Critical Factors Influencing the Performance of Public Housing Construction Projects in Myanmar
Main Article Content
Abstract
Public housing is a basic need for low- and middle-income families. Unfortunately, in many developing countries, housing construction projects often fall short of achieving the required performance levels. This problem occurs for many reasons: low budget, corruption, poor governance, inadequate policy and the lack of modern technologies used in construction. As a developing country, Myanmar is facing these challenges in public housing construction projects. Although many studies have investigated the factors influencing the performance of construction projects, there has been limited research focusing on public housing construction, particularly. Myanmar plans to provide one million homes by 2030. However, the country faces significant challenges, including political instability and the COVID-19 pandemic. This study attempted to identify the critical factors influencing the performance of public housing construction projects in Myanmar (PHCPM) amid the current changing circumstances. A survey was conducted to collect data from 86 experienced personnel on 51 factors identified in the literature review. The dataset was then analysed using a one-way analysis of variance (ANOVA) and frequency-adjusted important index (FAII) analysis method. The factors were ranked according to FAII scores and 10 critical factors were identified and discussed. The results of this study can help inform individuals responsible for taking action to mitigate the impact of the critical factors identified on improving the performance of PHCPM.
Article Details

This work is licensed under a Creative Commons Attribution 4.0 International License.
References
Aibinu, A.A. and Odeyinka, H.A. (2006). Construction delays and their causative
factors in Nigeria. Journal of Construction Engineering and Management,
(7): 667–677. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(667)
Akanni, P.O., Oke, A.E. and Akpomiemie, O.A. (2019). Impact of environmental
factors on building project performance in Delta State, Nigeria. HBRC Journal,
(1): 91–97. https://doi.org/10.1016/j.hbrcj.2014.02.010
Alaghbari, W.E., Salim, A., Dola, K. and Abdullah Abang Ali, A. (2009). Housing
shortage for low‐income in Yemen: causes and suggestions. International
Journal of Housing Markets and Analysis, 2(4): 363–372. https://doi.org/doi:10.1108/17538270910992809
Alzahrani, J.I. and Emsley, M.W. (2013). The impact of contractors’ attributes on
construction project success: A post-construction evaluation. International
Journal of Project Management, 31(2): 313–322. https://doi.org/10.1016/j.ijproman.2012.06.006
Amoatey, C.T., Ameyaw, Y.A., Adaku, E. and Famiyeh, S. (2015). Analysing delay
causes and effects in Ghanaian state housing construction projects.
International Journal of Managing Projects in Business, 8(1): 198–214. https://doi.org/10.1108/IJMPB-04-2014-0035
Amusan, L.M., Afolabi, A., Ojelabi, R., Omuh, I. and Okagbue, H.I. (2018). Data
exploration on factors that influences construction cost and time performance
on construction project sites. Data in Brief, 17: 1320–1325. https://doi.org/10.1016/j.dib.2018.02.035
Aragonés-Beltrán, P., García-Melón, M. and Montesinos-Valera, J. (2017). How to
assess stakeholders’ influence in project management? A proposal based on
the analytic network process. International Journal of Project Management,
(3): 451–462. https://doi.org/10.1016/j.ijproman.2017.01.001
Asian Development Bank (2019). Financing Affordable Housing in Yangon. https://doi.org/10.22617/TCS190167-2
Assaf, S.A. and Al-Hejji, S. (2006). Causes of delay in large construction projects.
International Journal of Project Management, 24(4): 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Bingol, B.N. and Polat, G. (2017). Measuring managerial capability of subcontractors
using a KPI model. Procedia Engineering, 196: 68–75. https://doi.org/ 10.1016/j.proeng.2017.07.174
Chadee, A.A., Martin, H.H., Mwasha, A. and Otuloge, F. (2022). Rationalizing critical
cost overrun factors on public sector housing programmes. Emerging Science
Journal, 6(3): 647–666. https://doi.org/10.28991/ESJ-2022-06-03-016
Chen, L., Lu, Q. and Han, D. (2023). A Bayesian-driven Monte Carlo approach for
managing construction schedule risks of infrastructures under uncertainty.
