Determination of Contractor Strategies in Delivering Construction Projects in Oman

Main Article Content

Ayisha Powmya
Nazirah Zainul Abidin
Nurul Sakina Mokhtar Azizi1

Abstract

Contractors are responsible to deliver construction projects as per contract. Past literature highlighted various implications of poor project delivery and as the ones who are responsible to deliver the project, contractors need to plan and strategise to ensure their projects are successfully delivered to the client. This article focuses on identifying the strategies adopted by Omani main contractors to deliver construction projects successfully. Using 48 strategies identified through literature review, a survey has been conducted with 108 main contractors in Oman with top grade level of Oman Chamber of Commerce and Industry (OCCI) to investigate the significant strategies adapted ensuring successful project delivery. The top grade level contractor is on the focus of this research because they are involved as main contractors for construction projects in Oman. Using factor analysis technique, the 48 strategies have been reduced into 28 sub-strategies which are grouped into 7 main strategies. The seven main strategies are: (1) People and subcontractor management, (2) Technology and innovative solutions adoption, (3) Quality, safety and environmental protection, (4) Develop technical capability, monitor and control, (5) Organisational efficiency and financial stability, (6) Legislative compliance and (7) Clients’ satisfaction. This research revisits the successful strategy for project delivery and restructures them to suit the practices in Oman. The strategy can be emulated by contractors in the country and perhaps other Middle East countries, as a way to expedite better construction performance. 

Article Details

How to Cite
Ayisha Powmya, Nazirah Zainul Abidin, and Nurul Sakina Mokhtar Azizi1. 2023. “Determination of Contractor Strategies in Delivering Construction Projects in Oman”. Journal of Construction in Developing Countries 28 (1): 293-316. https://doi.org/10.21315/jcdc-12-21-0203.
Section
Articles

References

Acheamfour, V.K., Kissi, E. and Adjei-Kumi, T. (2019). Ascertaining the impact of contractors pre-qualification criteria on project success criteria. Engineering, Construction and Architectural Management, 26(4): 618–632. https://doi.org/10.1108/ECAM-03-2018-0110

Acheamfour, V.K., Kissi, E. Adjei-Kumi, T. and Adinyira, E. (2020). Review of empirical arguments on contractor pre-qualification criteria. Journal of Engineering, Design and Technology, 18(1): 70–83. https://doi.org/10.1108/JEDT-03-2019-0067

Agenbag, H. and Amoah, C. (2021). The impact of modern construction technology on the workforce in the construction industry. IOP Conference Series: Earth and Environmental Science, 654: 012001. https://doi.org/10.1088/1755-1315/654/1/012001

Aje, I. (2012). The impact of contractors’ prequalification on construction project delivery in Nigeria. Engineering, Construction and Architectural Management, 19(2): 159–172. https://doi.org/10.1108/09699981211206098

Aje, O.I., Odusami, K.T. and Ogunsemi, D.R. (2009). The impact of contractors’ management capability on cost and time performance of construction projects in Nigeria. Journal of Financial Management of Property and Construction, 14(2): 171–187. https://doi.org/10.1108/13664380910977619

Al Amri, T. and Marey-Pérez, M. (2020). Impact of COVID-19 on Oman’s construction industry. Technium Social Sciences Journal, 9: 661–670. https://doi.org/10.47577/tssj.v9i1.1021

Albino, V. and Berardi, U. (2012). Green buildings and organizational changes in Italian case studies. Business Strategy and the Environment, 21(6): 387–400. https://doi.org/10.1002/bse.1728

Al Kuwaiti, E., Ajmal, M.M., and Hussain, M. (2018). Determining success factors in Abu Dhabi health care construction projects: Customer and contractor perspectives. International Journal of Construction Management, 18(5): 430–445. https://doi.org/10.1080/15623599.2017.1333401

Alnuaimi, A.S. and Al Mohsin, M.A. (2013). Causes of delay in completion of construction projects in Oman. Paper presented at the International

Conference on Innovations in Engineering and Technology (ICIET) 2013. Bangkok, Thailand, 25–26 December.

Alnuaimi, A.S., Taha, R.A., Al Mohsin, M. and Al-Harthi, A.S. (2010). Causes, effects, benefits, and remedies of change orders on public construction projects in Oman. Journal of Construction Engineering and Management, 136(5): 615–622. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154

Alpen Capital (2015). GCC construction industry. Report June 2015. Available at: https://alpencapital.com/research/2015/GCC_Construction_Industry_Report_June_2015.pdf [Accessed on 25 March 2020].

