Impact of External Risks on International Construction Projects Success: Evidence from Commonwealth Caribbean Islands

Main Article Content

Hernan Albeiro Parra
Alexander Zuñiga-Collazos
Luis Fernando Cruz-Caicedo

Abstract

Since risks on international construction show region to region variation, the present study investigates the impact of external risks on international construction project (ICP) success and the relationships between them, from the perspective of construction professionals working in the Commonwealth Caribbean Islands (CCI) states. After a literature review, a survey questionnaire was designed with the input of a small group of experts. An instrument was tested and then sent to the construction professionals working in the CCI. Seventy valid surveys collected were processed using the structural equation model (SEM). The results suggest that the reason why CCI is an attractive region for construction enterprises looking into developing countries is because they do not support a direct impact of external risks on the project success, contrary to the findings in other studies on developing regions. The SEM confirmed that global risks influence economic risks, while economic risks influence legal risks and, in this region, influence the social risks. Results obtained help to address the knowledge gap for the ICP risks for the Caribbean region. The study will help the firms and the professionals looking to venture into the CCI or other regions with similar characteristics to create their risk management plan.

Article Details

How to Cite
Hernan Albeiro Parra, Alexander Zuñiga-Collazos, and Luis Fernando Cruz-Caicedo. 2023. “Impact of External Risks on International Construction Projects Success: Evidence from Commonwealth Caribbean Islands”. Journal of Construction in Developing Countries 28 (1): 113-32. https://doi.org/10.21315/jcdc-07-21-0106.
Section
Articles

References

Abdul-Rahman, H., Loo, S.C. and Wang, C. (2011). Risk identification and mitigation for architectural, engineering, and construction firms operating in the Gulf region. Canadian Journal of Civil Engineering, 39(1): 55–71. https://doi.org/10.1139/l11-111

Al-Sabah, R., Menassa, C.C. and Hanna, A. (2014). Evaluating impact of construction risks in the Arabian Gulf Region from perspective of multinational architecture, engineering and construction firms. Construction Management and Economics, 32(4): 382–402. https://doi.org/10.1080/01446193.2014.884281

BCQS International (2019). Caribbean and Latin America Construction: 2018–2019 Market Trend Report. Barbados: BCQS International. Available at: https://bcqs.com/wp-content/uploads/2019/09/bcqs-construction-market-report-2019.pdf [Accessed on 22 January 2021].

Browne, M.W. and Cudeck, R. (1993). Alternate ways of assessing model fit. Sociological Methods and Research, 21(2): 230–258. https://doi.org/10.1177/0049124192021002005

CCEO (Council of Caribbean Engineering Organisations) (2002). Report on the CARICOM Construction and Installation Services Sector: Elements for Competitive Strategies. Barbados: CCEO. Available at: https://caricom.org/documents/10182-report_on_the_caricom_construction__installation_services_sector.pdf [Accessed on 22 January 2021].

Chang, T., Deng, X., Hwang, B.-G. and Zhao, X. (2019). Improving quantitative assessment of political risk in international construction projects: The case of Chinese construction companies. Journal of Construction Engineering and Management, 145(12): 04019083. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001738

_____. (2018). Political risk paths in international construction projects: Case study from Chinese construction enterprises. Advances in Civil Engineering, 3: 1–11. https://doi.org/10.1155/2018/6939828

Chua, D.K.H., Wang, Y. and Tan, W.T. (2003). Impacts of obstacles in East Asian crossborder construction. Journal of Construction Engineering and Management, 129(2): 131–141. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:2(131)

Dandage, R.V., Mantha, S.S. and Rane, S.B. (2019). Strategy development using TOWS matrix for international project risk management based on prioritization of risk categories. International Journal of Managing Projects in Business, 12(4): 1003–1029. https://doi.org/10.1108/IJMPB-07-2018-0128

_____. (2018). Ranking the risk categories in international projects using the TOPSIS method. International Journal of Managing Projects in Business, 11(2): 317–331. https://doi.org/10.1108/IJMPB-06-2017-0070

Deng, X., Low, S.P., Zhao, X. and Chang, T. (2018). Identifying micro variables contributing to political risks in international construction projects. Engineering, Construction and Architectural Management, 25(3): 317–334. https://doi.org/10.1108/ECAM-02-2017-0042

Dina, Y. (2018). UPDATE: Guide to Caribbean Law Research. New York: Hauser Global Law School Program. Available at: http://www.nyulawglobal.org/globalex/Caribbean1.html [Accessed on 24 January 2021].

