Modelling Cost-Risk Impact on Nigerian Highway Projects Using Multiple Linear Regression and Artificial Neural Networks

Main Article Content

Victor Imohnikhe Aligamhe
Muzani Mustapa
Chukwuemeka Patrick Ogbu
Mohd Saidin Misnan

Abstract

Cost predictive models for highway projects are relatively scarce in developing countries, despite the frequency and magnitude of project cost overruns in such countries. This study identified critical cost risks impacting highway projects and modelled their impacts on the actual cost of the projects. Historical cost data on highway projects published by the Nigerian Federal Ministry of Power, Works and Housing in 2017 served as a preliminary list of projects for the study, while further cost data were obtained from highway engineers and quantity surveyors across Nigeria using the snowballing technique until 103 highway projects were identified. Project participants were purposively chosen to fill out questionnaires on cost-risks factors associated with highway construction projects. The relative importance index and Pareto 80/20 rule were used to analyse the collected primary data. Thereafter, multiple linear regression and artificial neural network models were developed. Findings revealed that the increase in the cost of construction materials and labour and the fluctuations in foreign exchange rates were the most significant risks impacting highway project cost performance. A comparison of the models indicated that the artificial neural networks model performed better. Hence, the artificial neural networks model is a superior technique for modelling the relationship between cost risks and cost performance of highway projects.

Article Details

How to Cite
Victor Imohnikhe Aligamhe, Muzani Mustapa, Chukwuemeka Patrick Ogbu, and Mohd Saidin Misnan. 2026. “Modelling Cost-Risk Impact on Nigerian Highway Projects Using Multiple Linear Regression and Artificial Neural Networks”. Journal of Construction in Developing Countries 29 (Supp. 1): 107–128. https://doi.org/10.21315/.
Section
Articles

References

Al-Suhaili, R., Saco, Z.M. and Al-Zwainy, M. (2010). Using artificial neural networks for predicting the total cost of highway projects in Iraq. Paper presented at the 2nd Regional Conference for Engineering Science. College of Engineering. Al-Nahrain University, Iraq, 1–2 December.

Al-Zwainy, F.S. and Aidan, F.M.S. (2017). Forecasting the cost of structure of infrastructure projects utilising artificial neural network model (highway projects as case study). Indian Journal of Science and Technology, 10(20): 1–12. https://doi.org/10.17485/ijst/2017/v10i20/108567

Anigbogu, N.A., Ahmad, Z.B. and Molwus, J.J. (2019). Cost overruns on federal capital territory authority road construction projects. Journal of the Environment, 13(1): 1–14.

Awuku, B., Asa, E., Baffoe-Twum, E. and Essegbey, A. (2022). Conceptual cost estimation of highway bid items: A systematic literature review. Engineering, Construction and Architectural Management, 31(3): 1187–1221. https://doi.org/10.1108/ECAM-03-2022-0266

Barros, L.B., Marcy, M. and Carvalho, M.T.M. (2018). Construction cost estimation of Brazilian highways using artificial neural networks. International Journal of Structural and Civil Engineering Research, 7(3): 283–289. https://doi.org/10.18178/ijscer.7.3.283-289

Changali, S., Mohammad, A. and Van Nieuwland, M. (2015). The construction productivity imperative. Available at: https://www.mckinsey.com/capabilities/operations/our-insights/the-construction-productivity-imperative [Accessed on 23 July 2024].

Dysert, L.R. (2001). Developing a parametric model for estimating process control costs. International Journal of Construction Engineering, 43(2): 31–34.

Elbeltagi, H., Hosny, O., Abdel-Razek, R. and El-Fitory, A. (2014). Conceptual cost estimate of Libyan highway projects using artificial neural networks. Journal of Engineering Research and Application, 4(8): 56–66.

El-Kholy, A.M. (2019). Exploring the best ANN model based on four paradigms to predict delay and cost overrun percentages of highway projects. International Journal of Construction Management, 21(7): 694–712. https://doi.org/10.1080/15623599.2019.1580001

El-Sayegh, S.M. and Mansour, M.H. (2015). Risk assessment and allocation in highway construction projects in the UAE. Journal of Management in Engineering, 31(6): 04015004. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000365

Federal Ministry of Power, Works and Housing (2017). List of on-going federal highway projects. Available at: https://www.google.com/url?sa=t&source=web&rct=j&opi=89978449&url=https://worksandhousing.gov.ng/themes/front_end_themes_01/images/uploads_images/1562351340.pdf&ved=2ahUKEwiNsMzC-LyHAxUdZ0EAHXx8AP8QFnoECBkQAQ&usg=AOvVaw0K7XRMEuv8IjsVOPwxEszX [Accessed 15 December 2021]

