Silent Failures: Uncovering the Root Causes of Poor Communication in Malaysian Construction Projects

Main Article Content

Jeffrey Boon Hui Yap
Jia Hui Oo

Abstract

Communication-related issues significantly hinder project performance throughout the construction project lifecycle. This study aimed to identify the key causes of poor communication in construction projects to mitigate communication-related issues. A comprehensive literature review identified 20 potential causes and a questionnaire survey was conducted with 106 Malaysian construction stakeholders, including clients, consultants and developers. The data were analysed using descriptive and inferential statistics. The study found five primary causes of poor communication, namely: (1) lack of effective communication between parties, (2) poor planning and coordination, (3) inadequate communication skills, (4) unclear objectives and (5) improper communication channels. The study’s exploratory factor analysis revealed four underlying factors contributing to poor communication: (1)  ineffective  communication  and  supportive  tools,  (2)  noise  in  communication, (3) fragmentation and coordination problems and (4) improper planning and language disabilities. These findings provide valuable insights for construction practitioners, offering guidance on addressing communication issues before they negatively impact project performance. The study also informs researchers and practitioners on the critical causes of poor communication, facilitating the development of effective strategies to enhance communication effectiveness.

Article Details

How to Cite
Jeffrey Boon Hui Yap, and Jia Hui Oo. 2025. “Silent Failures: Uncovering the Root Causes of Poor Communication in Malaysian Construction Projects”. Journal of Construction in Developing Countries 30 (2): 109–136. https://doi.org/10.21315/.
Section
Articles

References

Abdallah, A.A., Shaawat, M.E. and Almohassen, A.S. (2024). Causes of miscommunication leading to project delays and low work quality in the construction industry of Saudi Arabia. Ain Shams Engineering Journal, 15(3): 102447. https://doi.org/10.1016/j.asej.2024.102447

Al-aloosy, K.F.Ǫ., Mirvalad, S. and Shabakhty, N. (2024). Evaluating the impact of internet communication quality in human resource management on the productivity of construction projects. Heliyon, 10(7): e28500. https://doi.org/10.1016/j.heliyon.2024.e28500

Alaloul, W.S., Liew, M.S. and Zawawi, N.A.W.A. (2016). Identification of coordination factors affecting building projects performance. Alexandria Engineering Journal, 55(3): 2689–2698. https://doi.org/10.1016/j.aej.2016.06.010

Assaf, S., Hassanain, M.A. and Mughal, H. (2014). Effectiveness of project teams and their impact on the performance of Saudi construction projects. Research Journal of Applied Sciences, Engineering and Technology, 7(24): 5148–5156. https://doi.org/10.19026/rjaset.7.911

Assaf, S.A. and Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Proįect Management, 24(4): 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010

Aziz, N.A., Rahim, F.A.M. and Aziz, N.M. (2022a). Delay mitigation strategies and the implication on the construction industry: A systematic literature review. Planning Malaysia, 20(4): 223–234. https://doi.org/10.21837/pm.v20i24.1199

. (2022b). Systematic literature review on communication in construction project management: Issues among project participants. Journal of Surveying, Construction and Property, 13: 52–70. https://doi.org/10.22452/jscp.sp2022no1.5

Berenger, Y.R. and Justus, N.A. (2016). The issue of communication in the construction industry: A case of South Africa. In O.J. Ebohon, D.A. Ayeni, C.O. Egbu and F.K. Omole (eds.), Procs. of the Joint International Conference (JIC) on 21st Century Human Habitat: Issues, Sustainability and Development. Akure, Nigeria: The Joint International Conference Editorial Committee, 1729–1738.

Bröchner, J., Josephson, P.E. and Kadefors, A. (2002). Swedish construction culture, quality management and collaborative practice. Building Research and Information, 30(6): 392–400. https://doi.org/10.1080/09613210210159866

Daim, T.U., Ha, A., Reutiman, S., Hughes, B., Pathak, U., Bynum, W. and Bhatla, A. (2012). Exploring the communication breakdown in global virtual teams. International Journal of Proįect Management, 30(2): 199–212. https://doi.org/10.1016/j.ijproman.2011.06.004

Dainty, A., Moore, D. and Murray, M. (2006). Communication in Construction: Theory and Practice. London: Taylor & Francis.

