Examining the Causes of Disregarding Influencing Factors on Artisan Performance in Tanzania’s Building Construction Projects

Main Article Content

Japhary Juma Shengeza
Joseph John Msambichaka
Yazid Hassan Mwishwa

Abstract

Poor artisans’ performance during construction is often attributed to disregarding influencing factors that affect their performance. This study aims to identify the causes behind the disregard of influencing factors in artisans’ performance in Tanzanian building projects, categorising them into external and internal factors. External factors include motivation, formal training and informal training, while internal factors involve qualification-related factors. A qualitative approach was used for data collection through semi-structured interviews and purposive sampling was employed to select supervisors as interviewees. The data was analysed using content and narrative analysis. The result from the semi-structured interview revealed several causes for disregarding motivational factors frequently mentioned by interviewees. These included employers offering work at low prices, supervisors neglecting to apply motivational techniques and employers undervaluing artisans’ importance compared to material requirements. Regarding formal and informal training factors, interviewees emphasised supervisors’ reliance on constant monitoring to correct mistakes and address poor workmanship during construction. For qualification factors, interviewees noted that construction activities prioritise experience and practical abilities over formal certifications. Based on these findings, this study guides policymakers in preventing disregarding influencing factors in artisans’ performance in construction projects. The study concludes by advocating for all stakeholders to support apprenticeships and internships in developing practical skills and recommends the formation of an artisans’ association.

Article Details

How to Cite
Japhary Juma Shengeza, Joseph John Msambichaka, and Yazid Hassan Mwishwa. 2024. “Examining the Causes of Disregarding Influencing Factors on Artisan Performance in Tanzania’s Building Construction Projects”. Journal of Construction in Developing Countries 29 (2): 135-55. https://doi.org/10.21315/.
Section
Articles

References

Akomah, B.B., Ahinaquah, L.K. and Mustapha, Z. (2020). Skilled labour shortage in

the building construction industry within the central region. Baltic Journal of

Real Estate Economics and Construction Management, 8(1): 83–92. https://

doi.org/10.2478/bjreecm-2020-0006

Alinaitwe, H., Mwakali, J. and Hansson, B. (2005). Labour productivity in the building

industry. In K. Kähkönen and M. Sexton (eds.), Understanding the Construction

Business and Companies in the New Millenium. Finland: Technical Research

Centre of Finland and Association of Finnish Civil Engineers, 210–220.

Architects and Quantity Surveyors Registration Board (2022). Proceedings of the

rd Annual Conference: “Conservation of Buildings in Urban Areas in Africa

Today”. Dodoma, Tanzania: Ministry of Works.

Bergman, M.E., Donovan, M.A., Drasgow, F., Overton, R.C. and Henning, J.B. (2008).

Test of Motowidlo et al.’s (1997) theory of individual differences in task and

contextual performance. Human Performance, 21(3): 227–253. https://doi.

org/10.1080/08959280802137606

Bergström, E. and Martinez, M.G. (2016). The influence of intrinsic and extrinsic

motivation on employee engagement: A qualitative study of the perceptions

of managers in public and private sector organisations. Degree project.

Umeå University.

Campbell, J.P. and Wiernik, B.M. (2015). The modeling and assessment of work

performance. Annual Review of Organizational Psychology and Organizational

Behavior, 2: 47–74. https://doi.org/10.1146/annurev-orgpsych-032414-111427

Campbell, J.P., McCloy, R.A., Oppler, S.H. and Sager, C.E. (1992). A theory of

performance. In. N. Schmitt and W.C. Borman (eds.), Personnel Selection in

Organizations. San Francisco: Jossey Bass, 35–70.