Expert Systems with Applications, 212: 118810. https://doi.org/10.1016/j.eswa.2022.118810
Cheng, M.-Y., Tsai, H.-C. and Sudjono, E. (2011). Evaluating subcontractor
performance using evolutionary fuzzy hybrid neural network. International
Journal of Project Management, 29(3): 349–356. https://doi.org/10.1016/j.ijproman.2010.03.005
Chileshe, N. and Yirenkyi‐Fianko, A.B. (2012). An evaluation of risk factors impacting
construction projects in Ghana. Journal of Engineering, Design and
Technology, 10(3): 306–329. https://doi.org/10.1108/17260531211274693
Cohen, J. (1988). Statistical Power Analysis for the Behavioral Sciences. New York:
Routledge. https://doi.org/10.4324/9780203771587
Denis, D.J. (2016). Applied Univariate, Bivariate and Multivariate Statistics. Hoboken,
NJ: Wiley. https://doi.org/10.1002/9781119583004
Dick-Sagoe, C., Lee, K.Y., Odoom, D. and Boateng, P.O. (2023). Stakeholder
perceptions on causes and effects of public project failures in Ghana.
Humanities and Social Sciences Communications, 10(1): 14. https://doi.org/10.1057/s41599-022-01497-7
Department of Population (2017). Thematic Report on Housing Conditions and
Household Amenities. Naypyidaw: Department of Population, The Republic
of the Union of Myanmar.
_____. (2015). The 2014 Myanmar Population and Housing Census, Union Report.
Census report vol. 2. Naypyidaw: Department of Population, The Republic of
the Union of Myanmar.
El-khalek, H.A., Aziz, R.F. and Morgan, E.S. (2019). Identification of construction
subcontractor prequalification evaluation criteria and their impact on
project success. Alexandria Engineering Journal, 58(1): 217–223. https://doi.org/10.1016/j.aej.2018.11.010
Enshassi, A., Mohamed, S. and Abushaban, S. (2009). Factors affecting the
performance of construction projects in the Gaza Strip. Journal of Civil
Engineering and Management, 15(3): 269–280.
Eom, C.S., Yun, S.H. and Paek, J.H. (2008). Subcontractor evaluation and
management framework for strategic partnering. Journal of Construction
Engineering and Management, 134(11): 842–851.
Garson, G.D. (2012). Testing Statistical Assumptions. Asheboro, NC: Statistical
Associates Publishing.
Gebrehiwet, T. and Luo, H. (2017). Analysis of delay impact on construction project
based on rii and correlation coefficient: Empirical study. Procedia Engineering,
: 366–374. https://doi.org/10.1016/j.proeng.2017.07.212
Gunduz, M. and Ahsan, B. (2018). Construction safety factors assessment through
Frequency Adjusted Importance Index. International Journal of Industrial
Ergonomics, 64: 155–162. https://doi.org/10.1016/j.ergon.2018.01.007
Gunduz, M., Nielsen, Y. and Özdemir, M. (2013). Quantification of delay factors
using the relative importance index method for construction projects in
Turkey. Journal of Management in Engineering, 29(2): 133–139. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129
Habitat for Humanity (2023). Affordable Housing. Available at: https://www.habitat.
org/emea/about/what-we-do/affordable-housing
Hair, J.F. (2009). Multivariate Data Analysis. 7th Ed. New York: Pearson.
Hansen, W.B. and Collins, L.M. (1994). Seven ways to increase power without
increasing N. American Psychological Association (APA). https://doi.org/10.1037/e495862006-008
Hashim, A.E., Samikon, S.A., Nasir, N.M. and Ismail, N. (2012). Assessing factors
influencing performance of Malaysian low-cost public housing in sustainable
environment. Procedia – Social and Behavioral Sciences, 50: 920–927. https://doi.org/10.1016/j.sbspro.2012.08.093
Hatmoko, J. and Scott, S. (2010). Simulating the impact of supply chain
management practice on the performance of medium-sized building
projects. Construction Management and Economics, 28: 35–49. https://doi.org/10.1080/01446190903365632
Hatmoko, J.U.D. and Khasania, R.R. (2016). Comparing performance of government
and private clients in construction projects: Contractors’ perspective. Civil
Engineering Dimension, 18(2): 85–92. https://doi.org/10.9744/ced.18.2.85-92
Hossen, M. M., Kang, S. and Kim, J. (2015). Construction schedule delay risk
assessment by using combined AHP-RII methodology for an international NPP
project. Nuclear Engineering and Technology, 47(3): 362–379. https://doi.org/10.1016/j.net.2014.12.019
Housing and Development Board (2023). Public housing: A Singapore icon. Available
Hwang, B.-G., Zhao, X. and Ng, S.Y. (2013). Identifying the critical factors affecting
schedule performance of public housing projects. Habitat International, 38:
–221. https://doi.org/10.1016/j.habitatint.2012.06.008
Jha, K. and Iyer, K. (2006). Critical factors affecting quality performance in
construction projects. Total Quality Management and Business Excellence,
(9): 1155–1170.