Ejohwomu, O.A., Oshodi, O.S. and Lam, K.C (2017). Nigeria’s construction industry: Barriers to effective communication. Engineering, Construction and Architectural Management, 24(4): 652–667. https://doi.org/10.1108/ecam-01-2016-0003

El-Razek, M.E.A., Bassioni, H.A. and Mobarak, A.M. (2008). Causes of delay in large building construction projects. Journal of Construction Engineering and Management, 134(11): 831–841. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831)

Emuze, F. and James, M. (2013). Exploring communication challenges due to language and cultural diversity on South African construction sites. Acta Structilia, 20(1): 44–65. https://doi.org/10.38140/as.v20i1.133

English, J. (2002). The communication problems experienced by workforce on-site and their possible solutions. Journal of Construction Research, 3(2): 311–321. https://doi.org/10.1142/s1609945102000163

Enshassi, A., Al-Najjar, J. and Kumaraswamy, M. (2009). Delays and cost overruns in the construction projects in the Gaza Strip. Journal of Financial Management of Property and Construction, 14(2): 126–151. https://doi.org/10.1108/13664380910977592

Fellows, R. and Liu, A. (2015). Research Methods for Construction. 4th Ed. Oxford: John Wiley & Sons, Ltd.

Fernández, M.D., Ǫuintana, S., Chavarría, N. and Ballesteros, J.A. (2009). Noise exposure of workers of the construction sector. Applied Acoustics, 70(5): 753–760. https://doi.org/10.1016/j.apacoust.2008.07.014

Fong, P.S. and Lung, B.W. (2007). Interorganizational teamwork in the construction industry. Journal of Construction Engineering and Management, 133(2): 157–168. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:2(157)

Franz, B., Leicht, R., Molenaar, K. and Messner, J. (2016). Impact of team integration and group cohesion on project delivery performance. Journal of Construction Engineering and Management, 143(1): 04016088. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001219

Galaz-Delgado, E.I., Herrera, R.F., Atencio, E., Muñoz-La Rivera, F. and Biotto, C.N. (2021). Problems and challenges in the interactions of design teams of construction projects: A bibliometric study. Buildings, 11(10): 461. https://doi.org/10.3390/buildings11100461

Gamil, Y. and Rahman, I.A. (2023a). Impact of poor communication on dispute occurrence in the construction industry: A preliminary exploratory study of Yemen construction industry. International Journal of Construction Management, 23(16): 2729–2735. https://doi.org/10.1080/15623599.2022.2092388

Gamil, Y. and Rahman, I.A. (2023b). Studying the relationship between causes and effects of poor communication in construction projects using PLS-SEM approach. Journal of Facilities Management, 21(1): 102–148. https://doi.org/10.1108/jfm-04-2021-0039

Gamil, Y. and Rahman, I.A. (2017). Identification of causes and effects of poor communication in construction industry: A theoretical review. Emerging Science Journal, 1(4): 239–247. https://doi.org/10.28991/ijse-01121

Gustavo, R.-M. and Nicholas, C. (2011). Effectiveness of communication between contractors and sub-contractors: Practices, barriers and enablers. In Proceedings of the 9th International Conference on Construction and Real Estate Management (ICCREM 2011). Guangzhou: ICCREM 2011, 1372–1379.

Hair, J.F., Black, W.C., Babin, B.J. and Anderson, R.E. (2019). Multivariate Data Analysis. 8th Ed. Hampshire, UK: Cengage Learning.

Haslam, R.A., Hide, S.A., Gibb, A.G.F., Gyi, D.E., Pavitt, T., Atkinson, S. and Duff, A.R. (2005). Contributing factors in construction accidents. Applied Ergonomics, 36(4): 401–415. https://doi.org/10.1016/j.apergo.2004.12.002

Hatem, W.A., Naji, H.I. and Alkreem, Z.A.A. (2018). Using of advanced communication technology in the construction projects during the implementation stage. Diyala Journal of Engineering Sciences, 11(2): 14–32. https://doi.org/10.24237/djes.2018.11202

Heldman, K. (2018). Proįect Management Jumpstart. 4th Ed. Indianapolis: Wiley.

Hussain, M.A., Othman, A.A.E., Gabr, H.S. and Aziz, T.A. (2018). Causes and impacts of poor communication in the construction industry. In Proceedings of the 2nd International Conference on Sustainable Construction and Proįect Management: Sustainable Infrastructure and Transportation for Future Cities. Aswan, Egypt: Housing and Building National Research Center, 1–11.