Collins, W., Parrish, K. and Gibson, G.E. (2017). Defining and understanding “small

projects” in the industrial construction sector. Procedia Engineering, 196: 315–

https://doi.org/10.1016/j.proeng.2017.07.205

Cox, R.F., Issa, R.R.A. and Koblegard, K. (2005). Management’s perception of key

behavioral indicators for construction. Journal of Construction Engineering

and Management, 131(3): 368–376. https://doi.org/10.1061/(ASCE)0733-

(2005)131:3(368)

Creswell, J. (2009). Research Design: Qualitative, Quantitative and Mixed Methods

Approaches. 3rd Ed. California: SAGE Publications, Inc.

Egwunatum, S.I. (2017). A review of construction project performance

estimators. MOJ Civil Engineering, 3(4): 326–328. https://doi.org/10.15406/

mojce.2017.03.00075

El-Gohary, K.M. and Aziz, R.F. (2013). Factors influencing construction labor

productivity in Egypt. Journal of Management in Engineering, 30(1): 1–9.

https://doi.org/10.1061/(asce)me.1943-5479.0000168

Evarist, C., Luvara, V.G.M. and Chileshe, N. (2022). Perception on constraining factors

impacting recruitment and selection practices of building contractors in Dar

es Salaam, Tanzania. International Journal of Construction Management,

(12): 2012–2023. https://doi.org/10.1080/15623599.2022.2031556

Fagbenle, O.I. (2011). Factor affecting the performance of labour in Nigerian

construction sites. Mediterranean Journal of Social Sciences, 2(2): 251–257.

Farmer, M. (2016). The Farmer Review of the UK Construction Labour Model.

London: Construction Leadership Council (CLC). Available at: https://www.

constructionleadershipcouncil.co.uk/wp-content/uploads/2016/10/FarmerReview.pdf

Flick, U. (2014). The SAGE Handbook of Qualitative Data Analysis. California: SAGE

Publications, Inc.

Gundecha, M.M. (2012). Study of factors affecting labor productivity at a building

construction project in the USA: Web survey. MSc diss. North Dakota State

University of Agriculture and Applied Science.

Hussain, S., Xuetong, W. and Hussain, T. (2020). Impact of skilled and unskilled labor

on project performance using structural equation modelling approach. SAGE

Open, 10(1): 1–16. https://doi.org/10.1177/2158244020914590

Jarkas, A.M. and Bitar, C.G. (2012). Factors affecting construction labor productivity

in Kuwait. Journal of Construction Engineering and Management, 138(7):

–10. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000501

Jason, A. (2005). Informal construction workers in Dar es Salaam, Tanzania. Working

Paper 226. Geneva: ILO.

Jesumoroti, C. and Draai, W. (2021). Analysis of construction worker’s demotivation

that affect productivity in the South African construction industry. IOP

Conference Series: Earth and Environmental Science, 654: 012014. https://

doi.org/10.1088/1755-1315/654/1/012014

Karimi, H., Taylor, T.R.B. and Goodrum, P.M. (2017). Analysis of the impact of craft

labour availability on North American construction project productivity and

schedule performance. Construction Management and Economics, 35(6):

–380. https://doi.org/10.1080/01446193.2017.1294257

Khamis, M.K. (2019). The effects of training on employees’ performance: A case of

the Zanzibar social security fund. MHRM diss. Open University of Tanzania.

Kikwasi, G.J. (2011). An evaluation of construction skills in Tanzania. Engineering,

Construction and Architectural Management, 18(2): 127–139. https://doi.

org/10.1108/09699981111111111

Kikwasi, G.J. and Escalante, C. (2018). Role of the construction sector and key

bottlenecks to supply response in Tanzania. WIDER Working Paper 2018/131.