Drinkwater, S., Lashley, J. and Robinson, C. (2018). Barriers to enterprise development in the Caribbean. Entrepreneurship and Regional Development, 30(9–10): 942–963. https://doi.org/10.1080/08985626.2018.1515821

El-Sayegh, S.M. (2008). Risk assessment and allocation in the UAE construction industry. International Journal of Project Management, 26(4): 431–438. https://doi.org/10.1016/j.ijproman.2007.07.004

El-Sayegh, S.M., Manjikian, S., Ibrahim, A., Abouelyousr, A. and Jabbour, R. (2021). Risk identification and assessment in sustainable construction projects in the UAE. International Journal of Construction Management, 21(4): 327–336.

https://doi.org/10.1080/15623599.2018.1536963

Eybpoosh, M., Dikmen, I. and Birgonul, M.T. (2011). Identification of risk paths in international construction projects using structural equation modeling. Journal of Construction Engineering and Management, 137(12): 1164–1175.

https://doi.org/10.1061/(ASCE)CO.1943-7862.0000382

Fornell, C. and Larcker, D.F. (1981). Evaluating structural equation models with unobservable variables and measurement error. Journal of Marketing Research, 18(1): 39–50. https://doi.org/10.2307/3151312

Gefen, D. and Straub, D. (2005). A practical guide to factorial validity using PLSgraph: Tutorial and annotated example. Communications of the Association for Information Systems, 16(1): 91–109. https://doi.org/10.17705/1CAIS.01605

Guo, S. and Hussey, D.L. (2004). Nonprobability sampling in social work research. Journal of Social Service Research, 30(3): 1–18. https://doi.org/10.1300/J079v30n03_01

Hair, J.F., Black, W.C., Babin, B.J. and Anderson, R.E. (2014). Structural equations modeling overview. In Multivariate Data Analysis. 7th Ed. Harlow: Pearson, 541–598.

Han, S.H. and Diekmann, J.E. (2001). Approaches for making risk-based go/nogo decision for international projects. Journal of Construction Engineering and Management, 127(4): 300–308. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:4(300)

Husin, S., Abdullah, A., Riza, M. and Afifuddin, M. (2018). Risk assessment of resources factor in affecting project time. Advances in Civil Engineering, 2018(8): 1–9. https://doi.org/10.1155/2018/6896141

Isa, C.M.M., Saman, H.M. and Nasir, S.R.M. (2014). Specific-factors influencing market selection decision by Malaysian construction firms into international market. Procedia – Social and Behavioral Sciences, 129: 4–10. https://doi.org/10.1016/j.sbspro.2014.03.641

Isa, C.M.M., Saman, H.M. and Preece, C.N. (2015). Determining significant factors influencing Malaysian construction business performance in international markets. Journal of Construction in Developing Countries, 20(2): 1–23.

Jha, K.N. and Devaya, M.N. (2008). Modelling the risks faced by Indian construction companies assessing international projects. Construction Management and Economics, 26(4): 337–348. https://doi.org/10.1080/01446190801953281

Joslin, R. and Müller, R. (2016). The relationship between project governance and project success. International Journal of Project Management, 34(4): 613–626. https://doi.org/10.1016/j.ijproman.2016.01.008

Lee, K.P., Lee, H.S., Park, M., Kim, D.Y. and Jung, M. (2017). Management-reserve estimation for international construction projects based on risk-informed k-NN. Journal of Management in Engineering, 33(4): 04017002. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000510

Ling, F.Y.Y. and Hoang, V.T.P. (2010). Political, economic, and legal risks faced in international projects: Case study of Vietnam. Journal of Professional Issues in Engineering Education and Practice, 136(3): 156–164. https://doi.org/10.1061/(ASCE)EI.1943-5541.0000015