Ishaq, I.M., Omar, R. and Mohammed, M. (2018). Challenges of communication between the client and contractor during construction projects: The Nigerian perspective. International Journal of Engineering and Modern Technology, 4(2): 20–29.

Ishaq, I.M., Omar, R., Yahya, M.Y. and Sarpin, N. (2019). Improving communication between client and contractor during construction project in Nigerian construction industry. Journal of Technology Management and Business, 6(3): 60–75.

Keyton, J. (2017). Communication in organizations. Annual Review of Organisational Psychology and Organisational Behavior, 4: 501–526.

Khahro, S.H., Shaikh, H.H., Zainun, N.Y., Sultan, B. and Khahro, Ǫ.H. (2023). Delay in decision-making affecting construction projects: A sustainable decision-making model for mega projects. Sustainability, 15(7): 5872. https://doi.org/10.3390/su15075872

Kwofie, T.E., Aigbavboa, C.O. and Machethe, S.O. (2019). Nature of communication performance in non-traditional procurements in South Africa. Engineering, Construction and Architectural Management, 26(10): 2264–2288. https://doi.org/10.1108/ecam-02-2018-0044

Kwofie, T.E., Aigbavboa, C.O. and Matsane, Z.S.S. (2018). Dimensions of social barriers to effective collaborative working in construction supply chain. International Journal of Proįect Organisation and Management, 10(1): 37. https://doi.org/10.1504/ijpom.2018.090382

Latif, K.F. and Williams, N. (2017). Team effectiveness in non-governmental organizations (NGOs) projects. Evaluation and Program Planning, 64(May): 20–32. https://doi.org/10.1016/j.evalprogplan.2017.05.004

Lim, E.C. and Alum, J. (1995). Construction productivity: Issues encountered by contractors in Singapore. International Journal of Proįect Management, 13(1): 51-58. https://doi.org/10.1016/0263-7863(95)95704-H

Liu, Y., Baldwin, R.N. and Shen, L.Y. (2006). Identification of factors influencing communication between participants in construction projects. In The CRIOCM 2006 International Symposium on Advancement of Construction Management and Real Estate. Hong Kong: CRIOCM 2006, 1–9.

Loosemore, M. and Lee, P. (2002). Communication problems with ethnic minorities in the construction industry. International Journal of Proįect Management, 20(7): 517–524. https://doi.org/10.1016/s0263-7863(01)00055-2

Meng, Ǫ., Liu, W., Li, Z. and Hu, X. (2021). Influencing factors, mechanism and prevention of construction workers’ unsafe behaviors: A systematic literature review. International Journal of Environmental Research and Public Health, 18(5): 1–23. https://doi.org/10.3390/ijerph18052644

Obonadhuze, B.I., Eze, C.E., Siunoje, L.U. and Sofolahan, O. (2018). Causes and effects of ineffective communication on construction projects. Borneo Journal of Sciences and Technology, 3(1): 77–92.

Ochieng, E.G. and Price, A.D.F. (2010). Managing cross-cultural communication in multicultural construction project teams: The case of Kenya and UK. International Journal of Proįect Management, 28(5): 449–460. https://doi.org/10.1016/j.ijproman.2009.08.001

Odusami, K.T. (2002). Perceptions of construction professionals concerning important skills of effective project leaders. Journal of Management in Engineering, 18(2): 61–67. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:2(61)

Olanrewaju, A., Tan, S.Y. and Kwan, L.F. (2017). Roles of communication on performance of the construction sector. Procedia Engineering, 196: 763–770. https://doi.org/10.1016/j.proeng.2017.08.005

Olanrewaju, O.I., Bello, A.O., Semiu, M.A. and Mudashiru, S.A. (2024). Critical barriers to effective communication in the construction industry: Evidence from Nigeria. International Journal of Construction Management. https://doi.org/10.1080/1562 3599.2024.2362018

Otter, A.D. and Emmitt, S. (2007). Exploring effectiveness of team communication. Engineering, Construction and Architectural Management, 14(5), 408–419. https://doi.org/10.1108/09699980710780728

Pamidimukkala, A., Kermanshachi, S. and Rad, S.K. (2023). Ranking and weighting effective project-based communication indicators for primary and secondary stakeholders in construction projects. Journal of Legal Affiairs and Dispute Resolution in Engineering and Construction, 15(1): 04022058. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000581

Perera, H., Azadnia, A.H. and Ghadimi, P. (2022). Development of a multi-agent system to tackle communication fragmentation and information exchange in the construction industry. IFAC PapersOnLine, 55(10): 335–340. https://doi.org/10.1016/j.ifacol.2022.09.409

Ǫuan, B.L.T., Chai, C.S., Tan, J.S. and Choy, S.Y. (2022). Effects of poor communication in the construction industry in Klang Valley, Malaysia. Jurnal Keįuruteraan, 34(5): 837–841.