Fernando, N., Dishan, T.A.K. and Zhang, H. (2023). An artificial neural network (ANN) approach for early cost estimation of concrete bridge systems in developing countries: The case of Sri Lanka. Journal of Financial Management of Property and Construction, 29(1): 23-51. https://doi.org/10.1108/JFMPC-09-2022-0048

Glymis, E., Kanelakis, A., Aretoulis, G.N. and Mastoras, T. (2017). Predicting highway projects’ actual duration using neural networks. Paper presented at the Lean and Computing in Construction Congress: Joint Conference in Computing Construction (LC3-2017). Heraklion, Greece, 4–7 July. https://doi.org/10.24928/JC3-2017/0260

Gondia, A., Siam, A., El-Dakhakhni, W. and Nassar, A.H. (2019). Machine learning algorithms for construction projects delay risk prediction. Journal of Construction Engineering and Management, 146(1): 04019085. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001736

Grosfeld-Nir, A., Ronen, B. and Kozlovsky, N. (2007). The Pareto managerial principle: When does it apply? International Journal of Production Research, 45(10): 2317–2325. https://doi.org/10.1080/00207540600818203

Hamma-Adama, M., Ogunsemi, M., Mashwama, N.X., Ahmad, A.B.S. and Abba, H.A. (2021). Assessment of risks associated with road infrastructure development in developing countries. Global Scientific Journal, 9(7): 1223–1229.

Hegazy, T., Fazio, P. and Moselhi, O. (1994). Developing practical neural network applications using back-propagation. Microcomputers in Civil Engineering, 9(2): 145–159. https://doi.org/10.1111/j.1467-8667.1994.tb00369.x

Ikechukwu, A.N. and Akiohnbare, W. (2017). Factors affecting cost of construction in Nigeria. International Journal of Advancement in Engineering Technology, Management and Applied Science, 4(6): 48–61

Kovacevic, M., Ivanisevic, N., Petronijevic, P. and Despotovic, V. (2021). Construction cost estimation of reinforced and pre-stressed concrete bridges using machine learning. Graðevinar, 73(1): 1–13. https://doi.org/10.14256/JCE.2738.2019

Leo-Olagbaye, F. and Odeyinka, H.A. (2020). An assessment of risk impact on road projects in Osun State, Nigeria. Built Environment Project and Asset Management, 10(5): 673–691. https://doi.org/10.1108/BEPAM-04-2019-0040

Lewis, C.D. (1982). International and Business Forecasting Methods. London: Butterworths. https://doi.org/10.1002/FOR.3980020210

Love, P., Edwards, D. and Iran, Z. (2012). Moving beyond optimism bias and strategic misrepresentation: An explanation for social infrastructure project cost overruns. IEEE Transportation Engineering Management, 59(4): 590–571. https://doi.org/10.1109/TEM.2011.2163628

Okate, A. and Kakade, V. (2019). Risk management in road construction projects. High-volume roads. In Proceedings of Sustainable Infrastructure Development and Management (SIDM). Maharashtra, India: Visvesvaraya National Institute of Technology. https://doi.org/10.2139/ssm.3375904

Pineda-Jaramillo, J.D., Insa, R. and Martínez, P. (2017). Modelling the energy consumption of trains applying neural networks. Journal of Rail and Rapid Transit, 232(3): 816–823. https://doi.org/10.1177/0954409717694522

Rizwan, M. and Iqbal, M. (2011). Application of 80/20 rule in software engineering rapid application development (RAD) model. In J.M. Zain, W.M.W. Mohd, and E. El-Qawasmeh (eds.), Software Engineering and Computer Systems. ICSECS 2011. Communications in Computer and Information Science, Vol. 181. Berlin: Springer, 518–532. https://doi.org/10.1007/978-3-642-22203-0_45

Sarker, I.H. (2021). Machine learning: Algorithms, real-world applications and research directions. SN Computer Science, 2(3): 1–21. https://doi.org/10.1007/s42979-021-00592-x

Sodikov, J. (2005). Cost estimation of highway projects in developing countries: Artificial neural network approach. Journal of the Eastern Asia Society for Transportation Studies, 6: 1036–1047. https://doi.org/10.11175/easts.6.1036

Tariq, J. and Gardezi, S.S. (2023). Study the delays and conflicts for construction projects and their mutual relationship: A review. Ain Shams Engineering Journal, 14(1): 101815. https://doi.org/10.1016/j.asej.2022.101815

Thaseena, T. and Vishnu, K. (2017). Analysis of cost overruns in highway construction projects using multiple regression and artificial neural networks. International Research Journal of Engineering and Technology, 4(4): 2332–2336.

Tijanić, K., Car-Pušić, D. and Šperac, M. (2019). Cost estimation in road construction using artificial neural networks. Neural Computing and Applications, 32(13): 9343–9355. https://doi.org/10.1007/s00521-019-04443-y