Alzahrani, J.I. and Emsley, M.W. (2013). The impact of contractors’ attributes on construction project success: A post construction evaluation. International Journal of Project Management, 31(2): 313–322. https://doi.org/10.1016/j.ijproman.2012.06.006

Ariffin, H.L.T. and Sutrisna, M. (2010). Developing a framework to minimize the occurrence of construction conflict and disputes in different procurement strategies: An initial review of literature. In Proceedings: 26th Annual ARCOM Conference. Reading: Association of Researchers in Construction Management, 1059–1068. Available at: https://www.arcom.ac.uk/-docs/proceedings/ar2010-1059-1068_Tajul-Ariffin_and_Surisna.pdf [Accessed on 22 March 2020].

Azeem, M., Ullah, F., Thaheem, M.J. and Qayyum, S. (2020). Competitiveness in the construction industry: A contractor’s perspective on barriers to improving the construction industry performance. Journal of Construction Engineering, Management and Innovation, 3(3): 193–219. https://doi.org/10.31462/jcemi.2020.03193219

Bagozzi, R.P. and Yi, Y. (1988). On the evaluation of structural equation models. Journal of the Academy of Marketing Science, 16(1): 74–94. https://doi.org/10.1007/BF02723327

Bryde, D.J. and Robinson, L. (2005). Client versus contractor perspectives on project success criteria. International Journal of Project Management, 23(8): 622–629. https://doi.org/10.1016/j.ijproman.2005.05.003

Chen, P.-H., Ong, C.-F. and Hsu, S.-C. (2016). The linkages between internationalization and environmental strategies of multinational construction firms. Journal of Cleaner Production, 116: 207–216. https://doi.org/10.1016/j.jclepro.2015.12.105

Chew, D.A.S., Yan, S. and Cheah, C.Y.J. (2008). Core capability and competitive strategy for construction SMEs in China. Chinese Management Studies, 2(3): 203–214. https://doi.org/10.1108/17506140810895898

Choi, S., Cho, I., Han, S.H., Kwak, Y.H. and Chih, Y.-Y. (2018). Dynamic capabilities of project-based organization in global operations. Journal of Management in Engineering, 34(5): 1–12. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000621

CISION (2017). Construction in Oman, key trends and opportunities to 2021. Available at: https://www.prnewswire.com/news-releases/construction-inoman-key-trends-and-opportunities-to-2021-300407578.html [Accessed on 25 March 2023].

Dąbrowski, A. (2015). An investigation and analysis of safety issues in Polish small construction plants. International Journal of Occupational Safety and Ergonomics, 21(4): 498–511. https://doi.org/10.1080/10803548.2015.1085206

Davies, R. and Harty, C. (2013). Implementing “Site BIM”: A case study of ICT innovation on a large hospital project. Automation in Construction, 30: 15–24. https://doi.org/10.1016/j.autcon.2012.11.024

Dikmen, I. and Birgönül, M.T. (2003). Strategic perspective of Turkish construction companies. Journal of Management in Engineering, 19(1): 33–40. https://doi.org/10.1061/(ASCE)0742-597X(2003)19:1(33)

Doloi, H. (2013). Cost overruns and failure in project management: Understanding the roles of key stakeholders in construction projects. Journal of Construction Engineering and Management, 139(3): 267–279. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000621

Doloi, H., Iyer, K.C. and Sawhney, A. (2011). Structural equation model for assessing impacts of contractor’s performance on project success. International Journal of Project Management, 29(6): 687–695. https://doi.org/10.1016/j.ijproman.2010.05.007

Dvir, D., Raz, T. and Shenhar, A.J. (2003). An empirical analysis of the relationship between project planning and project success. International Journal of Project Management, 21(2): 89–95. https://doi.org/10.1016/S0263-7863(02)00012-1

Egemen, M. and Mohamed, A.N. (2005). Different approaches of clients and consultants to contractors’ qualification and selection. Journal of Civil

Engineering and Management, 11(4): 267–276. https://doi.org/10.1080/13923730.2005.9636357

Fang, Y., Cho, Y.K., Zhang, S. and Perez, E. (2016). Case study of BIM and cloud–enabled real-time RFID indoor localization for construction management applications. Journal of Construction Engineering and Management, 142(7): 05016003. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001125

Fanning, B., Clevenger, C.M., Ozbek, M.E. and Mahmoud, H. (2015). Implementing BIM on infrastructure: Comparison of two bridge construction projects. Practice Periodical on Structural Design and Construction, 20(4): 04014044. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000239