Liu, J., Low, S.P. and Zhang, Q. (2018). Enterprise risk management practices of top ENR international contractors. International Journal of Construction Management, 18(5): 364–374. https://doi.org/10.1080/15623599.2017.1326299

Liu, J., Zhao, X. and Yan, P. (2016). Risk paths in international construction projects: Case study from Chinese contractors. Journal of Construction Engineering and Management, 142(6): 05016002. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001116

McIntosh, K. and McCabe, B. (2003). Risk and benefits associated with international construction-consulting joint ventures in the English-speaking Caribbean. Canadian Journal of Civil Engineering, 30(6): 1143–1152. https://doi.org/10.1139/l03-063

Mohamed, S. (2003). Performance in international construction joint ventures: Modeling perspective. Journal of Construction Engineering and Management, 129(6): 619–626. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:6(619)

Nunnally, J.C. and Bernstein, I.H. (1994). Psychometric Theory. 3rd Ed. New York: McGraw-Hill Inc.

Ozorhon, B., Arditi, D., Dikmen, I. and Birgonul, M.T. (2007). Effect of host country and project conditions in international construction joint ventures. International Journal of Project Management, 25(8): 799–806. https://doi.org/10.1016/j.ijproman.2007.05.003

Project Management Institute (PMI) (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide). 6th Ed. Newtown Square: PMI.

Siraj, N.B. and Fayek, A.R. (2019). Risk identification and common risks in construction: Literature review and content analysis. Journal of Construction Engineering and Management, 145(9): 03119004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001685

Sutton, P. (1999). Democracy in the Commonwealth Caribbean. Democratization, 6(1): 67–86. https://doi.org/10.1080/13510349908403597

Ullman, J.B. (2001). Structural equation modeling. In B.G. Tabachnick and L.S. Fidell (eds.), Using Multivariate Statistics. 6th Ed. Boston, MA: Pearson Education.

Utama, W.P., Chan, A.P.C., Gao, R. and Zahoor, H. (2018). Making international expansion decision for construction enterprises with multiple criteria: A literature review approach. International Journal of Construction Management, 18(3): 221–231. https://doi.org/10.1080/15623599.2017.1315527

Viswanathan, S.K. and Jha, K.N. (2020). Critical risk factors in international construction projects: An Indian perspective. Engineering, Construction and Architectural Management, 27(5): 1169–1190. https://doi.org/10.1108/ECAM-04-2019-0220

Viswanathan, S.K., Tripathi, K.K. and Jha, K.N. (2019). Influence of risk mitigation measures on international construction project success criteria: A survey of Indian experiences. Construction Management and Economics, 38(3): 207–222. https://doi.org/10.1080/01446193.2019.1577987

Wang, S.Q., Dulaimi, M.F. and Aguria, M.Y. (2004). Risk management framework for construction projects in developing countries. Construction Management and Economics, 22(3): 237–252. https://doi.org/10.1080/0144619032000124689

Wang, T., Tang, W., Du, L., Duffield, C.F. and Wei, Y. (2016). Relationships among risk management, partnering, and contractor capability in international EPC project delivery. Journal of Management in Engineering, 32(6): 04016017.

https://doi.org/10.1061/(ASCE)ME.1943-5479.0000459

Wilkins, J.R. (2011). Construction workers’ perceptions of health and safety training programmes. Construction Management and Economics, 29(10): 1017–1026. https://doi.org/10.1080/01446193.2011.633538

Worldatlas (2018). Caribbean countries: A list of countries that are considered to be part of the world’s Caribbean Region. Available at: https://www.worldatlas.com/articles/caribbean-countries.html [Accessed on 24 January 2021].

Xiaopeng, D. and Pheng, L.S. (2013). Understanding the critical variables affecting the level of political risks in international construction projects. KSCE Journal of Civil Engineering, 17(5): 895–907. https://doi.org/10.1007/s12205-013-0354-5

Zhang, X. (2011). Social risks for international players in the construction market: A China study. Habitat International, 35(3): 514–519. https://doi.org/10.1016/j.habitatint.2011.02.005

Zhi, H. (1995). Risk management for overseas construction projects. International Journal of Project Management, 13(4): 231–237. https://doi.org/10.1016/0263-7863(95)00015-I