Engineering and Construction, 1(1): 18−31. https://doi.
org/10.1061/(ASCE)1943-4162(2009)1:1(18)
Hassanein, A.A.G. and El Nemr, W. (2007). Management of change order
claims in the Egyptian industrial construction sector. Journal of Financial
Management of Property and Construction, 12(1): 45−60. https://doi.org/10.1108/13664380780001093
Hosseinian, S.S. and Torghabeh, Z.J. (2012). Major theories of construction accident
causation models: A literature review. International Journal of Advances in
Engineering and Technology, 4(2): 53–66.
Jaffar, N., Tharim, A.H.A. and Shuib, M.N. (2011). Factors of conflict in construction
industry: A literature review. Procedia Engineering, 20: 193−202. https://doi.org/10.1016/j.proeng.2011.11.156
Kalyan, H.S. and Prakash, A. (2019). Case studies on dispute resolutions in construction
projects for framing an expert solution B. International Journal of Recent
Technology and Engineering, 8(1): 476–483.
Kassab, M., Hipel, K. and Hegazy, T. (2006). Conflict resolution in construction
disputes using the graph model. Journal of Construction Engineering and
Management, 132(10): 1043−1052. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:10(1043)
Kish, L. (1965). Survey Sampling. New York: John Wiley & Sons, Inc.
Klinger, M. (2009). Confronting construction conflicts electrical construction and
maintenance. Available at: https://www.ecmweb.com/maintenancerepairoperations/article/20891433/confronting-construction-conflicts
[Accessed on 1 March 2023].
Marzouk, M., El-Mesteckawi, L. and El-Said, M. (2011). Dispute resolution aided tool for
construction projects in Egypt. Journal of Civil Engineering and Management,
(1): 63−71. https://doi.org/10.3846/13923730.2011.554165
Mohamed, H.H., Ibrahim, A.H. and Soliman, A.A. (2014). Reducing construction
disputes through effective claims management. American Journal of Civil
Engineering and Architecture, 2(6): 186−196. https://doi.org/10.12691/ajcea-2-6-2
Moura, H.M.P. and Teixeira, J.M.C. (2010). Managing stakeholders conflicts. In E.
Chinyio and P. Olomolaiye (eds.), Construction Stakeholder Management.
West Sussex: Wiley-Blackwell, 286−316. https://doi.org/10.1002/9781444315349.ch17
Narh, O.C. (2015). An exploratory study of professional conflicts and disputes within
the construction industry. International Journal of Managerial Studies and
Research, 3(12): 44−65.
Project Management Institute (2017). A Guide to the Project Management Body
of Knowledge (PMBOK Guide). 6th Ed. Pennsylvania: Project Management
Institute, Inc.
Rumane, A.R. (2017). Quality Management in Construction Projects. Boca Raton,
FL: CRC Press.
Ruuska, I. and Teigland, R. (2009). Ensuring project success through collective
competence and creative conflict in public-private partnerships: A case study
of Bygga Villa, a Swedish triple helix e-government initiative. International
Journal of Project Management, 27(4): 323−334. https://doi.org/10.1016/j.ijproman.2008.02.007
Sabri, O., Lædre, O. and Bruland, A. (2019). Why conflicts occur in roads and tunnels
projects in Norway. Journal of Civil Engineering and Management, 25(3):
−264. https://doi.org/10.3846/jcem.2019.8566
Sambasivan, M. and Soon, Y.W. (2007). Causes and effects of delays in Malaysian
construction industry. International Journal of Project Management, 25:
−526. https://doi.org/10.1016/j.ijproman.2006.11.007
Sayed-Gharib, T., Price, A. and Lord, W. (2010). Improving dispute resolution on
construction projects in Kuwait. In Proceedings of 2010 18th CIB World Building
Congress Salford. Salford: International Council for Building.
Speaight, A. (ed.) (2010). Architect’s Legal Handbook: The Law for Architects. 9th
Ed. London: Architectural Press.
Statista (2022). Size of the global construction market from 2020 to 2021, with forecasts
from 2022 to 2030. Available at: https://www.statista.com/statistics/1290105/global-construction-market-size-with-forecasts/ [Accessed on 1 February 2023].
Tarawneh, S., Sarireh, M. and Tarawneh, E. (2020). Time and cost overruns in
Jordanian Building construction projects. Natural and Applied Sciences
Series, 35(1): 53−73.
Wilkinson, P. (2016). Middle East contract disputes are world’s largest. Available
at: https://www.meed.com/middle-east-contract-disputes [Accessed on 2 March 2023].
Yamane, T. (1967). Statistics, An Introductory Analysis. New York: Harper and Row.
Zaneldin, E.K. (2006). Construction claims in United Arab Emirates: Types, causes
and frequency. International Journal of Project Management, 24(5): 453−459.