Farooquie, P. and Farooquie, J.A. (2009). Project planning and performance: An empirical study. International Journal of Project Organisation and

Management, 1(4): 408–421. https://doi.org/10.1504/IJPOM.2009.029109

Fergusson, H. and Langford, D.A. (2006). Strategies for managing environmental issues in construction organizations. Engineering,

Construction and Architectural Management, 13(2): 171–185. https://doi.org/10.1108/09699980610659625

Field, A. (2018). Discovering Statistics Using IBM SPSS Statistics. 5th Ed. London: SAGE Publications Ltd.

Fortune, J. and White, D. (2006). Framing of project critical success factors by a systems model. International Journal of Project Management, 24(1): 53–65. https://doi.org/10.1016/j.ijproman.2005.07.004

Gudienė, N., Banaitis, A., Podvezko, V. and Banaitiene, N. (2014). Identification and evaluation of the critical success factors for construction projects in Lithuania: AHP approach. Journal of Civil Engineering and Management, 20(3): 350–359. https://doi.org/10.3846/13923730.2014.914082

Gunasekera, V.S. and Chong, S.C. (2018). Knowledge management for construction organisations: A research agenda. Kybernetes, 47(9): 1778–1800. https://doi.org/10.1108/K-10-2017-0378

Gunduz, M. and Yahya, A.M.A. (2018). Analysis of project success factors in construction industry. Technological and Economic Development of

Economy, 24(1): 67–80. https://doi.org/10.3846/20294913.2015.1074129

Hair, J.F., Black, W.C., Babin, B.J. and Anderson, R.E. (2018). Multivariate Data Analysis. 8th Ed. Hampshire, UK: Cengage Learning (EMEA) Ltd.

Hartmann, A. (2006). The context of innovation management in construction firms. Construction Management and Economics, 24(6): 567–578. https://doi.org/10.1080/01446190600790629

Hwang, B.-G. and Lim, E.-S.J. (2013). Critical success factors for key project players and objectives: Case study of Singapore. Journal of Construction Engineering and Management, 139(2): 204–215. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000597

Hwang, B.-G., Shan, M. and Lye, J.-M. (2018). Adoption of sustainable construction for small contractors: Major barriers and best solutions. Clean Technologies and Environmental Policy, 20: 2223–2237. https://doi.org/10.1007/s10098-018-1598-z

Hwang, B., Zhu, L. and Ming, J.T.T. (2016). Factors affecting productivity in green building construction projects: The case of Singapore. Journal of

Management in Engineering, 33(3): 04016052. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000499

Isik, Z., Arditi, D., Dikmen, I. and Birgonul, M.T. (2009). Impact of corporate strengths/weaknesses on project management competencies. International Journal of Project Management, 27(6): 629–637. https://doi.org/10.1016/j.ijproman.2008.10.002

Islam, M.A. and Khadem, M.M.R.K. (2013). Productivity determinants in Oman construction industry. International Journal of Productivity and Quality Management, 12(4): 426–448. https://doi.org/10.1504/IJPQM.2013.056736

Iyer, K.C., Kumar, R. and Singh, S.P. (2020). Understanding the role of contractor capability in risk management: A comparative case study of two similar projects. Construction Management and Economics, 38(3): 223–238. https://doi.org/10.1080/01446193.2019.1590614

Jaśkowski, P., Sobotka, A. and Czarnigowska, A. (2018). Decision model for planning material supply channels in construction. Automation in Construction, 90: 235–242. https://doi.org/10.1016/j.autcon.2018.02.026

Kaiser, H.F. and Rice, J. (1974). Little Jiffy, Mark Iv. Educational and Psychological Measurement, 34(1), 111–117. https://doi.org/10.1177/001316447403400115

Kazaz, A., Er, B. and Ozdemir, B.E. (2014). A fuzzy model to determine construction firm strategies. KSCE Journal of Civil Engineering, 18(7): 1934–1944. https://doi.org/10.1007/s12205-014-0239-2

Kim, K., Walewski, J. and Cho, Y.K. (2016). Multiobjective construction schedule optimization using modified Niched Pareto Genetic Algorithm. Journal of Management in Engineering, 32(2): 1–12. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000374

Kim, M.J., Chi, H.-L., Wang, X. and Ding, L. (2015). Automation and robotics in construction and civil engineering. Journal of Intelligent and Robotic Systems, 79: 347–350. https://doi.org/10.1007/s10846-015-0252-9