Jiboye, A. D. (2011). Evaluating public housing performance: providing a basis for
residential quality improvement in Nigeria. Middle-East Journal of Scientific
Research, 9(2): 225–232.
Japan International Cooperation Agency (2018). Myanmar data collection survey
on housing finance system report. Available at: https://openjicareport.jica.go.jp/pdf/12305769.pdf
Khodeir, L.M. and Mohamed, A.H.M. (2015). Identifying the latest risk probabilities
affecting construction projects in Egypt according to political and economic
variables: From January 2011 to January 2013. HBRC Journal, 11(1): 129–135.
https://doi.org/10.1016/j.hbrcj.2014.03.007
Kumar, R. (2018). Research Methodology: A Step-By-Step Guide for Beginners. New
York: Sage.
Larsen, J. K., Shen, G. Q., Lindhard, S. M. and Brunoe, T. D. (2016). Factors affecting
schedule delay, cost overrun and quality level in public construction projects.
Journal of Management in Engineering, 32(1). https://doi.org/10.1061/(ASCE)me.1943-5479.0000391
Larsson, J. (2018). The importance of hard project management and team
motivation for construction project performance. International Journal
of Managing Projects in Business, 11(2): 275–288. https://doi.org/10.1108/IJMPB-04-2017-0035
Latiffi, A.A., Mohd, S. and Brahim, J. (2015). Application of building information
modeling (BIM) in the Malaysian construction industry: A story of the first
government project. Applied Mechanics and Materials, 773: 996–1001
Le-Hoai, L., Lee, Y.D. and Lee, J.Y. (2008). Delay and cost overruns in Vietnam large
construction projects: A comparison with other selected countries. KSCE
Journal of Civil Engineering, 12(6): 367–377. https://doi.org/10.1007/s12205-008-0367-7
Lew, Y.-L., Hassim, S., Muniandy, R. and Hua, L.T. (2018). Structural equation modelling
for subcontracting practice: Malaysia chapter. Engineering, Construction
and Architectural Management, 25(7): 835–860. https://doi.org/10.1108/ECAM-04-2017-0073
Li, C.Z., Hong, J., Fan, C., Xu, X. and Shen, G.Q. (2018). Schedule delay analysis
of prefabricated housing production: A hybrid dynamic approach.
Journal of Cleaner Production, 195: 1533–1545. https://doi.org/10.1016/j.jclepro.2017.09.066
Luu, V.T., Kim, S.-Y., Tuan, N.V. and Ogunlana, S.O. (2009). Quantifying schedule
risk in construction projects using Bayesian belief networks. International
Journal of Project Management, 27(1): 39–50. https://doi.org/10.1016/j.ijproman.2008.03.003
Mahmud, A.T., Ogunlana, S.O. and Hong, W.T. (2021). Key driving factors of cost
overrun in highway infrastructure projects in Nigeria: A context-based
perspective. Journal of Engineering, Design and Technology, 19(6): 1530–
https://doi.org/10.1108/JEDT-05-2020-0171
Mandala, R.S.K. and Nayaka, R.R. (2023). A state of art review on time, cost and
sustainable benefits of modern construction techniques for affordable
housing. Construction Innovation [Forthcoming]. https://doi.org/10.1108/CI03-2022-0048
Maturana, S., Alarcón, L.F., Gazmuri, P. and Vrsalovic, M. (2007). On-site
subcontractor evaluation method based on lean principles and partnering
practices. Journal of Management in Engineering, 23(2): 67–74. https://doi.org/10.1061/(ASCE)0742-597X(2007)23:2(67)
McCarty, M. (2014). Introduction to public housing. Available at: https://digital.library.unt.edu/ark:/67531/metadc820996/
Mohamed, M. (2018). Assessing Egyptian construction projects performance
using principal component analysis. International Journal of Productivity
and Performance Management, 67(9): 1727–1744. https://doi.org/10.1108/IJPPM-06-2017-0134
Naing, M. (2021). Brief history of department of urban and housing development:
focal institution for housing sector in Myanmar. Current Urban Studies, 9(4):
–743. https://doi.org/10.4236/cus.2021.94043
Naing, Y.M., Tsai, S.L. and Kobayashi, H. (2021). Exploration of potential public
housing strategies for low-income households in Yangon, Myanmar. Paper
presented at 57th ISOCARP World Planning Congress. Doha, Qatar, 8–11
November.