Rahimian, A. Hosseini, M.R., Martek, I., Taroun, A., Alvanchi, A. and Odeh, I. (2022). Predicting communication quality in construction projects: A fully-connected deep neural network approach. Automation in Construction, 139: 104268. https://doi.org/10.1016/j.autcon.2022.104268

Rahman, I.A. and Gamil, Y. (2019). Assessment of cause and effect factors of poor communication in construction industry. IOP Conference Series: Materials Science and Engineering, 601(1): 012014. https://doi.org/10.1088/1757-899X/601/1/012014

Rehan, A., Thorpe, D. and Heravi, A. (2024). A framework for leadership practices and communication in the context of the construction sector. Proįect Leadership and Society, 5: 100142. https://doi.org/10.1016/j.plas.2024.100142

Roscoe, J.T. (1975). Fundamental Research Statistics for the Behavioural Sciences. 2nd Ed. New York: Holt, Rinehart & Winston.

Safapour, E., Kermanshachi, S., Kamalirad, S. and Tran, D. (2019). Identifying effective project-based communication indicators within primary and secondary stakeholders in construction projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 11(4). https://doi.org/10.1061/(asce)la.1943-4170.0000332

Senaratne, S. and Ruwanpura, M. (2016). Communication in construction: A management perspective through case studies in Sri Lanka. Architectural Engineering and Design Management, 12(1): 3–18. https://doi.org/10.1080/17452007.2015.1056721

Shakeri, H., Khalilzadeh, M., Raslanas, S. and Zavadskas, E.K. (2020). What do project managers need to know to succeed in face-to-face communication? Economic Research-Ekonomska Istraživanįa, 34(1): 1094–1120. https://doi.org/10.1080/1331677x.2020.1819851

Shehu, Z., Holt, G.D., Endut, I.R. and Akintoye, A. (2015). Analysis of characteristics affecting completion time for Malaysian construction projects. Built Environment Proįect and Asset Management, 5(1), 52–68. https://doi.org/10.1108/bepam-10-2013-0056

Suleiman, A. (2022). Causes and effects of poor communication in the construction industry in the MENA region. Journal of Civil Engineering and Management, 28(5): 365–376. https://doi.org/10.3846/jcem.2022.16728

Suleiman, A., Almasaeid, H., Hussein, N. and Abahre, J. (2023). Addressing the causes and effects of poor communication in the Jordanian construction industry: A Study on improving project performance. Civil and Environmental Engineering, 19(1): 156–166. https://doi.org/10.2478/cee-2023-0014

Tai, S., Wang, Y. and Anumba, C.J. (2009). A survey on communications in large-scale construction projects in China. Engineering, Construction and Architectural Management, 16(2): 136–149. https://doi.org/10.1108/09699980910938019

Taleb, H. Ismail, S., Wahab, M.H., Mardiah, W.N., Rani, W.M. and Amat, R.C. (2017). An overview of project communication management in construction industry projects. Journal of Management, Economics, and Industrial Organization, 1–9. https://doi.org/10.31039/jomeino.2017.1.1.1

Tipili, L.G., Ojeba, P.O. and Ilyasu, M.S. (2014). Evaluating the effects of communication in construction project delivery in Nigeria. Global Journal of Environmental Science and Technology, 2(5): 2360–7955.

Trajkovski, S. and Loosemore, M. (2006). Safety implications of low-English proficiency among migrant construction site operatives. International Journal of Proįect Management, 24(5): 446–452. https://doi.org/10.1016/j.ijproman.2005.11.004

Tsai, M.K. (2009). Improving communication barriers for on-site information flow: An exploratory study. Advanced Engineering Informatics, 23(3): 323–331. https://doi.org/10.1016/j.aei.2009.03.002

Vasista, T.G. and Abone, A. (2018). Benefits, barriers and applications of information communication technology in construction industry: A contemporary study. International Journal of Engineering and Technology, 7(3.27): 492–499. https://doi.org/10.14419/ijet.v7i3.27.18004