Kog, F. and Yaman, H. (2016). A multi-agent systems-based contractor prequalification model. Engineering, Construction and Architectural

Management, 23(6): 709–726. https://doi.org/10.1108/ECAM-01-2016-0013

Kurien, M., Kim, M.-K., Kopsida, M. and Brilakis, I. (2018). Real-time simulation of construction workers using combined human body and hand tracking for robotic construction worker system. Automation in Construction, 86: 125–137. https://doi.org/10.1016/j.autcon.2017.11.005

Lou, J., Xu, J. and Wang, K. (2017). Study on construction quality control of urban complex project based on BIM. Procedia Engineering, 174: 668–676. https://doi.org/10.1016/j.proeng.2017.01.215

Lu, W., Shen, L. and Yam, M.C. (2008). Critical success factors for competitiveness of contractors: China study. Journal of Construction Engineering and Management, 134(12): 972–982. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:12(972)

Malik, M.J. and Mitchell, H. (2018). Construction and projects in Oman: Overview. Available at: https://www.amjoman.com/wp-content/uploads/2019/01/Construction-and-projects-in-Oman-overview.pdf [Accessed on 25 March 2020]

Manley, K., McFallan, S. and Kajewski, S. (2009). Relationship between construction firm strategies and innovation outcomes. Journal of Construction Engineering and Management, 135(8): 764–771. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000030

Manu, P., Mahamadu, A.-M., Phung, V.M., Nguyen, T.T., Ath, C., Heng, A.Y.T. and Kit, S.C. (2018). Health and safety management practices of contractors in South East Asia: A multi country study of Cambodia, Vietnam, and Malaysia. Safety Science, 107: 188–201. https://doi.org/10.1016/j.ssci.2017.07.007

Meng, X. (2012). The effect of relationship management on project performance in construction. International Journal of Project Management, 30(2): 188–198. https://doi.org/10.1016/j.ijproman.2011.04.002

Mordor Intelligence (2022). Oman construction market size and share analysis: Growth trends and forecasts (2023–2028). Available at: https://www.

mordorintelligence.com/industry-reports/oman-construction-market [Accessed on 25 May 2023].

Odeyinka, H.A. (2000). An evaluation of the use of insurance in managing construction risks. Construction Management and Economics, 18(5): 519–524. https://doi.org/10.1080/014461900407329

Osawaru, F., Amusan, L., Awotinde, O., Akanya, C., Asiyanbola, O. and Akinbo, F. (2018). Planning materials supply for construction works. IOP Conference Series: Earth and Environmental Science, 173: 012002. https://doi.org/10.1088/1755-1315/173/1/012002

Oyegoke, A.S. and Al Kiyumi, N. (2017). The causes, impacts and mitigations of delay in megaprojects in the Sultanate of Oman. Journal of Financial Management of Property and Construction, 22(3): 286–302. https://doi.org/10.1108/JFMPC-11-2016-0052

Oxford Business Group (2019). Oman’s construction activity ramps up amid government initiatives. Available at: https://oxfordbusinessgroup.com/

reports/oman/2019-report/economy/building-excitement-activity-inthe-sector-picks-up-after-a-slow-2017-aided-by-higher-oil-prices-andgovernment-initiatives [Accessed on 14 February 2020].

Pakseresht, A. and Asgari, G. (2012). Determining the critical success factors in construction projects: AHP approach. Interdisciplinary Journal of

Contemporary Research in Business, 4(8): 383–393.

Project Oman (2020). Oman’s construction market snapshot. Available at: http://www.project-oman.com/market-insights [Accessed on 15 February 2020].

Rao, M.V.K., Kumar, V.S.S. and Kumar, P.R. (2018). Optimal contractor selection in construction industry: The fuzzy way. Journal of the Institution of Engineers (India): Series A, 99: 67–78. https://doi.org/10.1007/s40030-018-0271-1

Reichstein, T., Salter, A.J. and Gann, D.M. (2008). Break on through: Sources and determinants of product and process innovation among UK

construction firms. Industry and Innovation, 15(6): 601–625. https://doi.org/10.1080/13662710802565198

Sambasivan, M. and Soon, Y.W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25: 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007

Sekar, G., Viswanathan, K. and Sambasivan, M. (2018). Effects of project-related and organizational-related factors on five dimensions of project performance: A study across the construction sectors in Malaysia. Engineering Management Journal, 30(4): 247–261. https://doi.org/10.1080/10429247.2018.1485000