Nasir, D., McCabe, B. and Hartono, L. (2003). Evaluating risk in construction schedule
model: Construction schedule risk model. Journal of Construction Engineering
and Management, 129(5): 518–527. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:5(518)
National Housing Authority (2023). Baan Eua-Arthon project. Available at: https://www.nha.co.th/en/
Ndou, V.D. (2004). E-government for developing countries: Opportunities and
challenges. he Electronic Journal of Information Systems in Developing
Countries, 18(1): 1–24. https://doi.org/10.1002/j.1681-4835.2004.tb00117.x
Ng, S.T. and Tang, Z. (2010). Labour-intensive construction sub-contractors: Their
critical success factors. International Journal of Project Management, 28(7):
–740. https://doi.org/10.1016/j.ijproman.2009.11.005
Nwal, S. and Panuwatwanich, K. (2018). Social housing in myanmar: Issues and
way forward. Paper presented at 2018 Joint Asia-Pacific Network for Housing
Research and Australasian Housing Researchers Conference Griffith University.
Gold Coast, Australia, 6–8 June.
Nyein, T.S. and Hadikusumo, B.H.W. (2021). Factors influencing the adoption of public–
private partnership in low-cost housing development in Myanmar. Journal
of Financial Management of Property and Construction, 26(3): 337–365.
https://doi.org/10.1108/jfmpc-01-2020-0003
Rachid, Z., Toufik, B. and Mohammed, B. (2019). Causes of schedule delays in
construction projects in Algeria. International Journal of Construction
Management, 19(5): 371–381. https://doi.org/10.1080/15623599.2018.1435234
Rhoads, E.L., Poine, T.S., Win, C.C. and Kyed, H. (2020). Myanmar: Urban Housing
Diagnostic and COVID-19 Rapid Assessment (English). Washington, DC: World
Bank Group.
Sambasivan, M. and Soon, YW (2007). Causes and effects of delays in Malaysian
construction industry. International Journal of Project Management, 25(5):
–526. https://doi.org/10.1016/j.ijproman.2006.11.007
Sinesilassie, E.G., Tabish, S.Z.S. and Jha, K.N. (2018). Critical factors affecting cost
performance: a case of Ethiopian public construction projects. International
Journal of Construction Management, 18(2): 108–119. https://doi.org/10.1080/15623599.2016.1277058
Soetanto, R. (2002). Modelling the satisfaction of contractors: The impact of client
performance. Engineering, Construction and Architectural Management,
(5/6): 453. https://doi.org/10.1108/eb021239
Sullivan, G.M. and Feinn, R. (2012). Using effect size-or why the p value is not
enough. Journal of Graduate Medical Education, 4(3): 279–282. https://doi.org/10.4300%2FJGME-D-12-00156.1
Sweis, R.J., Bisharat, S.M., Bisharat, L. and Sweis, G. (2014). Factors affecting
contractor performance on public construction projects. Life Science Journal,
(4): 28–39.
Takim, R. and Akintoye, A. (2002). Performance indicators for successful construction
project performance. In D. Greenwood (ed.), 18th Annual ARCOM
Conference, Vol. 2. Newcastle upon Tyne: ARCOM, 545–555.
Tam, V.W.Y., Shen, L.Y. and Kong, J.S.Y. (2011). Impacts of multi-layer chain
subcontracting on project management performance. International
Journal of Project Management, 29(1): 108–116. https://doi.org/10.1016/j.ijproman.2010.01.005
Thai, H.-T., Ngo, T. and Uy, B. (2020). A review on modular construction for high-rise
buildings. Structures, 28: 1265–1290. https://doi.org/10.1016/j.istruc.2020.09.070
The World Bank (2022). Myanmar economic monitor: Reforms reversed. Available at:
United Nations (2022). The Sustainable Development Goals report 2022. Available
at: https://unstats.un.org/sdgs/report/2022/
_____. (2015). Transforming our world: The 2030 agenda for sustainable development.
Available at: https://sdgs.un.org/2030agenda
Wu, G., Yang, R., Li, L., Bi, X., Liu, B., Li, S. and Zhou, S. (2019) . Factors
influencing the application of prefabricated construction in
China: From perspectives of technology promotion and cleaner
production. Journal of Cleaner Production, 219: 753–762.
https://doi.org/10.1016/j.jclepro.2019.02.110.
Yu, T., Man, Q., Wang, Y., Shen, G.Q., Hong, J., Zhang, J. and Zhong, J. (2019).
Evaluating different stakeholder impacts on the occurrence of quality defects
in offsite construction projects: A Bayesian-network-based model. Journal of
Cleaner Production, 241: 118390. https://doi.org/10.1016/j.jclepro.2019.118390