Vo, K.D., Nguyen, P.T. and Nguyen, Ǫ.L.H.T.T. (2020). Disputes in managing projects: A case study of construction industry in Vietnam. Journal of Asian Finance, Economics and Business, 7(8): 635–644. https://doi.org/10.13106/jafeb.2020.vol7.no8.635

Wang, J., Zhang, S., Jin, R., Fenn, P., Yu, D., and Zhao, L. (2023). Identifying critical dispute causes in the construction industry: A cross-regional comparative study between China and the UK. Journal of Management in Engineering, 39(2). https://doi.org/10.1061/jmenea.meeng-4943

Wu, G., Liu, C., Zhao, X. and Zuo, J. (2017). Investigating the relationship between communication-conflict interaction and project success among construction project teams. International Journal of Proįect Management, 35(8): 1466–1482. https://doi.org/10.1016/j.ijproman.2017.08.006

Wood, H. and Gidado, K. (2008). Project complexity in construction. In COBRA 2008: Construction and Building Research Conference of the Royal Institution of Chartered Surveyors. Dublin: The Royal Institution of Chartered Surveyors.

Xie, H. Hong, Y., Xin, M., Brilakis, I. and Shi, O. (2023). Identification and analysis of communication barriers for construction projects with time uncertainties. Engineering, Construction and Architectural Management, 32(1), 305–331. https://doi.org/10.1108/ecam-07-2022-0669

Xu, S. and Luo, H. (2014). The information-related time loss on construction sites: A case study on two sites. International Journal of Advanced Robotic Systems, 11(128): 1–12. https://doi.org/10.5772/58444

Yakubu, G.A., Ogunsanmi, O.E. and Yakubu, A.O. (2019). Influences of communication problems on project performance in Nigeria. Journal of Engineering Research, 7(3): 74–84. https://doi.org/10.30918/ajer.73.15.017

Yap, J.B.H., Abdul-Rahman, H. and Chen, W. (2017). Collaborative model: Managing design changes with reusable project experiences through project learning and effective communication. International Journal of Proįect Management, 35(7): 1253–1271. https://doi.org/10.1016/j.ijproman.2017.04.010

Yap, J.B.H., Abdul-Rahman, H. and Wang, C. (2018). Preventive mitigation of overruns with project communication management and continuous learning: PLS-SEM approach. Journal of Construction Engineering and Management, 144(5): 04018025. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001456

Yap, J.B.H., Chow, I.N. and Shavarebi, K. (2019). Criticality of construction industry problems in developing countries: Analysing Malaysian projects. Journal of Management in Engineering, 35(5): 04019020. https://doi.org/10.1061/(asce)me.1943-5479.0000709

Yap, J.B.H., Goay, P.L., Woon, Y.B. and Skitmore, M. (2021). Revisiting critical delay factors for construction: Analysing projects in Malaysia. Alexandria Engineering Journal, 60(1): 1717–1729. https://doi.org/10.1016/j.aej.2020.11.021

Yap, J.B.H., Lam, C.G.Y., Skitmore, M. and Talebian, N. (2022). Barriers to the adoption of new safety technologies in construction: A developing country context. Journal of Civil Engineering and Management, 28(2): 120–133. https://doi.org/10.3846/jcem.2022.16014

Yap, J.B.H., Leong, W.J. and Skitmore, M. (2020). Capitalising teamwork for enhancing project delivery and management in construction: Empirical study in Malaysia. Engineering, Construction and Architectural Management, 27(7): 1479–1503. https://doi.org/10.1108/ecam-10-2019-0581

Yap, J.B.H., Low, P.L. and Wang, C. (2017). Rework in Malaysian building construction: Impacts, causes and potential solutions. Journal of Engineering, Design and Technology, 15(5): 591–618. https://doi.org/10.1108/jedt-01-2017-0002

Yap, J.B.H. and Skitmore, M. (2018). Investigating design changes in Malaysian building projects. Architectural Engineering and Design Management, 14(3): 218–238. https://doi.org/10.1080/17452007.2017.1384714

Zulch, B.G. (2016). A proposed model for construction project management communication in the South African construction industry. Acta Structilia, 23(1): 1–35. https://doi.org/10.18820/24150487/as23i1.1

Zuo, J., Zhao, X., Nguyen, Ǫ. B. M., Ma, T. and Gao, S. (2018). Soft skills of construction project management professionals and project success factors. Engineering, Construction and Architectural Management, 25(3): 425–442. https://doi.org/10.1108/ecam-01-2016-0016