Helsinki: UNU-WIDER. https://doi.org/10.35188/UNU-WIDER/2018/573-2

Kusumarukmi, E.I and Adi, T.J.W. (2019). Public tendering process for construction

projects: Problem identifications, analysis and proposed solutions. MATEC Web

of Conferences, 258: 1–8. https://doi.org/10.1051/matecconf/201925802013

Mahamid, I. (2013). Contractors’ perspective toward factors affecting labor

productivity in building construction. Journal of Engineering, Construction

and Architectural Management, 20(5): 446–460. https://doi.org/10.1108/

ECAM-08-2011-0074

Malinga, R.S. and Wells, J. (2002). Collaboration between formal and informal

enterprises in the construction sector in Tanzania. Habitat International, 26(2):

–280. https://doi.org/10.1016/S0197-3975(01)00048-0

Moradi, S., Nasirzadeh, F. and Golkhoo, F. (2017). Modeling labor productivity in

construction projects using hybrid SD-DES approach. Scientia Iranica, 24(6):

–2761. https://doi.org/10.24200/sci.2017.4171

Olomolaiye, P.O., Jayawardane, A.K.W. and Harris, F.C. (1998). Construction

Productivity Management. Essex, England: Longman.

Othman, N.A. and Mydin, M.A.O. (2014). Poor workmanship in construction of lowcost housing. Analele Universităţii “Eftimie Murgu” Reşiţa: Fascicola I, Inginerie,

(1): 300–306.

Patton, M. (2002). Qualitative Research and evaluation methods. 3rd Ed. California:

SAGE Publications, Inc.

Rutayuga, A.B. (2014). The emerging Tanzanian concept of competence: Conditions

for successful implementation and future development. Quality Assurance in

Education, 16(2): 164–180.

Ryan, R.M. and Deci, E.L. (2000). Intrinsic and extrinsic motivations: Classic definitions

and new directions. Contemporary Educational Psychology, 25(1): 54–67.

https://doi.org/10.1006/ceps.1999.1020

Salleh, N.M., Alang, N., Saberi, M.H. and Mamter, S. (2022). Factors affecting quality

of workmanship in building construction. International Journal of Academic

Research in Business and Social Sciences, 7(5): 1620–1628. https://doi.

org/10.6007/IJARBSS/v12-i8/14174

Shengeza, J.J., Msambichaka, J.J. and Mwishwa, Y.H. (2023). Assessment of the

impact of disregarding influencing factors on artisans performance in building

construction projects in Tanzania. Journal of Project Management, 8: 1–14.

https://doi.org/10.5267/j.jpm.2023.5.001

Tam, N.V., Huong, N.L. and Ngoc, N.B. (2018). Factors affecting labour productivity

of construction worker on construction site: A case of Hanoi. Journal of

Science and Technology in Civil Engineering (JSTCE) – HUCE, 12(5): 127–138.

https://doi.org/10.31814/stce.nuce2018-12(5)-13

United Republic of Tanzania (2020). The Water Supply and Sanitation Services

(Licensing and Quality of Services) Rules, 2020, Supplement No. 41:

Government Notice No. 849. Dar es Salaam: United Republic of Tanzania.

United Republic of Tanzania (2019). The Electricity (Electrical Installation Services) Rules, 2019, Government

Notice No. 382. Dar es Salaam: United Republic of Tanzania.

United Republic of Tanzania (2016). The Public Procurement (Amendment) Act, 2016. Dar es Salaam:

United Republic of Tanzania.

United Republic of Tanzania (2015). The Engineering Works, Services and Projects Monitoring Regulation

, Supplement No. 25: Government Notice No. 237. Dar es Salaam: United

Republic of Tanzania.

United Republic of Tanzania (2013). The Public Procurement Regulations, 2013, Supplement No. 48:

Government Notice No. 446. Dar es Salaam: United Republic of Tanzania.

United Republic of Tanzania (2008). The Contractors Registration (Amendment) Act No. 15 of 2008. Dar es

Salaam: United Republic of Tanzania.

Zannah, A.A. (2016). Improving skilled workers’ performance in construction projects

in Nigeria. MSc diss. Universiti Tun Hussein Onn Malaysia.

Zannah, A.A., Latiffi, A.A., Raji, A.U., Waziri, A.A. and Mohammed, U. (2017). Causes

of low-skilled workers’ performance in construction projects. Path of Science:

International Electronic Scientific Journal, 3(6): 1–15. https://doi.org/10.22178/

pos.23-7