Shen, L.-Y., Lu, W.-S. and Yam, M.C. (2006). Contractor key competitiveness indicators: A China study. Journal of Construction Engineering and

Management, 132(4): 416–424. https://doi.org/10.1061/(ASCE)0733-9634(2006)132:4(416)

Shen, W., Tang, W., Siripanan, A., Lei, Z., Duffield, C.F. and Hui, F.K.P. (2018). Understanding the green technical capabilities and barriers to green buildings in developing countries: A case study of Thailand. Sustainability, 10(10): 3585. https://doi.org/10.3390/su10103585

Tan, Y., Xue, B. and Cheung, Y.T. (2017). Relationships between main contractors and subcontractors and their impacts on main contractor competitiveness: An empirical study in Hong Kong. Journal of Construction Engineering and Management, 143(7): 1–11. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001311

The World Bank Group. (2019). Oman’s economic update: October 2019. Available at: https://www.worldbank.org/en/country/gcc/publication/omaneconomic-update-october-2019 [Accessed on 20 March 2020].

Townsend, S. (2017). Oman to get boost from expat property law. Arabian Business, September. Available at: https://www.arabianbusiness.com/interviews/property/property-news/377877-oman-to-get-boost-from-expat-propertylaw# [Accessed on 20 March 2020].

Trejo, D., Patil, S., Anderson, S. and Cervantes, E. (2002). Framework for competency and capability assessment for resource allocation. Journal of Management in Engineering, 18(1): 44–49. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:1(44)

Tsai, W.-H., Lin, S.-J., Lee, Y.-F., Chang, Y.-C. and Hsu, J.-L. (2013). Construction method selection for green building projects to improve environmental sustainability by using an MCDM approach. Journal of Environmental Planning and Management, 56(10): 1487–1510. https://doi.org/10.1080/09640568.2012.731385

Wang, J., Sun, W., Shou, W., Wang, X., Wu, C., Chong, H.-Y., Liu, Y. and Sun, C. (2014). Integrating BIM and LiDAR for real-time construction quality control. Journal of Intelligent and Robotic Systems, 79(3–4): 417–432. https://doi.org/10.1007/s10846-014-0116-8

Wang, S.Q., Dulaimi, M.F. and Aguria, M.Y. (2004). Risk management framework for construction projects in developing countries. Construction Management and Economics, 22(3): 237–252. https://doi.org/10.1080/0144619032000124689

Wilkinson, A., Johnstone, S. and Townsend, K. (2012). Changing patterns of human resource management in construction. Construction Management and Economics, 30(7): 507–512. https://doi.org/10.1080/01446193.2012.711562

Windapo, A. and Cattell, K. (2010). A study of building contractors’ compliance with national building regulations in Cape Town. In Proceedings: Construction and Building Research Conference (COBRA) of the Royal Institution of Chartered Surveyors. Paris: Dauphine Université, 1–14. Available at: https://mafiadoc.com/a-study-of-building-contractors-compliance-with-national-building_599c1fcd1723dd09401ad6fe.html [Accessed on 20 March 2020]

Wong, P.S., Cheung, S.O. and Ho, P.K. (2005). Contractor as trust initiator in construction partnering: Prisoner’s dilemma perspective. Journal of

Construction Engineering and Management, 131(10): 1045–1053. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:10(1045)

Yang, X., Yu, M. and Zhu, F. (2020). Impact of project planning on knowledge integration in construction projects. Journal of Construction Engineering and Management, 146(7): 04020066. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001852

Yong, Y.C. and Mustaffa, N.E. (2013). Critical success factors for Malaysian construction projects: An empirical assessment. Construction Management and Economics, 31(9): 959–978. https://doi.org/10.1080/01446193.2013.828843

_____. (2012). Analysis of factors critical to construction project success in Malaysia. Engineering, Construction and Architectural Management, 19(5): 543–556. https://doi.org/10.1108/09699981211259612

Zavadskas, E.K., Vilutienė, T., Turskis, Z. and Šaparauskas, J. (2014). Multi-criteria analysis of projects’ performance in construction. Archives of Civil and Mechanical Engineering, 14(1): 114–121. https://doi.org/10.1016/j.acme.2013.07.006

Zhao, Z.Y., Shen, L.Y. and Zuo, J. (2009). Performance and strategy of Chinese contractors in the international market. Journal of Construction Engineering and Management, 135(2): 108–118. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:2(108)